TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES

Ayala Blvd., Ermita, Manila


COLLEGE OF ENGINEERING
Department of Civil Engineering

Name of Project: PROPOSED FOUR STOREY SCHOOL BUILDING Date: MARCH 27, 2018
Owner: ST. THERESE OF ROSE SCHOOL
Location: CALOOCAN CITY
MASONRY WORKS

MATERIALS AND QUANTITIES REQUIRED


ITEM TO BE
CALCULATIONS CHB CHB CEMENT SAND
ESTIMATED
(150mm) (100mm) (bags) (cu. m)
GROUND FLOOR
AREA OF WALL (sq. m) ൌ 205.536
LESS: DOORS AND WINDOWS (sq. m) ൌ 7.440
PLUS: 5% ALLOWANCE FOR WASTAGE ൌ 9.905
TOTAL NET AREA (sq. m) ൌ 208.001
EXTERIOR
WALL USING FORMULAS FOR CLASS AA (1 : 1.5)
150 mm x 200 mm x 400 mm CHB
CHB: 208.001 x 12.5 ൌ 2600.010 ;SAY 2601 PCS.
MORTAR
CEMENT: 208.001 x 2.53 ൌ 526.242 ;SAY 527
SAND: 208.001 x 0.85 ൌ 176.801 ;SAY 177
MATERIALS AND QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS CHB CHB CEMENT SAND
ESTIMATED
(150mm) (100mm) (bags) (cu. m)
GROUND FLOOR
AREA OF WALL (sq. m) ൌ 132.056
LESS: DOORS AND WINDOWS (sq. m) ൌ 23.040
PLUS: 5% ALLOWANCE FOR WASTAGE ൌ 5.451
TOTAL NET AREA (sq. m) ൌ 114.467
INTERIOR
WALL USING FORMULAS FOR CLASS AA (1 : 1.5)
100 mm x 200 mm x 400 mm CHB
CHB: 114.467 x 12.5 ൌ 1430.835 ;SAY 1431
MORTAR
CEMENT: 114.467 x 2.53 ൌ 289.601 ;SAY 290
SAND: 114.467 x 0.85 ൌ 97.297 ;SAY 98
MATERIALS AND QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS CHB CHB CEMENT SAND
ESTIMATED
(150mm) (100mm) (bags) (cu. m)
SECOND FLOOR
AREA OF WALL (sq. m) ൌ211.936
LESS: DOORS AND WINDOWS (sq. m) ൌ 35.914
PLUS: 5% ALLOWANCE FOR WASTAGE ൌ 8.801
TOTAL NET AREA (sq. m) ൌ 184.823
EXTERIOR
WALL USING FORMULAS FOR CLASS AA (1 : 1.5)
150 mm x 200 mm x 400 mm CHB
CHB: 184.823 x 12.5 ൌ 2310.289 ;SAY 2311
MORTAR
CEMENT: 184.823 x 2.53 ൌ 467.602 ;SAY 468
Prepared By: SAND: 184.823 x 0.85 ൌ 157.100 ;SAY Checked By: 158
COLA, JOHN EDEN ROSS V. ENGR. ARNOLFO ARCIBAL
SIA, ALFONSO RAPHAEL V. INSTRUCTOR
BSCE 3A
TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES
Ayala Blvd., Ermita, Manila
COLLEGE OF ENGINEERING
Department of Civil Engineering

Name of Project: PROPOSED FOUR STOREY SCHOOL BUILDING Date: MARCH 27, 2018
Owner: ST. THERESE OF ROSE SCHOOL
Location: CALOOCAN CITY
MASONRY WORKS

MATERIALS AND QUANTITIES REQUIRED


ITEM TO BE
CALCULATIONS CHB CHB CEMENT SAND
ESTIMATED
(150mm) (100mm) (bags) (cu. m)
SECOND FLOOR
AREA OF WALL (sq. m) ൌ111.762
LESS: DOORS AND WINDOWS (sq. m) ൌ 17.520
PLUS: 5% ALLOWANCE FOR WASTAGE ൌ 4.712
TOTAL NET AREA (sq. m) ൌ 98.954
INTERIOR
WALL USING FORMULAS FOR CLASS AA (1 : 1.5)
100 mm x 200 mm x 400 mm CHB
CHB: 98.954 x 12.5 ൌ 1236.926 ;SAY 1237
MORTAR
CEMENT: 98.954 x 2.53 ൌ 250.354 ;SAY 251
SAND: 98.954 x 0.85 ൌ 84.111 ;SAY 85
MATERIALS AND QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS CHB CHB CEMENT SAND
ESTIMATED
(150mm) (100mm) (bags) (cu. m)
THIRD FLOOR
AREA OF WALL (sq. m) ൌ 165.248
LESS: DOORS AND WINDOWS (sq. m) ൌ 10.080
PLUS: 5% ALLOWANCE FOR WASTAGE ൌ 7.758
TOTAL NET AREA (sq. m) ൌ 162.926
EXTERIOR
WALL USING FORMULAS FOR CLASS AA (1 : 1.5)
150 mm x 200 mm x 400 mm CHB
CHB: 162.926 x 12.5 ൌ 2036.580 ;SAY 2037
MORTAR
CEMENT: 162.926 x 2.53 ൌ 412.204 ;SAY 413
SAND: 162.926 x 0.85 ൌ 138.487 ;SAY 139
MATERIALS AND QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS CHB CHB CEMENT SAND
ESTIMATED
(150mm) (100mm) (bags) (cu. m)
THIRD FLOOR
AREA OF WALL (sq. m) ൌ 130.156
LESS: DOORS AND WINDOWS (sq. m) ൌ 28.440
PLUS: 5% ALLOWANCE FOR WASTAGE ൌ 5.086
TOTAL NET AREA (sq. m) ൌ 106.802
INTERIOR
WALL USING FORMULAS FOR CLASS AA (1 : 1.5)
100 mm x 200 mm x 400 mm CHB
CHB: 106.802 x 12.5 ൌ 1335.023 ;SAY 1336
MORTAR
CEMENT: 106.802 x 2.53 ൌ 270.209 ;SAY 271
Prepared By: SAND: 106.802 x 0.85 ൌ 90.782 ;SAY Checked By: 91
COLA, JOHN EDEN ROSS V. ENGR. ARNOLFO ARCIBAL
SIA, ALFONSO RAPHAEL V. INSTRUCTOR
BSCE 3A
TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES
Ayala Blvd., Ermita, Manila
COLLEGE OF ENGINEERING
Department of Civil Engineering

Name of Project: PROPOSED FOUR STOREY SCHOOL BUILDING Date: MARCH 27, 2018
Owner: ST. THERESE OF ROSE SCHOOL
Location: CALOOCAN CITY
MASONRY WORKS

MATERIALS AND QUANTITIES REQUIRED


ITEM TO BE
CALCULATIONS CHB CHB CEMENT SAND
ESTIMATED
(150mm) (100mm) (bags) (cu. m)
FOURTH FLOOR
AREA OF WALL (sq. m) ൌ 165.248
LESS: DOORS AND WINDOWS (sq. m) ൌ 10.080
PLUS: 5% ALLOWANCE FOR WASTAGE ൌ 7.758
TOTAL NET AREA (sq. m) ൌ 162.926
EXTERIOR
WALL USING FORMULAS FOR CLASS AA (1 : 1.5)
150 mm x 200 mm x 400 mm CHB
CHB: 162.926 x 12.5 ൌ 2036.580 ;SAY 2037
MORTAR
CEMENT: 162.926 x 2.53 ൌ 412.204 ;SAY 413
SAND: 162.926 x 0.85 ൌ 138.487 ;SAY 139
MATERIALS AND QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS CHB CHB CEMENT SAND
ESTIMATED
(150mm) (100mm) (bags) (cu. m)
FOURTH FLOOR
AREA OF WALL (sq. m) ൌ 130.156
LESS: DOORS AND WINDOWS (sq. m) ൌ 28.440
PLUS: 5% ALLOWANCE FOR WASTAGE ൌ 5.086
TOTAL NET AREA (sq. m) ൌ 106.802
INTERIOR
WALL USING FORMULAS FOR CLASS AA (1 : 1.5)
100 mm x 200 mm x 400 mm CHB
CHB: 106.802 x 12.5 ൌ 1335.023 ;SAY 1336
MORTAR
CEMENT: 106.802 x 2.53 ൌ 270.209 ;SAY 271
SAND: 106.802 x 0.85 ൌ 90.782 ;SAY 91
MATERIALS AND QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS CHB CHB CEMENT SAND
ESTIMATED
(150mm) (100mm) (bags) (cu. m)
ROOF DECK
AREA OF WALL (sq. m) ൌ 75.100
LESS: DOORS AND WINDOWS (sq. m) ൌ 0.000
PLUS: 5% ALLOWANCE FOR WASTAGE ൌ 3.755
TOTAL NET AREA (sq. m) ൌ 78.855
EXTERIOR
WALL USING FORMULAS FOR CLASS AA (1 : 1.5)
150 mm x 200 mm x 400 mm CHB
CHB: 78.855 x 12.5 ൌ 985.688 ;SAY 986
MORTAR
CEMENT: 78.855 x 2.53 ൌ 199.503 ;SAY 200
Prepared By: SAND: 78.855 x 0.85 ൌ 67.027 ;SAY Checked By: 68
COLA, JOHN EDEN ROSS V. ENGR. ARNOLFO ARCIBAL
SIA, ALFONSO RAPHAEL V. INSTRUCTOR
BSCE 3A