Name of Project: PROPOSED FOUR STOREY SCHOOL BUILDING Date: MARCH 27, 2018
Owner: ST. THERESE OF ROSE SCHOOL
Location: CALOOCAN CITY
SCAFFOLDING AND STAGING
MATERIALS ESTIMATED QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS LUMBER LUMBER LUMBER LUMBER 20d CWN NAIL
ESTIMATED
2" x 2" (bd. Ft) 2" x 3" (bd. Ft) 2" x 4" (bd. Ft) 2" x 5" (bd. Ft) (kg)
GROUND FLOOR
TOTAL LENGTH OF COLUMNS (m) ൌ64.000
COMPUTATION
VERTICAL ൌ
64.000 x 7 448.000
ൌ ;SAY 448
COLUMNS
SUPPORT 64.000
HORIZONTAL ൌ x 21 1344.000
ൌ ;SAY 1344
BRACE ൌ64.000 x 11.7 ൌ
748.800 ;SAY 749
NAILS (20d)
ൌ
TOTAL LENGTH*KILOGRAM ൌ64.000 x 0.73 ൌ46.720 ;SAY 47
MATERIALS ESTIMATED QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS LUMBER LUMBER LUMBER LUMBER 20d CWN NAIL
ESTIMATED
2" x 2" (bd. Ft) 2" x 3" (bd. Ft) 2" x 4" (bd. Ft) 2" x 5" (bd. Ft) (kg)
SECOND FLOOR
TOTAL LENGTH OF COLUMNS (m) ൌ41.600
COMPUTATION
VERTICAL ൌ
41.600 x 7 291.200
ൌ ;SAY 292
COLUMNS
SUPPORT 41.600
HORIZONTAL ൌ x 21 873.600
ൌ ;SAY 874
BRACE ൌ41.600 x 11.7 ൌ
486.720 ;SAY 487
NAILS (20d)
ൌ
TOTAL LENGTH*KILOGRAM ൌ41.600 x 0.73 ൌ30.368 ;SAY 31
MATERIALS ESTIMATED QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS LUMBER LUMBER LUMBER LUMBER 20d CWN NAIL
ESTIMATED
2" x 2" (bd. Ft) 2" x 3" (bd. Ft) 2" x 4" (bd. Ft) 2" x 5" (bd. Ft) (kg)
THIRD FLOOR
TOTAL LENGTH OF COLUMNS (m) ൌ41.600
COMPUTATION
VERTICAL ൌ
41.600 x 7 291.200
ൌ ;SAY 292
COLUMNS
SUPPORT 41.600
HORIZONTAL ൌ x 21 873.600
ൌ ;SAY 874
BRACE ൌ41.600 x 11.7 ൌ
486.720 ;SAY 487
NAILS (20d)
ൌ
TOTAL LENGTH*KILOGRAM ൌ41.600 x 0.73 ൌ30.368 ;SAY 31
MATERIALS ESTIMATED QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS LUMBER LUMBER LUMBER LUMBER 20d CWN NAIL
ESTIMATED
2" x 2" (bd. Ft) 2" x 3" (bd. Ft) 2" x 4" (bd. Ft) 2" x 5" (bd. Ft) (kg)
FOURTH FLOOR
TOTAL LENGTH OF COLUMNS (m) ൌ41.600
COMPUTATION
VERTICAL ൌ
41.600 x 7 291.200
ൌ ;SAY 292
COLUMNS
SUPPORT 41.600
HORIZONTAL ൌ x 21 873.600
ൌ ;SAY 874
BRACE ൌ41.600 x 11.7 ൌ
486.720 ;SAY 487
NAILS (20d)
ൌ
TOTAL LENGTH*KILOGRAM ൌ41.600 x 0.73 ൌ30.368 ;SAY 31
Name of Project: PROPOSED FOUR STOREY SCHOOL BUILDING Date: MARCH 27, 2018
Owner: ST. THERESE OF ROSE SCHOOL
Location: CALOOCAN CITY
SCAFFOLDING AND STAGING
MATERIALS ESTIMATED QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS LUMBER LUMBER LUMBER LUMBER 20d CWN NAIL
ESTIMATED
2" x 2" (bd. Ft) 2" x 3" (bd. Ft) 2" x 4" (bd. Ft) 2" x 5" (bd. Ft) (kg)
ROOF DECK
TOTAL LENGTH OF COLUMNS (m) ൌ13.000
COMPUTATION
VERTICAL ൌ
13.000 x 7 ൌ91.000 ;SAY 91
COLUMNS
SUPPORT 13.000
HORIZONTAL ൌ x 21 273.000
ൌ ;SAY 273
BRACE ൌ13.000 x 11.7 ൌ
152.100 ;SAY 153
NAILS (20d)
ൌ
TOTAL LENGTH*KILOGRAM ൌ13.000 x 0.73 ൌ9.490 ;SAY 10
MATERIALS ESTIMATED QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS LUMBER LUMBER LUMBER LUMBER 20d CWN NAIL
ESTIMATED
2" x 2" (bd. Ft) 2" x 3" (bd. Ft) 2" x 4" (bd. Ft) 2" x 5" (bd. Ft) (kg)
FOOTING TIE BEAMS
TOTAL LENGTH OF BEAMS (m) ൌ 80.650
COMPUTATION
VERTICAL ൌ
80.650 x 6 483.900
ൌ ;SAY 484
BEAMS
SUPPORT
80.650
HORIZONTAL ൌ x 4.7 379.055
ൌ ;SAY 380
NAILS (20d)
ൌ
TOTAL LENGTH*KILOGRAM ൌ80.650 x 0.73 ൌ58.875 ;SAY 59
MATERIALS ESTIMATED QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS LUMBER LUMBER LUMBER LUMBER 20d CWN NAIL
ESTIMATED
2" x 2" (bd. Ft) 2" x 3" (bd. Ft) 2" x 4" (bd. Ft) 2" x 5" (bd. Ft) (kg)
GROUND FLOOR
TOTAL LENGTH OF BEAMS (m) ൌ47.190
COMPUTATION
VERTICAL ൌ
47.190 x 6 283.140
ൌ ;SAY 284
BEAMS
SUPPORT
47.190
HORIZONTAL ൌ x 4.7 221.793
ൌ ;SAY 222
NAILS (20d)
ൌ
TOTAL LENGTH*KILOGRAM ൌ47.190 x 0.73 ൌ34.449 ;SAY 35
MATERIALS ESTIMATED QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS LUMBER LUMBER LUMBER LUMBER 20d CWN NAIL
ESTIMATED
2" x 2" (bd. Ft) 2" x 3" (bd. Ft) 2" x 4" (bd. Ft) 2" x 5" (bd. Ft) (kg)
SECOND FLOOR
TOTAL LENGTH OF BEAMS (m) ൌ47.190
COMPUTATION
VERTICAL ൌ
47.190 x 6 283.140
ൌ ;SAY 284
BEAMS
SUPPORT
47.190
HORIZONTAL ൌ x 4.7 221.793
ൌ ;SAY 222
NAILS (20d)
ൌ
TOTAL LENGTH*KILOGRAM ൌ47.190 x 0.73 ൌ34.449 ;SAY 35
Name of Project: PROPOSED FOUR STOREY SCHOOL BUILDING Date: MARCH 27, 2018
Owner: ST. THERESE OF ROSE SCHOOL
Location: CALOOCAN CITY
SCAFFOLDING AND STAGING
MATERIALS ESTIMATED QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS LUMBER LUMBER LUMBER LUMBER 20d CWN NAIL
ESTIMATED
2" x 2" (bd. Ft) 2" x 3" (bd. Ft) 2" x 4" (bd. Ft) 2" x 5" (bd. Ft) (kg)
THIRD FLOOR
TOTAL LENGTH OF BEAMS (m) ൌ47.190
COMPUTATION
VERTICAL ൌ
47.190 x 6 283.140
ൌ ;SAY 284
BEAMS
SUPPORT
47.190
HORIZONTAL ൌ x 4.7 221.793
ൌ ;SAY 222
NAILS (20d)
ൌ
TOTAL LENGTH*KILOGRAM ൌ47.190 x 0.73 ൌ34.449 ;SAY 35
MATERIALS ESTIMATED QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS LUMBER LUMBER LUMBER LUMBER 20d CWN NAIL
ESTIMATED
2" x 2" (bd. Ft) 2" x 3" (bd. Ft) 2" x 4" (bd. Ft) 2" x 5" (bd. Ft) (kg)
FOURTH FLOOR
TOTAL LENGTH OF BEAMS (m) ൌ35.690
COMPUTATION
VERTICAL ൌ
35.690 x 6 214.140
ൌ ;SAY 215
BEAMS
SUPPORT
35.690
HORIZONTAL ൌ x 4.7 167.743
ൌ ;SAY 168
NAILS (20d)
ൌ
TOTAL LENGTH*KILOGRAM ൌ35.690 x 0.73 ൌ26.054 ;SAY 27
MATERIALS ESTIMATED QUANTITIES REQUIRED
ITEM TO BE
CALCULATIONS LUMBER LUMBER LUMBER LUMBER
ESTIMATED
2" x 2" (bd. Ft) 2" x 3" (bd. Ft) 2" x 4" (bd. Ft) 2" x 5" (bd. Ft)
FOUNDATION
TOTAL AREA OF SLABS (sq. m) ൌ284.100
SLABS
COMPUTATION
284.100
ൌ x 9.100 2585.310
ൌ ;SAY 2586
SECOND FLOOR
TOTAL AREA OF SLABS (sq. m) ൌ118.720
SLABS
COMPUTATION
118.720
ൌ x 9.100 1080.352
ൌ ;SAY 1081
THIRD FLOOR
TOTAL AREA OF SLABS (sq. m) ൌ 118.720
SLABS
COMPUTATION
118.720
ൌ x 9.100 1080.352
ൌ ;SAY 1081
FOURTH FLOOR
TOTAL AREA OF SLABS (sq. m) ൌ118.720
SLABS
COMPUTATION
118.720
ൌ x 9.100 1080.352
ൌ ;SAY 1081
ROOF DECK
TOTAL AREA OF SLABS (sq. m) ൌ111.220
SLABS
COMPUTATION
111.220
ൌ x 9.100 1012.102
ൌ ;SAY 1013