Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

PRICE EST NO:2020/125343

"Details of cost for 1 cum.


Material

Stone for masonry work


1157 cum 1.0 1100.00 1100.00
Carriage

Carriage of Soling stone & masonry stone


2215 cum 1.0 122.08 122.08
Labour

0125 Mason (for plain stone work) 2nd class Day 0.35 679.00 237.65

0114 Beldar Day 0.35 558.00 195.30

TOTAL 1655.03

Add Water Charges @ 1% 16.55

TOTAL 1671.58

Add CPOH @ 15% 250.74

TOTAL 1922.32

Cost of 1.0 cum 1922.32

Cost per cum 1922.32

Say 1922.3

Cost index 35.59 % 684.15

Total with Cost index 2606.45

Say 2606.45

12 Specification Code: od1770185/2022_2023

od1770185/2022_2023 :DR PACKING Under foundation - Dry stone packing under foundation using
departmental rubble including conveyance of material and labour charges etc. complete as per direction of
departmental officers at site.

Code Description Unit Quantity Rate Amount

printed on 02-11-2022 17:03:52 page 14


PRICE EST NO:2020/125343

0125 Mason (for plain stone work) 2nd class Day 0.35000 679.00 237.65

0114 Beldar Day 0.35000 558.00 195.30

TOTAL 432.95

cost for one cum 432.95

say 432.95

Add Water Charges @ 1.0% 4.32

Add CPOH @ 15.0% 65.59

Cost index 35.59 % 178.97

Total with Cost index 681.84

Say 681.84

printed on 02-11-2022 17:03:52 page 15