DRYDOCK/LAY OFF DEFECT LIST


R.S SUB WORK DETAILS QTY DATE OF DATE OF REMARKS
NO. ITM COMMN COMPLE
CE TION
D 001 – GENERAL SERVICES, DOCKING
D 001 AS PER CSH REQUIREMENT THE ___ 02.08.13 F.W TANK & P/S F.O TANK PR.TEST COMPLETED.
BELOW MENTIONED TANKS HAS TO STBD F.O TANK & BILGE TANK PR.TST PENDING
BE PRESSURE TESTED AND SURVEYED.
PRIOR TO THAT ALL TANKS
CLEANING ,WASHING AND GAS
FREEING HAS TO BE DONE. ALL TANKS
MANHOLE COVER GASKETS TO BE
RENEWED.
D 001 DISPOSE SAFELY 400 LTRS OF DIRTY AWAITING CERTIFICATE
RS07 OIL & ISSUE CERTIFICATE
D 004 – PAINTING
D 004 FOLLOWING JOBS TO CARRIED OUT ___
ON UNDERWATER HULL AREA
D 002 – HULL REPAIRS
D 002 BRIDGE WIND GLASS WIPER BLADES 03 17.07.13 IN PROGRESS
RS 01 ARE IN POOR CONDITION. SAME TO NOS
BE RENEWED.
D 002 BRIDGE PILOT CHAIR HIGHT 02 JOB DONE BY SHIP STAFF
RS 03 ADJUSTMENT TO BE REPAIRED NOS
D 002 BRIDGE WATER TIGHT DOOR OPPEN 01 NOT ATTENDED
RS 04 POSITION STOPPER DEFECTIVE. SAME NOS
TO BE REPLACED/REPAIRED
D 002 BRIDGE WIND GLASS WATER 03 CANCELLED. JOB DONE BY SHIP STAFF
RS 05 SPRAYER/WASHER LINE IS CHOCKED, NOS
SAME TO BE CLEARED.

D 002 PANTRY ROOM DOOR HANDLE IS 01 NOT ATTENDED


RS 06 DEFECTVE SAME TO BE
RENEWED/REPAIRED
D 002 PASSENGER SEAT TRAY ARE BROKEN, 05 IN PROGRESS.
RS 07 SAME TO BE REPLACED NOS SAMPLE TAKEN
D 002 PASSENGER SEAT COVER STRAPS ARE 12 NOT ATTENDED
RS 08 DEFECTIVE, SAME TO BE RENEWED NOS
D 002 ALL WATER TIGHT DOORS/HATCHES 12 29.08.13 IN PROGRESS
RS 10 RUBBER BEEDING TO BE RENEWED NOS
D 002 PORT SIDE VIP CABIN FWD WINDOW 01 17.07.13 IN PROGRESS
RS 11 GLASS IS BROKEN, SAME TO BE NOS
RENEWED.
D 002 ON PORT SIDE MAIN DECK 01 NO. 01 NOT ATTENDED
RS 12 MOB RESCUE LADDER CLAMP IS NO
BROKEN, SAME TO BE REPLACED
D 002 ON MAIN DECK STBD FUEL OIL 01 NOT ATTENDED
RS 13 AIRVENT WIRE MESH IS DAMAGED, NOS
SAME TO BE RENEWED
D 002 PORTABLE FIRE EXTINGUSHERS 07 15.07.13 05.08.13 4 NOS.FOAM EXTINGUISHERS SUPPLIED WITH
RS 17 ANNUAL SERVICES TO BE CARRIED NOS REFILLS .
OUT, SERVICE DUE ON SEP’2013 (04 03 NOS DCP EXTINGUSHERS SERVICED ON 05.08.13 BY
NOS. FOAM TYPE, MAKE: PALVO, SHM
CAPACITY:09 LTRS. 03 NOS. DCP TYPE,
MAKE:SUPREMAX, CAPACITY:5 KGS)
D 002 P/S F.O TANK AIRVENTS WIREMESH & 02 NOT ATTENDED
RS 18 BILGE HOLDING TANK AIR VENT MESH NO
FRAME BADLY CORRODED.
D 002 ANCHOR CHAIN TO BE IN PROGRESS
RS 19 RANGED/CALIBRATED
D 002 AFT VOID SPACE STBD SIDE 2 NOS NOT ATTENDED
RS 20 BRACKETS MISSING/ 2 NOS BRACKETS
DENTED TO BE REPLACED
D 002 ALL OVER BOARD DISCHARGE V/V’S NOT ATTENDED
RS 21 MOUTH ON P&S SIDE TO BE BUILT UP
WITH SUITABLE METERIAL
D 002 PROCURE & SUPPLY OF ANCHOR ROPE IN PROGRESS
RS 22 NYLONE 3 STRAND, 22 MM
DIAMETER, 75 MTRS LENGTH,
BREAKING STRENTH NOT LESS THAN
10 TONNES ( WITH CERTIFICATE )
D 002 NEWLY SUPPLIED 4 NOS 9 LTRS FOAM NOT ATTENDED
RS 23 TYPE FIRE EXTINGUSHERS TO BE RE-
POSITIONED WITH SUITABLE FITTINGS
IN ENGINE ROOM
D 002 STBD TOILET WASH BASIN DRANAGE NOT ATTENDED
RS 24 PIPE DAMAGED, SAME TO BE
REPLACED
R 001 – RADIO/NAVIGATION
R 001 BRIDGE VHF D.C LIGHT(RADIO 01 15.07.13 IN PROGRESS
RS 01 SURVEYOR RECOMONDATION) IS NO SAMPLE TAKEN
DEFECTIVE, SAME TO BE
RENEWED/REPAIRED
R001 SAT-C, UNABLE TO STORE MESSAGES. 01 IN PROGRESS
RS 02 FLOPPY TO BE RENEWED. NO
R 001 MF/HF TRANSMISSION & RECEPTION 01 05.09.13 IN PROGRESS
RS 03 FREQUENTLY CUTTING OFF, REQUIRED NO
SHORE BASE MAINTENANCE.
R 001 EPIRB ANNUAL SERVICE TO BE 01 NOT ATTENDED
RS 04 CARRIED OUT. (MAKE:KANNAD 406 NO
PRO, LAST SERVICE DONE ON
06.07.2011)
R 001 SART ANNUAL SERVICE TO BE 01 NOT ATTENDED
RS 05 CARRIED OUT. (MAKE:ACR- NO
PATHFINDER, LAST SERVICE DONE ON
13.07.2011)
R 001 NUC. LOWER LIGHT UNIT BASE IS 01 25.0813 IN PROGRESS
RS 06 BROKEN ON THE MAST, SAME TO BE NO
REPLACED.

R 001 STANDARD MAGNETIC COMPASS TO 01 NOT ATTENDED


RS 07 BE CALIBERATED.( MAKE: CASSENS & NO
PLATH, S.NO:G140002 )
R 001 GYRO COMPASS TO BE SERVICED, DUE 01 NOT ATTENDED
RS 08 TO FREQUENT FAILUR (MAKE: SIMRAD NO
AR 78 ).
R 001 SAT-C PRINTER NOT WORKING 01 NOT ATTENDED
RS 09 PROPERLY, SAME TOBE SERVICED NO
( MAKE:FURUNO- PP 510 )
R 001 AIS ANNUAL SERVICING/TEST TO BE 01 NOT ATTENDED
RS 10 CARRIED OUT. MAKE SAMYUNG – SI30 NO
E 001 – MACHINERY REPAIRS
E 001 BOTH P&S PROPELLER SHAFTS TO BE 15.07.13 IN PROGRESS
RS 03 REMOVED, TRUENESS CHECKING OF
SHAFTS, CRACK DETECTION OF SHAFTS
CONE TO BE CARRIED OUT, PRESENT
FOR TAIL SHAFT SURVEY. STERN
BUSHES TO BE INSPECTED, BOTH P&S
PROPELLERS TO BE REPLACED WITH
SPARE RECONDITIONED ONE’S. WHILE
BOXING BACK BOTH SHAFT SEAL TO
BE RENEWED & PROPER ALIGNMENT
TO BE DONE. AFRET COMLETION OF
WORK A SATISFACTORY SEA TRIAL TO
BE CARRIED OUT.
E 001 A/E NO:2 PORT, WITH ATTACHMENTS 26.08.13 IN PROGRESS
RS 05 & COOLERS TO BE OVERHAULED,
PRESENT FOR SURVEY & TO BE BOXED
BACK. A SATISFACTORY TRIAL RUN TO
BE SHOWN AFTER COMPLETION OF
WORK. MAKE- CUMMINS, MODEL-
4B3.9D(M)
E 001 A/E NO:1 STBD, ALL UNITS INJECTORS NOT ATTENDED
RS 06 TO BE REMOVED OVERHAULED,
PRESSURE TESTED & TO BE FITTED
BACK. A SATISFACTORY TRIAL RUN TO
BE SHOWN AFTER COMPLETION OF
WORK. MAKE-CUMMINS, MODEL-
4B3.9D(M).

E 001 06 SEA WATER HYDROPHORE SYSTEM 17.07.13 IN PROGRESS


RS 07 NOT FUNCTIONING, P/P NOT TAKING
SUCTION. SUCTION PIPE LINE MAY
HAVE TO BE MODIFIDE, AT MAIN
SEACHEST CONNECTION PIPE TO BE
REPOSITIONED. FAULT TO TRACE OUT
& RECTIFIED.
E 001 01 SME EXHAUST PIPE TRUNK 02.08.13 IN PROGRESS
RS 07 CONNECTED TO SHIPSIDE SHELL
PLATING BADLY CORRODED AND
HOLD. SAME TO BE RENEWED WITH
LAGGING. BEND PIPE DIA: 55 CM, L:30
CM.
E 001 02 A/E:2 PORT JACKET WATER 05.09.13 IN PROGRESS
RS 07 EXPANSION TANK BADLY CORRODED
& HOLD, SAME TO BE RENEWED AS
PER SAMPLE. APPRX DIMENSION- 31
CM (H), 13.5 CM(B), 27 CM(L).
E 001 03 TO FABRICATE & FIT, PME STARTING NOT ATTENDED
RS 07 BATTERY BOX TOP END COVER
ALUMINIUM PLATE. DIMENSION- 65
CM(L), 55 CM(B), 3 MM THICK.
E 001 08 A/E DIESEL OIL TRANSFER P/P TO BE 27.08.13 IN PROGRESS
RS 07 OVERHAULD

E 001 02 BOTH P&S PROPALLERS TO BE RE- 12.07.13 IN PROGRESS


RS 08 CONDITIONED WITH CLASS
CERTIFICATE
E 001 02 VOID SPACE SULLAGE TANK FLEXIBLE 12.08.13 IN PROGRESS
RS 09 HOSES TO BE RE-PLACED WITH S.S
PIPE.
E 001 03 VOID SPACE NO.2 SEWAGE LINE 12.08.13 IN PROGRESS
RS 09 FEXIBLE HOSE TO BE REPLACED WITH
S.S PIPES.
E 001 04 SEA WATER HYDROPHORE P/P 02.08.13 IN PROGRESS
RS 09 SUCTION PIPE CORRODED TO BE
RENEWED.
E 001 06 A/E-1 STBD F/W COOLER S/W INLET 02.08.13 IN PROGRESS
RS 09 PIPE CORRODED- TO BE RENEWED

E 001 03 SEWAGE STANDERD DISCHARGE IN PROGRESS


RS 10 CONNECTION TO BE FABRICATE &
SUPPLY.
E 001 SME LOAD SHOWS HIGHER VALUES NOT ATTENDED
RS 11 WHEN COMPARING WITH PME FOR
THE SAME RPM THAN NOMINAL
VALUES- SAME TO BE TRACE OUT &
RECTIFIED
E 001 02 TO PROCURE, SUPPLY & FIT 01 NO A/E 27.08.13 IN PROGRESS
RS 12 F/O TRANSFER P/P

E 002 – ELECTRICAL/ELECTRONICS/INSTRUMENTATION
E 002 FOLLOWING MAIN SWITCH
RS 01 BOARD/PANEL BOARD METERS, M/E
AND A/E GUAGES TO BE
CALIBERATED. IF FOUND DEFECTIVE
TO BE PROCURED & REPLACED
09 K.W METER 03 15.07.13 IN PROGRESS
NO
11 M/E F/O PR.GUAGES 04 15.07.13 IN PROGRESS
NO
15 A/E TACHO METERS 02 15.07.13 IN PROGRESS
NO
16 A/E THERMOMETERS 02 15.07.13 IN PROGRESS
NO
17 A/E BATTERY VOLT METERS 02 15.07.13 IN PROGRESS
NO
E 002 PASSENGER HALL PORT SIDE SPLIT A/C NOT ATTENDED
RS 02 UNIT TRIPS FREQUENTLY, FAULT TO
TRACE OUT & RECTIFY
E 002 E/R & STRG COMP. TELEPHONE 12.08.13 IN PROGRESS
RS 04 SYSTEM REVOLVING LIGHTS
DEFECTIVE – SAME TO BE RENEWED.
E 002 TO PROCURE,SUPPLY & FIT 01 NO NOT ATTENDED
RS 05 TUBE LIGHT IN STRG COMP.
E 002 TO PROCURE & SUPPLY 02 NOS NOT ATTENDED
RS 06 SMOKE DETECTERS WITH BASE
(NOTIFIER- FSP 851) FOR THE FIRE
ALARM SYSTEM.