REFURBISHMENT OF
GALVANISED PIPES TO uPVC
PIPES
ZAMDELA TOWNSHIP
Contract No.: MLM 22/2021/22
Report 16/09/2022
Client
METSIMAHOLO LOCAL MUNICIPALITY
Consultant
HLANGANANI CONSULTING
ENGINEERS AND PROJECT MANAGERS
Main Contractor
LANCE MANAGEMENT SERVICES
1. Progress
2. Financial Report
3. Labour Report
Adult Adult Youth Youth Disable
Category Total
Male Female Male Female d
Site Agent 1 1
Safety Officer 1 1
Foremen 2 2
CLO 1 1
Operators 1 1
Page 2|6
SHE Rep 1 1
Site Assisntant 1 1
General Labour 12 6 18
TOTAL 1 1 17 9 0 26
Day( Comment
Description Start Finish
s) s
Existing water pipe line breakage 22/07/2022 22/07/2022 1 Fixed
Cable damage near stand no.209 05/08/2022 05/08/2022 1 Fixed
TLB Breakdown 16/08/2022 16/08/2022 1 Replaced
Resident denied the Contractor from
17/08/2022 24/08/2022 6 Resolved
removing paving from outside her yard.
Wacker compactor breakdown 22/08/2022 22/08/2022 1 Fixed
Moving mobile trailer using TLB (Parked at
23/08/2022 23/08/2022 1 Resolved
proposed new pipeline path.)
Pipe burst near stand.no 105 23/08/2022 23/08/2022 1 Resolved
TLB Breakdown 15/09/2022 15/09/2022 1 Resolved
Page 3|6
5.2. Register of Equipment on Site
Equipment/Plant Quantity
Concrete cutter 1
Wacker 1
TLB 1
Bakkie 1
6. Information Required
Date Date
Description Requested Responded Comment
Culvert encountered across the road, 27/07/2022 - Pending
awaiting instruction of how to proceed.
Existing sewer layout drawings 22/08/2022 24/08/2022 23/08/2022
Site Financial
Date
Instructi Description Remarks implication
Received
on no. ?
To supply new rates for the fittings that
1 14/06/2022 Complied N
match the pipes on site.
Non approval to commence with works.
RE should be provided with the PPE
2 07/07/2022 according to BOQ & specifications. RE Complied N
should be given monthly airtime, as per
BOQ or specifications.
No excavation will be done before
3 14/07/2022 Complied N
approval by the Project Engineer.
The Contractor should provide Shelters.
The Contractor should install pipe not less
than 80m daily. The Contractor should
write daily site diary. The Contractor
should conduct density tests every 35m.
4 21/07/2022 Complied N
All the procument material needs to be
taken from water works to site camp.
Please release the site foremen because
because he does not take orders from Site
Employer’s Representative.
Contractor to send the Consultant new
5 12/08/2022 Complied N
rates for fittings.
8. Pictures
Page 4|6
8.3. Backfilling using Labour Intensive Method
Page 5|6
8.6. TEE – Connections (75x75mm)
Page 6|6