Professional Documents
Culture Documents
From Green Field Site To Block Cave Mine - Results of Northparke's Drill and Blast Design Process
From Green Field Site To Block Cave Mine - Results of Northparke's Drill and Blast Design Process
From Green Field Site To Block Cave Mine - Results of Northparke's Drill and Blast Design Process
ABSTRACT This paper will provide those developing new drill and blast projects
with an inside view of how one small technical team solved many design
The green field site is one that has no history of mining and as such it challenges to successfully construct Australia’s first block cave mine
presents the designer with a blank canvas, on which any number of drill under strict quality controls and ambitious time constraints.
and blasting options can be drafted. No matter which mining method is
selected all technology and experience will need to be acquired from
outside sources, applied quickly and produce the right results. INTRODUCTION
North Limited, in joint venture with the Sumitomo Group (20 per
cent), have developed Australia’s first block cave mine at Northparkes in The E26 orebody was found in 1976. Its low-grade large volume
New South Wales, Australia. This innovative and large scale mining properties put its owners in a quandary as to the most effective
project was taken from a green field site in November 1993 to a fully means of exploiting the resource. Traditional Australian methods
commissioned block cave mine in December 1997. Northparkes’ like open cut and open stope mining provided viable extraction
Endeavour 26 mine is now producing at a rate of 3.9Mt per annum from a options but did not exploit the large volumes of low-grade ore.
27Mt ore block.
Prior to 1993 no history of mining activity existed at Northparkes. The
From 1984 mining feasibility studies recognised the caving
rock had never been blasted and many questions were raised about how it potential of ore in the gypsum leached zone which as illustrated
would behave. While it was clear that the Endeavour 26 (E26) orebody in Figure 1 ends 200 m below the surface. In 1986 a proposal to
contained geotechnical properties appropriate to block caving, the open cut this 200 m deep ore zone was examined but the shape of
blasting methods required to establish a block cave mine had never been the orebody left a large portion of the low-grade ore in situ.
used in Australia and no designs were available. The joint venture
partners had no prior experience with block caving and it was
From 1990 to 1992 a total underground mining option was
immediately apparent that this blasting technology would have to be examined and in this plan the 200 m gypsum leached zone and a
acquired from foreign sources and applied to the unique local conditions. 40 m crown was to be caved into a void generated by open stope
Conceptual designs for the block cave drill and blast were first drafted mining below.
in 1994, first issued for drilling in December 1995 and first blasted in In January 1993 new geotechnical information revealed that
January 1996. 470 km of drill metres and four million tonnes of rock the rock would cave down to 330 m below the surface, 130 m
were blasted to complete the undercutting project by September 1997.
below the gypsum leeched zone. In May the design was revised
to 70 vertical metres of drill and blast firing into inclined
1. Northparkes Mines, PO Box 995, Parkes NSW 2870. extraction drives as illustrated in Figure 1 (Wulff, 1993).
From August 1993 to April 1994 this small technical team was
employed by the manager mining. It was led by a planning
manager and senior geologist. The planning manager took
responsibility for development design and ground support. Two
geologists were employed under the senior geologist to complete
orebody modelling. Rock mass analysis was undertaken by one
geotechnical engineer. A surveyor experienced in mine design
and drafting was employed to create the first construction
drawings and a mining engineer was employed with
responsibility for all drill and blast design. This small design
team was supported by four dedicated technicians providing
drafting and geology services (Figure 4).
Consultants
Given the limited experience of this team leading consultants
were employed in each core area of the mine design. They
provided an experience base to the team and valuable input to the
design process (Figure 4).
International block cave mining consultant, Dr Dennis FIG 4 - Mine design team.
Laubscher, was employed from 1993 to assist them in
establishing the principles on which a conceptual drill and blast
Guilfoyle and Associates were consulted to vet the upper and
design was completed. Unlike other block cave mines which had
lower undercut designs in the light of their drill and blast design
developed after long histories of mining soft secondary
experience. Karl Guilfoyle specialised in practical blasting and
(weathered) ores or surface open cuts the decision to block cave
was able to provide detailed design advice down to the detonator
the Endeavour 26 orebody in primary (unweatherred) ore was
and explosive selection.
made from core data.
The Julius Kruttschnitt Mineral Research Centre (JKMRC)
Dr Dennis Laubscher was able to compare the rock mass
were increasingly involved in block cave mining and had
properties at Northparkes with block caves found elsewhere in
established links with El Teniente and Andina mines out of their
the world and guide the Northparkes design team towards a mine
Santiago office in Chile. The experience of G Chitombo and A
concept that was appropriate to the local conditions. Laubscher’s
Tunstall was drawn upon to vet drill and blast designs in the light
geotechnical analysis and models convinced the design team that
of their Chilean work.
a 42 m high double undercut was sufficient to break up the high
strength rock at Northparkes. From the outset Northparkes were strongly focused on
minimising damage to their final mine structures. The JKMRC’s
Blasting and Reinforcement Technology (BART) project was Simple MRMR rock mass data was compiled on the mines
sponsored by Northparkes and through the JKMRC support was visited by the technical team and compared to their drill and blast
provided for blasting studies to minimise damage to the designs and then related to Northparkes’ ground conditions. In a
extraction level and its honey comb of drawbells and pillars surprising outcome the variety of caving drill and blast designs
(Vink, 1995). locally and internationally fell within a narrow band of
The short-term intensive construction phase of a block cave parameters that could be defined by some simple geometric
mine lends itself to the out source of contract work forces in all guidelines and rules of thumb. As for many other mines the
aspects that are not part of its long-term operation. Conceptual simple spacing and burden rule described by Persson, Holmberg
drilling and blast design is no exception. and Lee 1994, held true for all Northparke’s drill and blast
designs.
Blastability Formula: 1<S/B<1.3
During the design phase much information about the blasting S = hole spacing
conditions in the underground mine was coming to light from the
decline development. The rock was not particularly hard at 110 B = hole burden
MPa average strength and jumbo drill penetration rates were high Differences in Northparkes’ rock mass from other mine sites
compared with other sites. The rock was elastic and shot very resulted in some fine tuning of selected drill and blast designs
well, rounds pulling to the end with little measurable butt within these parameters rather than radical changes.
(Chitombo and Tunstall, 1995). The rock was quite
homogeneous and ground conditions varied little in the decline. Opening patterns
There was virtually no water in the decline and backs support
was limited to two rows of seven hollow groutable bolts every 3 No shots had ever been fired at Northparkes so the first drill and
m round. Development mining averaged 65.2 m/wk verses a blast patterns were conservative designs. Upper undercut rings
contract rate of 58 m/wk from March to June 1994, in a 5 x 5.5 were first fired as single rings of 16 holes on 1.6 m burdens in
m heading. Hoist shaft sinking averaged 19.7 m/wk verses a open blast conditions (Figures 5 and 6). Consistent with the
contract rate of 16.3 m from April to June 1994. These rates of blastability expectation of Northparkes rock these conservative
advance continued and this evidence built a picture of a rock type burdens were opened up to 2.5 m. The 16 hole patterns were
that was easily blasted. reduced to 14 and single ring firings in open conditions increased
Diamond drill hole geotechnical information from the ore- to double rings in choked. Increased confinement in choked
body showed that it was far more jointed and gypsum veined conditions was causing blast damage to the top of the next ring.
than the decline, and could be expected to fracture more easily In July 1996 the emulsion product was then lowered from 1.2 to
for that reason. The design team were not disappointed and each 1 density (ANFO is equivalent to 1). The stope was loaded open
time development headings entered the vicinity of the ore-body and an Optec survey of the void proved the blast had pulled to its
they struck jointed and gypsum veined rock. Bearing in mind the design without damaging the next ring in choked conditions.
level of technical risk associated with designing a block cave At each step blasts were tested for success by measuring
mine from core data and the huge amount of capital funds damage to the brow, the next ring and by loading open the stope
committed, this prolific jointing and veining came as a great for survey (Figures 5 and 6).
relief after the excellent ground conditions encountered in the
main decline.
Quality assurance
All drilling and loading activity was contracted out to Brandrill
Limited and ICI were subcontracted to charge. Quality
Assurance (QA) of the final product was dependent on accurate
drilling and precise blasting of the principals designs. The
contracts provided for the introduction of a full quality assurance
system and in April 1997 Brandrill became quality assurance
accredited at the Northparkes minesite.
Flow charts
Quality control of the drill and blast operation commenced with a
detailed flowsheet of steps in the process, starting with design
and ending with review of the blasted product (Figure 7). Any
variation from design led to an in specification or out of
specification decision that was controlled by standards consistent
with the contract and acceptable to the principal. For example a
drill hole measuring three per cent deviation from the contract
specification of ±2 per cent was not redrilled if the principal was
satisfied that it could be fired to achieve the design result.
In the drill and blast flow chart acceptable design from the
principal was issued to the driller by the contract foreman who
composed the driller’s QA checklist. From this point the driller
received the check sheet and the shift boss ensured that the
driller’s flow chart was followed.
All flowsheets were first composed by the principals engineers
in very close consultation with project management and the
contractors engineers. End products, like the driller’s QA sheet
(Figure 8) are practical working documents that were copied onto
water proof paper for use on the job. Operators filled out these
sheets on the drill rig and returned them to the shift boss for
filing to ensure a full record for future reference. FIG 7 - Drill and blast flowchart.
The flow sheet technique provides a tool to set up quality work. In this circumstance the principal and contractor had a
control for any drill and blast activity. Work practice was defined close working relationship in which deviations to the plan were
in the flow sheets (Figure 9) and the way in which job was done reported by the contractor and a course of action was preferably
became the way it was defined on the sheet. agreed or enforced to the contract specification if required.
This QA did not replace traditional management structures like
Contract conscience shift boss, foreman, site manager and contract manager.
The responsibility for measuring and reporting out of
Blast investigation
specification drill and blast results as Non-Conformance Reports
(NCR) was placed with the contractor. Once established this QA The results of each blast were inspected for fragmentation, signs
system operated as a conscience so that out of specification work of misfired holes, unblasted explosives and damage. This was the
was picked up, not by the principal, but by the contractor. The last step in the drill and blast quality assurance system.
principal is not immune from QA obligations and minimum
standards were applied to the quality of their drill and blast Audits
designs and project management.
This system required careful introduction and auditing but Audits were carried out on a periodic basis or when quality
once established the principal and contractors line management control problems became apparent. In such cases the QA
were freed from some contract enforcement for more productive standards were tested on the job by measuring the results and
taking operators through their QA sheets.
The slot fired was 190 m long. The concern with such a tall-
narrow-long slot was that it could loose height and require
recovering or freeze portions of the retreating undercut rings
before they were established. To avert the problem it was loaded
empty and surveyed with the Optec CMS. Survey results showed
full height was achieved for the entire slot. No reslot was
required.
A key to success in such a situation lays in locating the raise in
a position which allows access for firing from both sides. In this
case the raise can be stripped out piece meal to full height from
the south side and then brought to vertical on the North by stand
up stripping. Failure to pull the full height of the raise strip is not
the disaster it represents in a raise which has only end access for
example. This system of stripping open slot raises was used with
a 100 per cent success rate at Northparkes. No reslots and no
remedial drilling was required. FIG 12 - Typical stress overcut panel.
Upper undercut - centre access drive slot Even at drill and charge densities approaching cut-off slot
levels blasting success could only consistently be achieved by
Of primary importance was to ensure full undercut of the
firing two rings at a time. In addition it was essential to send a
orebody. No pillars could be left behind since they would form a
remote unit across the last fired rings to remove blasted rock an
path for stress concentration from the cave to the extraction level
provide void space for the next firing. QA requirements were
pillars. Initially the upper undercut was loaded open to check for
made to ensure that the loaders only stopped mucking when the
blast performance, but as the hydraulic radius increased the
cut off slot rill was sighted. This had also been the experience of
brows were closed for safety reasons.
other mines.
Once the upper undercut passed a hydraulic radius of 23 the
In block caving it is not sufficient to simply wreck the panels.
backs fell in and blasting was carried out in choked conditions.
They must be removed so that the extraction level pillars are not
This first caving event was confirmed by measurement of open
loaded by stress concentrating pillars. Northparkes learnt through
geotechnical monitoring holes. It must be stressed however that
difficult experiences of six ring firing, that two rings is the
continuous caving was not achieved at this hydraulic radius.
maximum number of rings that will give reliable and repeatable
The centre access drive (CAD) which was mined to speed up results. Over cut panels never perform like slots because despite
development and reduce congestion, provided a unique their similar geometry’s the effects of gravity work against the
opportunity (Figure 1). It was recognised that a reslot in the broken rock movement to choke and freeze the blast no matter
centre of the orebody could provide a fresh start for each drill what the void space calculations show.
drive to guarantee full back height once again.
Sending a Toro remote 450D LHD across an opening inside a
The CAD was drilled and fired as a reslot at 80 degrees and roughly hewn blasted pillar appears an impossible ask to the
parallel to the drill drive rings. The irony of this strategy was that inexperienced. In practice this quite achievable by using the
while not proven to be necessary on the upper undercut which finely blasted dirt to build a ramp and road base (Figure 12).
Lower undercut
Void space
As for the upper undercut void space was provided by loading a
minimum 30 per cent of the blasted rock from the last firing to
create low density choked conditions for the next ring firing.
Bucket counts were set for every blast at three loading points
(Figure 5). The next firing was not taken until suitable void space
was provided. The low density firing rule was used for 100 per
cent of the lower under cut blasts.
In July 1997 damage to the rings caused by loading led to a
radical revision of swell removal policy which took into account
the space being provided by the opened draw bells. The blasted
swell removal was reduced to 11 per cent. However in order to
ensure the success of each blast a 220 bucket load (8.5 t/bucket)
was stipulated every six rings from loading point one (Figure 5).
This ‘mass load’ was in effect the quality check which
guaranteed there were no frozen rings above the brow. Failed
blasts did occur and brows did open but in every case these were
bombed and loaded until they fell in. Techniques to bring down
frozen ground centred around persistent remote loading, assisted
by bombing, firing in adjacent drives, remedial drilling and firing
when the brow closed. Northparkes did not leave any frozen
ground behind because of the unacceptable risk of point loading
through rock that was not properly blasted.
After blasting of the south west quadrant, an average of 50 per tempered with the experience of other block cave miners. Having
cent of charge metres in the ring portion over 50 degrees became decided on the skull shaped geometry Northparkes was faced
inaccessible across all drill drives in the lower undercut. A redrill with three main drilling and firing options.
rig was incorporated into the charging cycle to solve this problem Wedge firing was discounted because of its damaging effects
in July 1997. to the pillar structure. Blind boring of the raise was discounted
Toes always fired well with good charge metres but following on time and cost constraints. Up hole raising was discounted on
toe firing the lower undercut ring was a precarious main ring damage criteria. Slots were selected and mined as conventional
geometry leaning out at 70 degrees into an active cave. The key raises, 1.5 x 1.5 m in geometry. Slicing of the slot toes into these
to ring preservation at the brow was to exclude the cave loaders raises was tried but with limited success. Entire holes were lost
from drawing within two draw bells of the blasting front (Figure to blast damage as were the toes of the next blast. The limited
6). The absolute minimum swell removal policy was
collar space was damaged by escaping gases and charge
implemented so that lower undercut rings were supported by
packed blast rock. conditions were not satisfactory.
The stepped blasting front was straightened and maximum Single slot firing was the answer. Conventional raise stripping
lead/lag distances of 10 m were set between drill drives (±4 and long hole raise stripping was tried with success. The same
rings). But this was of a secondary importance to the loading collar damage problems occurred with long hole stripping. Long
strategy. Cave stress modelling showed concentration in the hole stripping was tried with long delay to the body of the main
lead/lag sections of the blast front but hole measurement of these blast and found to be successful when combined with built in
areas did not reveal any significant hole loss. brow support for the south and north side blasts. In its final
format bells were blasted as single slots with one North side and
Redrill rig one south side firing. In the case of early cave connection bells
were fired in double ring choked conditions with loading for
A full time redrill rig was incorporated into the blasting cycle swell relief.
with a rigorous QA system of hole measurement. Owing to the
Only 47 000 m of draw bell drilling was tendered in the drill
rill from the brow obscuring access to the brow rings it was
sometimes necessary to drill standard remedial drill rings and blast contract document as slots had not been offered in the
dumped at 62 and 66 degrees for the ring portion over 50 original scope. Raises were tendered separately once the slot
degrees. Approximately 20 per cent of lower undercut holes design had been selected but this was of no consequence to the
outside the South West quadrant were cleaned/redrilled. contractor who was pleased to drill the extra metres as a contract
A QA flowsheet was written in which provision was made to extension under the same terms and conditions.
fire up to three rings if the front ring was missing by blast
damage, loading out or if the third ring would need a second Undercutting rates and production ramp up
redrill after firing the ring pair. Very poor ground conditions and
The upper undercut which was started in January 1996 was
safety considerations sometimes led to three ring firings. These
completed in June 1997 having been fired out at rates
firings were successful and checked by loading 220 buckets (at
8.5 tonnes/bucket) every six rings. The three ring firing technique approaching 50 rings per month. Completion of the upper
was used for a period two months. undercut was slowed once enough stress cover was provided for
extraction level development.
Draw bells The lower undercut panels and slots started firing in July 1996
and were complete by March 1997. Undercut cut panels were
slow to fire out peaking at about 30 rings per month.
Two bell advance rule The lower undercut rings firing program started in January
Draw bells could not be fired out more than two in advance of 1997 and was completed in September 1997. At its peak the
the lower undercut blasting front because they formed a mini lower undercut was fired out at 60 standard rings per month over
undercut of the main ring toes over the minor apexes (Figures 5 a three-month period. These advance rates were only achieved
and 6). after the introduction of the redrill rig, minimum swell loading
rules and exclusion of the cave loading operation.
Skull shape The projects performance was measured against the expansion
plan which set the target as an annualised mining rate of 3.9 Mt
All Northparke’s drill and blast design problems started with the
definition of a basic geometric shape. Surface tests of proposed by July 1997. Challenges in the rate of developement and
draw point layouts were carried out with a diesel Toro 450D unit undercutting resulted in a slow production ramp up during 1996,
and the operators specified their preference for a brow that was however in 1997 the technical difficulties were overcome and
perpendicular to the draw point. To meet this design request a this financial year to-date has returned an annualised production
skull shaped bell was designed which is wider on side closest to at the rate of 3.9 Mt per annum.
the centre of the extraction level. El Teniente engineers revealed
that this design had been tried before in the Isla Mine. While CONCLUSIONS
simpler symmetrical designs are most common at El Teniente,
the skull shaped design had a successful mining history. Technical blasting success at Northparkes’ Endeavour 26 project
Northparkes went ahead with the skull shaped draw bell design has demonstrated that brand new block cave drill and blast
(Figure 14). Brow rings were drilled and fired as a pre split if the methods can be specifically designed to suit the unique
burden to the steel set was greater than 1.5 m. The burden to the conditions of green field sites on the Australian continent.
brow ring is arguably the most important wear surface in the bell, Drill and blast technology was developed rapidly from local
defining the length of the draw point and providing a wear and international sources by a small design team who were able
surface for all the rock draw from that point. to consolidate the experience of many external sources.
The contractors employed at Northparkes executed works to
Firing the highest quality assurance standards and this was made
simpler because the project management were committed to
A steep learning curve was traced out with draw bell firing at implementing these systems prior to writing the contract
Northparkes. From the outset designs were conservative and
documents.
Drill and blast design quantities were estimated accurately by Persson, P A, Holmberg, R and Lee, J, 1993. Rock blasting and
using fundamental design principles which only varied a small explosives engineering, Ch 8, pp 233-259 (CRC Press:1994).
amount when the rock mass was fully understood. Tunstall, A, 1994. Blasting Investigations at Northparkes Mines, Julius
Kruttschnitt Mineral Research Centre, University Of Queensland,
Department Of Mining and Metallurgical Engineering, Project P93F,
REFERENCES pp2-17.
Chen, D, Dawson, L R, Vink, D M, 1997. El Teniente and Andina Mine Vink, D M, 1995. Minimising Blast Damage to the Extraction Level Of
Technical Report, North Mining Limited pp1-20. Northparkes Mine’s E26 Block Cave, in Proceedings Explo ‘95
Conference, pp 251-260 (The Australasian Institute of Mining and
Chitombo, G, Scott, C, 1995. Development Blasting Trials on the 9800
Extraction Level, Julius Kruttschnitt Mineral Research Centre, Metallurgy: Brisbane).Vink, D M, 1995. Sub Level Cave Drill and
Blast Practice At Mt Lyell Mine, North Limited, Northparkes Mines,
University Of Queensland, Department Of Mining and Metallurgical
pp 1-15.
Engineering, JKMRC/AMIRA/BART, Project P447, pp2-17.
Vink D M, 1997. Northparkes Endeavour 26 Mine Drill and Blast Files,
Contract Number D70-223, 1995. Endeavour 26 Mine contract for Drill
North Limited, Northparkes Mines, 9830, Vol 1-2, 9818, Vol 1-3,
and Blast, North Limited, Northparkes Mines, Vol 1, Technical
9800, Vol 1-2.
Specification, Vol 2, Technical Specification.
Wulff, 1993, Northparkes Mines Chronological History of the
North Limited, 1994. Northparkes Expansion, Board Report from
Conceptual Design Work for E26N Deposit June 1984 - May 1993,
Northparkes Mines to the North Limited Board requesting approval
North Limited, Northparkes Mines pp 1-27.
to expand, pp1-8, Appendix1-3.