Professional Documents
Culture Documents
Ground Support in Strongly Foliated and Faulted Rocks
Ground Support in Strongly Foliated and Faulted Rocks
MARK BOUFFLER 1
ABSTRACT
The Woodlawn base metal sulphide deposit, located 50km S of Goulbum,
New South Wales, was mined as an open pit operation for 10 years from
19TI I producing 8 million tonnes of ore. Underground development
began in 1985 and reached full production of SOO,OOOtIyr as open pit
mining ceased in mid 1987. Underground development highlighted the
extensive deformation and intense alteration associated with the deposit
and the host rocks.
The deposit occurs above an acid volcanic pile in a sequence of
interbedded and interfingering shales, cherts, volcanogenic sediments and
pyroclastics of mid to late Silurian age intruded by dolerite sills.
Intense talc-ehlorite alteration, faulting, folding, jointing and a strong
foliation have combined to produce unstable ground conditions which
require a high degree of ground support. Mining is by mechanised cut
and fill and small scale long hole stoping using development waste as
back fill.
Systematic short term ground support is provided by 2.4 m long split sets,
installed by a Tamrock 2 boom Jumbo. Long term support of the hanging
wall and successive lifts is provided by twin strand cable dowels from 5
to 20 m long installed using a Tamrock Cabolter. Steel W straps, arched
steel sets and shotcrete are occasionally used for specific ground support
requirements.
Improvements in recovery of-the orebody from about 50% in 1987 to
about 65% in 1989 were made by using a flexible approach to mine
planning and ground support and keeping a tight control on opening
geometry.
INTRODUCTION
The Woodlawn base metal sulphide deposit, located 50 km S of
Goulbum, NSW, (Figure 1) was discovered in 1969 and
commenced production from an open pit in 1977. During the 10
years of open pit operation, 5 million tonnes of complex ore,
grading 1.6% Cu, 4.7% Pb, 12.5% Zn and 88 g/t Ag, and 3
FIG. 1. Woodlawn Mine Location Map
million tonnes of copper ore grading 1.5% Cu, 0.5% Pb, 1.7% Zn
and 20 g/t Ag were treated in the concentrator.
Since commencement of full scale underground mining in The mineralisation occurs as complex, fine grained, banded
1987 until June 1990, 1.5 million tonnes of complex ore grading massive sulphides consisting of pyrite, sphalerite, galena and
1.4% Cu, 4.3% Pb, 10.3% Zn and 96 g/t Ag and 174,000 tormes chalcopyrite with associated stringers of disseminated copper ore
of copper ore grading 1.86% Cu, 0.7% Pb, 2.2% Zn and 29 g/t Ag on the footwall and the southern edge of the lenses. Gangue
were treated in the concentrator. minerals include talc, cWorite, pWogopite, quartz, barite, calcite
As at May 1990, diluted recoverable reserves at Woodlawn and dolomite.
stood at 3.6 million tonnes grading 1.6% Cu, 4.2% Pb, 10.3 % Zn The bulk of the mineralisation occurs in three main lenses as
and 90 g/t Ag. The mine is owned by Denehurst Limited who shown in Figure 2. Lens 1C which originally cropped out as a
purchased the operation from Australian Mining and Smelting massive ironstone gossan was mined to a depth of 200m from the
Lld in August 1987. open pit. Lens 1B and 2B (B Zone) have only been mined from
underground.
GEOLOGY AND MINERALISATION Numerous small pods and lenses of discontinuous
The Woodlawn deposit is hosted by a sequence of Late Silurian mineralisation occur over a strike length of 400m and make up
shales, cherts and pyroclastics intruded by dolerite sills. Detailed the Lens 3 horizon, about 250m into the stratigraphic hanging
regional and local geological descriptions are available in Malone wall of the main ore horizon.
et al (1975) and McKay and Hazeldene (1987). Intensely altered talc cWorite schist occurs on the footwall and
within the orebody. Elsewhere chloritisation, silicification and
I. Mark Bouffler Senior Geologist Woodlawn Mines, PO Box 141,
Goulbum NSW 2580
sericitisation are variably developed.
2700 J
~
~ L/ I
I ' _ _ Llns
......... Llns
1(
28
,
I \
2600
'""--
t --J ~
!A29/-
~-'r
/........
\
\
___ Lens
_Lens
_B26 Stope level
18 ex
11 (u
A26~.
(
\.
~ \~\"
\
"\
I
"- \. I
I
2500 \
(21..\
".,
'., I
f
I
"-
\~
\.-. \ \-B20
\I
"'\ \.
2'00
\ \.. \ ..j 11
tBn
l..,
"B16
'l- B14
/ ~ \~ J
i
l/I \
\
r I \
\
'""-,
2300 I I ~
\ \ ,-, r--- '" '"
// \
I~
'"\ -j/
\
2200 ~, ,..-
\
\ /V
' ........./
-J
\
\
"
\
2100 \
~ ~ ~ ~ ~ <: ~ <:
<:> <:> <:> <:> <:> <:>
<:>
~
<:> ,.,
<:> <:> <:>
<:>
<:> <:> ..,
<:>
2000 0.
'"
0. 0.
~
0.
'"
0.
'0
0. "
0. 0.
Fro.2. Woodlawn Mine longitudinal section (looking west), showing stope levels referred to in the text.
.J
............ ~
'"...... ...'".
~
._- _._-- c~blts 20..
'",
~ lIN\ 1~ 'SSON
".,,~
....
--,-- "'"
~
'~
-
1\0 'AU' r
1st lif t
,-
A CROSS SECTION 1.8
'AU' ,
~
190
-.::.. r-,~ not to ICill.
1--------.-- 'SOON
-'--~
/
stub
piU.,
i'r_,,-- HANGING
,-._-_ .. -
:
----
~
--
l fJrf~
. - -
'(
"
-- - - ---
~
""(,
WALL
cross·
(ut
piln.l
9HON
FIG. 3. Level plan of ore outline showing 750 and 790 Fault
offsets for Lens 1B, Lens 1C and Lens 2B at RL 2560.
between panels (Figure 4). Before drilling each face, split set
bolts 2.4m long and 46mm diameter,are installed with a plate and
washer, at the operator's discretion, in holes with a nominal ___ Ore outline
diameter of 43mm, using the Jumbo. An average of about 25 _ _ Stope outline
split sets are installed for each four metre end fired in a stope and ..=9...;.'-'-O.:;.:ON'--_ _-t- ..; r:::I Ore not mine d
10 for each development end.
After completion of the sill lift, rows of twin superstrand cable
(15.2mm diameter) with a 26t breaking strain, are installed and
grouted using a Tamrock Cabolter. Cable dowels are generally
installed on a two metre grid pattern with all holes drilled
vertically except on the footwall row where holes are 5 to 20° FIG. 4. B20 stope RL 2482 Lens lB. Typical sill level on a cut
from vertical, depending on the dip of the lens (Figure 4). and fill stope. Inset shows cross sectional view of ground
Hole depths range from 6m to 20m depending on their location
These will be five to a row, 2m apart, also in a fan pattern (Figure
relative to the hanging wall and the dip of the lens. This pattern
of support gives reinforcement for two or three lifts both in the
5).
ore and the strongly foliated hanging wall. Experience at After installation of ground support, a rise is cut through at one
Woodlawn showed that most failures occur within ground not end of the stope and successive rings of vertical, column charged
pre-reinforced by cable dowels. blast holes fired into the slOL
After cabling the stope is backfilled with development waste Other Forms of Support
pushed up to within half a metre of the back using a Caterpillar
D6 bulldozer. Steel Sets
On following lifts, taken in 5m slices, exposed cable dowels Arched steel sets are erected where primary development passes
are cut and pre-stressed to 10 to 12t and a plate with a barrel and through major fault zones. In the past this was used for long term
wedge anchor installed. One or two rows of cable dowels are support and safety. If similar faults were encountered now, they
also installed along the footwall to provide support in that part of would be systematically supported with cable dowels and split
the lens not covered from the sill lift. Split sets are generally sets with steel sets used as a last resort.
placed between cable dowels where necessary.
Shoterete and Mesh
Long Hole Stopes Shoterete, mesh and W straps are occasionally used for specific
Small scale long hole stoping is used in the thickest sections of requirements. Various types of shoterete and mesh are currently
the orebody (Lens 1C) and where ground conditions are too poor being tested in areas where the block size is less than the split
to enable reasonable recovery by cut and fill mining. Using this set/cable dowel spacing.
method, a sill level and drill level are driven (4.5m x 4.5m), along
the footwall, about lOm apart vertically (back to floor) and short GEOLOGICAL FACTORS AFFECTING GROUND
term ground support installed as for cut and fill stopes. STABILITY
Localised support around the mucking level is provided by a
Many geological factors affect ground conditions to varying
fan pattern of five or six, 6m long cable dowels on a 2m row degrees. Information on most of these is obtained from drill core
spacing. In addition, 9m long countersunk birdcage cable dowels prior to mining and from mapping as mining progresses. They
are proposed to be installed to help support the hanging wall.
pillar parallel to the hanging wall. However, after one or two lifts
these usually collapsed as they had no natural support and were a
dead weight supported by cable dowels and split sets.
Most pillars are now vertical, beginning on or near the footwall
and gradually moving closer to the hanging wall on successive
drive lifts. Where the ore is greater than 15m thick, the footwall stub
pillars become island pillars by the third lift and hanging wall
stub pillars by the fourth lift.
Vertical rib pillars are left where cross-cutting faults make
mining of the ore unsafe or impossible. Crown pillars, IOm
thick, are left every 60m vertically in each lens and a 40m thick
2.4m split floor pillar remains between the open pit and underground
sets _ _
workings in Lens IC.
/ Two stope profiles are commonly used when driving a sill lift.
/ These are the "shanty back" or arch abutment profile and the
/ / natural arch profile.
The shanty back stope profile is used where the orebody is
mined over the full thickness and the dip is less than about 65°.
FIG. 5. Cross section of long hole stope layout and ground The footwall shoulder holes are not drilled in the face, a wedge of
support. ore is left which places the pressure squarely on the footwall.
Sometimes the knee and lifter holes are not drilled on the hanging
are discussed below. wall which leaves a wedge of ore at the base, thus decreasing the
1. Attitude of the lens - governs the cable pattern and stope up dip span over which the hanging wall is exposed (Figure 6).
proflle. The natural arch profile is used wherever the orebody thickness is
greater than the stope width.
2. Faulting and shearing - restricts access points, determines
where pillars will be and can severely limit mining recovery. 12111
3. Joints - are irregular, ubiquitous and unpredictable in some 10111
areas. (~bles
611
4. Talc chlorite alteration and silicification.
5. Thickness of the lens - determines stope layout and pillar
location.
6. Rock type - shales and tuffs are strongly foliated.
Dolerite is strongly jointed and blocky with block size often
smaller than the ground support spacing.
Acid volcanics are siliceous, weak to moderately foliated
and generally very competent.
Ore is banded and foliated parallel to the hanging wall and
HW wedge of
often jointed with irregularly distributed chlorite layers. Oftnot lIined
7. Foliation intensity - strongly foliated schistose rocks tend to
fret around split set and cable dowel plates, thus relieving the
pre-stress and minimising their effectiveness. FiG. 6. Cross section of shanty back stope profIle and ground
support.
8. Groundwater and mine production water - any water
whatsoever in talcose ground causes rock falls. TYPES OF FAILURE - CAUSE AND CONTROL
9. Folding - very little affect on the mesoscale. However, the The structural complexity caused by four periods of deformation
lower confining pressure in the hinge area of the larger folds has resulted in several common failure patterns. By identifying
results in strike slip movement along talc chlorite layers and these patterns and where they occur, appropriate measures are
opening up of the foliation. developed to control or avoid them, thus improving recovery of
the ore, safety and reducing operating costs. The most common
STOPE GEOMETRY ones are:
As well as the ground support described previously, well planned 1. Fretting or unraveling of the hanging wall along the
stope geometry is essential to maximise use of the natural load foliation is generally avoided by split setting the hanging
bearing strength of the rock. Various combinations of pillars and wall to within two metres of the floor as stoping progresses.
stope profiles are used, depending upon the thickness and dip of Such a failure is usually small and can be controlled if extra
the ore. support is installed immediately the hanging wall starts to
Where ore is less than 15m thick, driving along the footwall relax. Pushing fill tight against the hanging wall as mining
with crosscuts to the hanging wall leaves stub pillars. Originally progresses also helps to stop unravelling.
these were maintained over successive lifts giving an inclined