Professional Documents
Culture Documents
FPS Dependency Works.
FPS Dependency Works.
Floor Activities Total Qty Unit Completed Balance % Completion Depedency to work Remarks
Sprinkler fixing 500 Nos 450 50 90.00 Pending in Tower crane area
Electrical Panel incoming 2 Nos 0 2 0.00 yet to give from client end.
Upper Basement
Cable tray 36 Mts 0 36 0.00 Exhaust duct to be rerouted for cable tray drop work.
Diesel pump exhaust pipe 150 Mts 0 150 0.00 Yard Clearance need to give.
1st Floor Piping 2989 Mts 2797 192 93.58 Store to be dismantled to work in tower crane area
3rd Floor Piping 2989 Mts 2959 30 99.00 Tower crane area flooring to be done.
5th Floor MLCP Piping 1489 Mts 1478 11 99.26 Tower crane area flooring to be done.
7th Floor Piping 2852 Mts 2800 52 98.18 Tower 2 side shaft door to be install
10th Floor Piping 3275 Mts 0 3275 0.00 Need clearance to proceed works
Terrace Floor Booster pump installation 2 Nos 0 2 0.00 Need clearance to proceed works
Cabling ( From Pump room panel ) 300 Mtrs 0 300 0.00 cable routing to be finalized
Shaft-01 ( Piping with floor tapping) 150 Mts 138 12 92.00 B2 shaft scaffolding to be remove to do the works
150 Mts 138 12 92 Piping completed till 9F .above 9th floor civil
Shaft-12 ( Piping with floor tapping) scaffolding to remove .
Piping completed till 9F .above 9th floor civil
Shaft-13 ( Piping with floor tapping) 50 Mts 39 11 78 scaffolding to remove .
Shaft-14 ( Piping with floor tapping) 24 Mts 18 6 75 Doors need to be fix to proceed futher.
Shaft-15 ( Piping with floor tapping) 24 Mts 18 6 75 Doors need to be fix to proceed futher.
External area
Yard Hydrant installation 12 nos 0 12 0.00 Need clearance to install