ETV-3A ( FPS Floor Wise Dependency work Status )

Floor Activities Total Qty Unit Completed Balance % Completion Depedency to work Remarks

Shaft cleaning to be done for shaft tapping work also


Piping 4500 Mts 4400 100 97.78
Core cutting need to be done
Lower Basement

Sprinkler fixing 500 Nos 450 50 90.00 Pending in Tower crane area

Shaft cleaning to be done for shaft tapping work also


Piping 5336 Mts 5154 182 96.5892053973013
Core cutting need to be done

Pump installation 11 Nos 11 0 100.00 pump sleeves concrete to be filled .

Electrical Panel incoming 2 Nos 0 2 0.00 yet to give from client end.
Upper Basement

Cable tray 36 Mts 0 36 0.00 Exhaust duct to be rerouted for cable tray drop work.

Cabling 520 Mts 0 520 0.00

Diesel pump exhaust pipe 150 Mts 0 150 0.00 Yard Clearance need to give.

1. AHU pedestal needs to be done .


Ground Floor Piping 2213 Mts 1450 763 65.52 2.Shaft cleaning to be done.
3.Jump lift grid alignment to be done.

1st Floor Piping 2989 Mts 2797 192 93.58 Store to be dismantled to work in tower crane area

1. AHU pedestal needs to be done .


2nd Floor Piping 2989 Mts 2953 36 98.80 2.Shaft cleaning to be done.

3rd Floor Piping 2989 Mts 2959 30 99.00 Tower crane area flooring to be done.

1. AHU pedestal needs to be done .


4th Floor Piping 2989 Mts 2959 30 99.00
2.Shaft cleaning to be done.

5th Floor MLCP Piping 1489 Mts 1478 11 99.26 Tower crane area flooring to be done.

1. AHU pedestal needs to be done . 2.Fasad


5th Floor Piping 2852 Nos 2800 52 98.18 area piping pending due to glazing work
Tower 2 side Refuge Area false ceiling grid to be fix to
6th Floor Piping 2852 Mts 2800 52 98.18
do the alignment work.

7th Floor Piping 2852 Mts 2800 52 98.18 Tower 2 side shaft door to be install

1. AHU pedestal needs to be done . 2.Fasad


8h Floor Piping 2852 Mts 2570 282 90.11
area piping pending due to glazing work

1. AHU pedestal needs to be done . 2.Fasad


9th Floor Piping 2694 Mts 1800 894 66.82
area piping pending due to glazing work

10th Floor Piping 3275 Mts 0 3275 0.00 Need clearance to proceed works

Piping 448 Mts 0 448 0.00 Need clearance to proceed works

BFV Valve Fixing 37 Nos 0 37 0.00 Need clearance to proceed works

Terrace Floor Booster pump installation 2 Nos 0 2 0.00 Need clearance to proceed works

Cable tray 10 Zones 0 10 0.00 cable routing to be finalized

Cabling ( From Pump room panel ) 300 Mtrs 0 300 0.00 cable routing to be finalized

Shaft-01 ( Piping with floor tapping) 150 Mts 138 12 92.00 B2 shaft scaffolding to be remove to do the works

Piping completed till 9F .above 9th floor civil


Shaft-02 ( Piping with floor tapping) 74 Mts 67 7 90.5405405405405
scaffolding to remove .
Piping completed till 9F .above 9th floor civil
Shaft-03 ( Piping with floor tapping) 150 Mts 138 12 92
scaffolding to remove .

50 Mts 38 12 76 Piping completed till 9F .above 9th floor civil


Shaft-04 ( Piping with floor tapping) scaffolding to remove .

Piping completed till 9F .above 9th floor civil


Shaft-05 ( Piping with floor tapping) 150 Mts 138 12 92 scaffolding to remove .B1 duct layed in below the
pipe we need clearnace to proceed further.

Piping completed till 9F .above 9th floor civil


Shaft-06 ( Piping with floor tapping) 50 Mts 38 12 76
scaffolding to remove .
Piping completed till 9F .above 9th floor civil
Shaft-07 ( Piping with floor tapping) 150 Mts 140 10 93.3333333333333
scaffolding to remove .
Piping completed till 9F .above 9th floor civil All Shaft pipes poured by concrete slurry.it needs to
Shaft works Shaft-08 ( Piping with floor tapping) 150 Mts 138 12 92 be remove to install the shaft accessories, Also doors
scaffolding to remove .
need to be install above 5th floors.
Piping completed till 9F .above 9th floor civil
Shaft-09 ( Piping with floor tapping) 150 Mts 135 15 90
scaffolding to remove .B2 shaft corecutting to done.

Piping completed till 9F .above 9th floor civil


Shaft-10 ( Piping with floor tapping) 50 Mts 42 8 84 scaffolding to remove . Also Ground floor FFl and
shaft have to construct.
piping work completed but pipes are covered with
Shaft-11 ( Piping with floor tapping) 150 Mts 138 12 92
concrete and water stagging in B2 .

150 Mts 138 12 92 Piping completed till 9F .above 9th floor civil
Shaft-12 ( Piping with floor tapping) scaffolding to remove .
Piping completed till 9F .above 9th floor civil
Shaft-13 ( Piping with floor tapping) 50 Mts 39 11 78 scaffolding to remove .

Shaft-14 ( Piping with floor tapping) 24 Mts 18 6 75 Doors need to be fix to proceed futher.

Shaft-15 ( Piping with floor tapping) 24 Mts 18 6 75 Doors need to be fix to proceed futher.

North side 3 points need to be done.all other points


Piping works 100 Mts 0 100 0.00
we need civil clearnace to proceed.

External area
Yard Hydrant installation 12 nos 0 12 0.00 Need clearance to install

4 way , 2 Way brigade connection 2 set 0 2 0.00 Need clearance to install