MATERIAL SCHEDULE FOR THE PROPOSED MASSIONATTE

FOR PATRICK MACHARIA UPTO LINTEL FIRST FLOOR


ITEM MATERIAL UNIT QTY RATE
FOUNDATION
Foundation stones(9x9) Feets 820 30 24600
Ballast 3/4 inch Ton 30 1200 36000
Sand Ton 40 1000 40000
Cement (50kg) Bags 45 680 30600
DPM 1000g Rolls 2 3300 6600
Hoop Iron Rolls 2 3600 7200
Y8 No. 21 550 11550
Gladiator Litres 1 6000 6000
Hard Core Ton 25 600 15000
Brc A142 Rolls 2 29000 58000

SUB TOTAL 235550


WALLING,
Blocks(6x6) No. 1400 35 49000
Sand ton 40 1,000 40000
Cement bags 35 680 23800
D12 Bars PCS 24 1,250 30000
D8 Bars PCS 18 550 9900
Wall pass (hoop iron) Rolls 3 3,600 10800
TOTAL 163500
TOTAL 399,050
TOTAL(INCLUDING VAT)

Allow 5% contigency 19,952

TOTAL

Allow 30% LABOUR 119,715

TOTAL 538,717

PREPARED BY: WESTON CHEGE