ID Task Task Name Duration Start Finish Predecessors February 2022 March 2022 April 2022

Mode 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5
1 Engineering Docs.  24.88 days Sun 2/6/22 Thu 3/10/22
Rev.00

2 Sizing Report for 1.5" 8 days Sun 2/6/22 Tue 2/15/22


& 6" Piping Rev.00

3 Isometrics of 6"  5 days Wed  Tue 2/22/22  2 


Piping, Rev.00 2/16/22

4 Isometrics of 1.5"  5 days Wed  Tue 3/1/22  3 


Piping, Rev.00 2/23/22

5 Design Report of 1.5" 10 days Wed 3/2/22 Tue 3/15/22  4 


& 6" Piping, Rev.00 

6 MTO of 1.5" Piping  3 days Wed  Sun 3/20/22  5 


and Supports, Rev.00 3/16/22

7 MTO of 6" Piping and 3 days Mon  Wed   6 


Supports, Rev.00 3/21/22 3/23/22

8 Engineering  27.88 days Thu 2/24/22 Mon 4/4/22


Documents Rev. 01

9 Sizing Report for 1.5" 4 days Thu 2/24/22 Tue 3/1/22  2 FS  + 6  days


& 6" Piping, Rev.01

10 Isometrics of 6"  3 days Thu 3/3/22 Mon 3/7/22  3 FS  + 6  days


Piping, Rev.01

11 Isometrics of 1.5"  3 days Thu 3/10/22 Mon   4 FS  + 6  days


Piping, Rev.01 3/14/22

12 Design Report of 1.5" 4 days Thu 3/24/22 Tue 3/29/22  5 FS  + 6  days


& 6" Piping, Rev.01

13 MTO of 1.5" Piping  2 days Tue 3/29/22 Wed   6 FS  + 6  days


and Supports, Rev.01 3/30/22

14 MTO of 6" Piping and 2 days Sun 4/3/22 Mon 4/4/22  7 FS  + 6  days


Supports, Rev.01

Task Project Summary Manual Task Start-only Deadline

Project: Steam Bolier Project Sc Split Inactive Task Duration-only Finish-only Progress
Date: Wed 2/2/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1