Harmonized System of Survey and Certification (HSSC) was brought about with the
sole objective of simplifying and systemizing the survey and certification of
ships. This will ensure that survey works will not be duplicated e.g. survey for load
line or cargo ship safety construction is more or less same with logical changes. If a
ship undergoes survey of one, the survey of other will only overlap and once
conducted can be valid for both. Needless to say, a single survey covering both
certifications will save a lot of time and money. This will also allow the ship to plan
the survey in a more relaxed and professional manner. The total number of surveys
will be reduced and maintenance and work on board will be more systematic and
ships will not be out of service at different times for different surveys. Though it is a
mandatory system it is implemented on individual ships on different dates. It may be
implemented by the FSA ( Formal Safety Assessment ) on or after 3rd February
2000.
IMO Resolution A.1104 (29) gives the Survey Guidelines under the HSSC system
adopted on 2 December 2015.
Harmonized System of Survey and
Certification (HSSC) covers the following
certification under the modified or
amended instruments:
1. SOLAS 1974 as modified by its 1988 protocol
2. LLC 1966 as modified by its 1988 protocol
3. MARPOL 1973 and 1978 as amended by 1990 resolution (MARPOL 73/78/90)
4. IBC Code
5. IGC Code
6. BCH Code
Surveys for the issuance of these certificates, under the SOLAS, MARPOL, the Load
Line Convention and the Gas and Chemical Tanker Codes are as follows:
Annual survey
General inspection of the items relating to the particular certificate to ensure that
they have been maintained and remain satisfactory for the service for which the ship
is intended in accordance with the relevant requirements. The annual survey, as
required by the relevant regulations should be held within three months before or
after each anniversary date of the certificate.
Intermediate survey
The intermediate survey should be an inspection of items relevant to the particular
certificate to ensure that they are in a satisfactory condition and are fit for the service
for which the ship is intended.
Periodical survey
Inspection of the items relating to the particular certificate to ensure that they are in a
satisfactory condition and fit for the service for which the ship is intended. The
periodical survey should also consist of a check that all the certificates,
record books, operating manuals and other instructions and documentation specified
in the requirements relevant to the particular certificate are on board the ship.
The periodical survey, as required by the relevant regulations should be held within
three months before or after the second anniversary date or within three months
before or after the third anniversary date in the case of the cargo ship safety
equipment certificate and should take the place of one of the annual surveys and
within three months before or after each anniversary date in the case of the
cargo ship safety radio certificate.
Renewal survey
As per periodical survey but leads to the issue of a new certificate and to be held
before the appropriate certificate is renewed.
The cargo ship safety construction renewal survey may be commenced at the fourth
annual survey and may be progressed during the succeeding year with a view to
completion by the fifth anniversary date. The survey items of the fourth annual
survey should not be credited to the completion of the renewal survey.
Related Article: Lifebuoys
The inspection of the outside of the ship’s bottom and the survey of related items
should include an inspection to ensure that they are in a satisfactory condition and fit
for the service for which the ship is intended. Inspections of the outside of the ship’s
bottom should normally be carried out with the ship in a dry dock. However,
consideration may be given to alternate inspections being carried out with the ship
afloat.
Additional survey
Inspection, either general or partial according to the circumstances, to be made after
a repair resulting from casualty investigations or whenever any important repairs or
renewals are made.
1. the renewal survey may be completed within 3 months before the expiry date
of the existing certificate with no loss of the period of validity.
2. there is a “window period” of 6 months, from 3 months before to 3 months after
the anniversary date of the certificate for annual, intermediate and periodical
surveys.
A maximum period of validity of 5 years for all certificates for cargo ships
A maximum period of validity of 12 months for the Passenger Ship Safety
Certificate
A system for the extension of certificates limited to 3 months to enable a ship
to complete its voyage or one month for ships engaged on short voyages
The period of validity of the new certificate starts from the expiry of the
existing certificate before its extension if the extension was granted
A flexible system for the inspection of the outside of the ship’s bottom on
the following conditions:
1. a minimum of two inspections during any 5 year period
2. the interval between any two such inspections may not exceed 36 months