Professional Documents
Culture Documents
Lecture 12 Example of CPM
Lecture 12 Example of CPM
Activity Duration
(days)
1-2 14
2-3 13
2-4 12
3-6 20
4-5 18
4-6 24
5-8 18
6-7 15
7-9 20
8-9 15
a) Prepare an arrow network based on the events given in the
Table 1 below and overall duration to complete the project.
(15 marks)
b) Calculate the earliest start event time and latest start event
time. (7 marks)
c) Indicate the critical path and critical activity in the network
diagram that has been prepared in Question 1 (a).
Activity Duration
(days)
1-2 2
2-3 4
2-4 3
3-5 4
4-5 8
4-6 4
5-6 1
5-7 8
6-7 4
a) Prepare an arrow network based on the events given in the
Table 1 below and overall duration to complete the project.
(15 marks)
b) Calculate the earliest start event time and latest start event
time. (7 marks)
c) Indicate the critical path and critical activity in the network
diagram that has been prepared in Question 1 (a).
Activity Duration
(days)
1-2 14
2-3 13
3-4 11
2-4 12
2-6 20
4-5 24
5-8 18
6-7 15
7-9 22
8-9 20
QnA