Subject: | INCIDENT REPORT REGARDING LOST OF WELDING MACHINE
CABLE WIRE(30 METERS)
Ma’am/Sir;
Good day!
This letter is to report the incident that happened in our Project Area, particularly at Mambalili
Bridge Project: 21NO-0107 which happened last June 6, 2022.
The cable wire of welding machine with the length of 30 meters at Mambalili Bridge found
lost by the Field Engineer Clent D. Morales when they resume to work. He reported it
immediately to our Project Engineer Dexter G. Serot so that it will be taken action and file a
blotter for the lost of cable wire.
In connection, | will ask your good office to notice this issue so that this matter will be taken
Legal Action
Herewith attached is the copy of barangay biotter.
Respectfully,
f OT.
QUANSTY ENGINEER
BENEDICTO T. TABAOSARES JR.
SENIOR PROJECT ENGINEER