Professional Documents
Culture Documents
Final - Internship - Report - of - Nhial - Panom 2
Final - Internship - Report - of - Nhial - Panom 2
ID No: SU1100746
Section: A
Declaration
I Nhial panom puot a 4th year civil engineering student in Samara University have
undertake my internship experience in Nile Lechwe General Construction Plc at
Gambela in building construction from june20/2022 up sep/20/2021 G.C under guidance
of buomkuoth panom(company supervisor). I hereby certify that my work is original and
compiled according to the internship report writing guide line given by department.
Signature:
The undersigned approve that the above student has completed his internship program
for two-month period under my supervision.
Catalog
Declaration.................................................................................................................................
Approval letter..........................................................................................................................
Acknowledgement...................................................................................................................
Executive summary................................................................................................................vii
List of figures.........................................................................................................................viii
List of tables.............................................................................................................................
2) Bill of quantity....................................................................................................................10
3) Bar schedule.......................................................................................................................10
2. Structural drawing.............................................................................................................13
4. Sanitary drawing................................................................................................................13
5.1 Conclusion......................................................................................................................41
3.7 Recommendation............................................................................................................42
Recommendation to the company.....................................................................................42
Recommendation to the university...................................................................................42
References...............................................................................................................................43
Approval letter
This is to certify that the internship report entitled of Final Internship Report Prepared by
Nhial panom puot is accepted in terms of quality & forms the report has been prepared
under my guidance. I also confirm that the report is prepared based on the daily and
monthly reports that he submitted.
I approved that this report is compiled in accordance to the fulfillment of the internship
program.
Acknowledgement
First, I would like to thank the almighty God for all the blessing she has given to me. Next,
I would like to recognize Bule Hora University for its provision of this curriculum. I also
want to express my deepest gratitude to Nile Lechwe General Construction Plc for
accepting me for this program.
Last but not list I want to thank my families and best friends who helped me in every
single time being on my side.
Finally, I would like to express my gratitude to all the company workers and for peoples
helping me at my stay and for their help for writing and preparation of the final report.
Executive summary
It is a clear fact that the knowledge of construction engineering cannot be upgraded
without practical experience in each field of the subject matter. This paper is a written
report about the internship program which was planned to help civil engineering students
grasp practical know-how of civil engineering projects, their design, implementation,
evaluation, and management in general.
In this portion the internship program that lasted for two months from April 20/2021 up
July 30/2021 G.C. I have been learning the vital roles of civil engineer. I was able to see
and supervise how the construction of different parts of a building takes place.
Furthermore, I was working on some office works. I prepare takeoff sheet for form
work, concrete work and reinforcement bar schedule and bill of quantity. In doing so, I
have developed my theoretical knowledge and practical skills.
This report discuses my overall internship experience that lasted for two months. It has
four main portions. The first part discusses the company’s brief history, organization,
and work flow. The second section talks more about the overall activity during my
internship period
The third section focuses on the overall benefits I gained from the internship program. I
discussed these benefits in to aspects of what I gained including improving my practical
skills, upgrading my theoretical knowledge, communication skills, team playing skills,
leader ship skills, work ethics and entrepreneurship skills.
The last section suggests some remedial measures that the company should take
regarding some technical errors that I have witnessed on the site. And I have stated my
overall assessment of the whole internship experience and indicated some improvements
that I believe can make it easy for this program to meet its objective.
In short it explains the experiences I have gained during my two months stay. And I
have tried to discuss them with much relation to what I have learnt in the class room for
the last three years
List of figures
Figure 1-1 : organizational structure and work flow of the company........................................
Figure 2-1 : Image of hand compacter.......................................................................
Figure 2-2 : Dump truck............................................................................................................
Figure 2-3 : Loader....................................................................................................................
Figure 2-4 : Image of Mixer used in our site...........................................
Figure 3-1 : Site layout of the construction.......................................................................14
Figure 3-2 : Casted concrete on the column.............................................................................15
Figure 3-3 : Controlling concrete mix proportions..................................................................16
Figure 3-4 : column sample......................................................................................................19
Figure 3-5 : Construction of column........................................................................................20
Figure 3-6 : Construction of beam...........................................................................................21
Figure 3-7 : HCB wall in our site.............................................................................................23
Figure 3-8 : Construction of roof.............................................................................................25
Figure 3-9 : Wall Finishing with plastering.............................................................................26
Figure 3-10 : column formwork...............................................................................................27
Figure 3-11 : Grade beam form work.......................................................................................28
Figure 3-12 : Curing of concrete..............................................................................................32
List of tables
Table 3-1 : Formats for takeoff sheet.......................................................................................11
Table 3-2 : Bill of quantity format...........................................................................................12
Table 3-3 : Minimum compressive strength of HCB according to EBCS...............................23
Table 3-4 ፡ shows Grade of concrete with their mixing ratio...................................................30
mm Millimetre
RC Reinforced Concrete
cm Centimeter
Chapter one
1. introduction
Based on the new curriculum, I was doing internship for four months at Nile Lechwe
General Construction Plc. This internship program is given for all 4th year civil
engineering students. It is planned based on the benefit which it gives for both the
students and their host company. For students, they can gain practical skill, they may
have a chance to be employed after graduation, and they may become familiar for words
which are used in practical work, to develop any inter personal communication skill. For
company, they have an opportunity to obtain well skilled persons, they get an
opportunity to advertise their products or services, and they get benefit comments for the
future.
These days all of engineering companies in Ethiopia have an aim of improving their
country construction, highway, and other infrastructures. They have also aim of placing
their country in a better socio-economic development, increasing citizens annual income
by providing work …etc. it’s the same to my hosting company.
Sub-city: Newland
Kebele: 01
E-mail: nilelechwecon@gmail.com
The Vision of Nile Lechwe General Construction Plc is to be the best and most
successful national construction company that can undertake all kinds of construction
projects that delivers efficient and quality construction services.
Some of the missions of Nile Lechwe General Construction Plc are as follows: -
System
The head of the company is focused on only in Project planning. Reporting to the senior
project managers in different locals, it will develop and manage on a day-to-day basis for
a team of project managers, integrated plans, and programs of work to support execution
and timely completion of several concurrent projects. They undertake project planning
requirements in accordance with the procedures in the company quality management
system &, monitor and report activities progress.
Local Experience
The main customers of the company are NGO’s, private sectors but mainly is the
Government. Works performed and some of them still going on by Nile Lechwe General
Construction P.L.C in the past five years (including the work done by Nile Lechwe
General Construction for the Road works), are the followings:
The organizational structure and work flow of the company as a general and for any
project is as follows
Architect
Office
Engineers Civil Engineer
Architect
Civil Engineer
Building occupancy
Infn & Documentation
Finance
Office Engineers: are engineers that work design in the office that includes
Architects, Civil engineers, and Electrical engineers.
Site Engineers: are Engineers that monitor the site activities that also include
Architects, Civil engineers, and Electrical engineers.
Civil Engineers: are engineers which design and check structural & sanitary
plans.
Electrical Engineers: are engineers which design and check electrical plans.
Finance: are takes care of salary (fee) of the employees and write a receipt of
every payment that the clients gave.
I. Construction Permit Office: Giving permission for the construction which builds in
in the region when the building has fulfilled the criterion.
CHAPTER 2: CONSTRUCTION
EQUIPMENTS AND METHODOLOGY
2.2 Methodology
I have used the following methodologies to gain experience and information about the
Project work by asking;
Chapter three
Since we finish 3rd year class we got the application letter for internship from the
department of civil engineering in samara university. In that summer I took the letter to
the Urban Development and construction Bureau of Gambella Regional State and they
accepts my request letter and they gave their accepted letter to me, later I submitted
acceptance letter to department... After I finished the 4th year courses, It was time to take
the internship program. Before I was employed to, I delivered the letter which was given
to me from my campus. I went to Urban Development and construction Bureau first.
Then they introduce me to Nile lechwe generally construction plc. This is how I get in to
company and Buom Ruach Chol introduces me to Buomkuoth Panom. After this I
submitted the necessary document to the company of Nile Lechwe General Construction
Plc.
Together with my colleagues I saw the site which we are going to work by the help of
our supervisor & office Engineer and they introduce us to site Engineer and foreman’s
those present at the site. We discussed the situations in the site and how they can help us
in the time of contract. And how could we have to work the practical part in the site. At
the end Company Supervisor introduces to us other office and site profession.
In the companies I was working at the Site section which has two sub sections, office
work and site work. I was assigned on the site as an assistant site engineer. I also
preferred to work on the site because it is the place where I can develop and improve my
practical skills, and working in the office I was able to prepare bar schedule and take of
sheet. On the other hand, I was also working with the site engineer which I was able to
observe so many technical works such as how structural drawings were implemented on
site, labor organizing and directing and how to make decision on site.
Generally, during my stay I was trying to work with the site manager in order to have a
clear view about a construction project. But I also spend some of my time working with
other site workers. This is because I wanted to know my role and some tasks that I will
face in the construction industry after graduation.
The work I have been executing on the site was as an assistant site engineer. But I also
work and gain experience on other tasks like data collection, quantity surveying, site
supervision, supervision & sanitary works. At first, on the site I usually spent the day
observing and trying to do small jobs like preparing bar schedule and collecting data.
But after a while I was given some duties like checking the spacing, position and
diameter of the bars, which made me to take the responsibility of the work. This enables
me to gain a good experience. The work task that I have been executing as an assistant
site engineer and on others working sectors was:
In my two-month internship period I practice office works that are worked in our site by
the help of office engineer and data collector. Office works that are executed in our site
includes
Takeoff is a part of cost estimating process in the construction industry. Estimators use
construction blueprints, either manually or electronically, and start taking off quantities
of items they will need from those blueprints in order to prepare part of the estimate.
Preparing take off sheet requires collected data from the site. It helps to prepare payment
for sub-contractors. I prepared take of sheet of concrete work and formwork for beam,
column.
Takeoff sheet was prepared for each component of the building separately. For example,
take of sheet for beam, column, and slab… etc. Was prepared and calculated separately.
General formats of takeoff sheets are looks like the following formats for concrete and
formwork.
TAKEOFF SHEET
Project: - --------
Consultant: - --------------
Location: - -------------
Client: ---------------
Contractor: - -------------
Column 1: Timising Column is used for stating the number of times an item occurs.
Column 2: Dimension Column is used to enter the dimensions of the items of works.
It is a document used in tendering process in which includes the material, parts, and labor with
respect to their costs. It also details the terms and conditions of the construction or repair and
contract and itemizes all work to enable a contractor to price the work for which he or she is
bidding.
General formats of bill of quantity are looks like the following formats for concrete and
formwork.
The takeoff sheet has no room for estimation of reinforcement bars. Therefore, another
separate sheet of paper is necessary. Bar schedule is a tabular format that is specially
used for estimating the quantity of reinforcement bars required for a given project. A
complete set of structural drawings is necessary to take sizes and shapes of bars of
different members of RC structures.
For each type of RCC work a schedule of bars is required. Different sizes and lengths of
bars may be known, and may be arranged and bent up during the time of construction
schedules of bars of R.C.C of slabs, column, beam, stairs, etc. We need to calculate the
number of bars is required and the number of stirrups which is needed for each element
of the structure such as beam, column, slab, footing pads including shear walls, lift
shafts.
As I discussed in the above, I have determined that the exactly quantity needed for the
structure by having structural drawings, since it is clearly mentioned in the structural
drawings based on this let’s see that the format of bar schedule.
N.B
Unit weight (kg/m): it is the weight of 1 berga of reinforcement. One full length of
reinforcement or Berga has 12 m.
2
0.222∗∅
Unit weight=
36
Total weight (kg): it is the product of total length and unit weight.
Drawings are a means by which the diagram conveys the physical and visual description
of the project. Drawings are a dimensional representation of the physical structure of that
project. They are also known as plans of blueprints in our site.
1. Architectural drawing
2. Structural drawing
3. Electrical and installation drawing
4. Sanitary drawing
The drawing is the main language between the architect, engineer and any worker at the
site or office. Drawings are the most correct means of communication for all types and
areas of project. Thus, I understand each drawing and know every symbol abbreviation
for every action and I able to communicate with different workers using it.
In my two-month internship period I practice site works in addition to office works that
are worked in our site by the help of site engineer and site Forman.
Collecting data
Controlling the casting of concrete
Check and supervise mix ratio
Controlling the production and use of spacers
Check the quality of construction materials
The work that has been done should be quantified to check if it is going according to the
schedule or to prepare takeoff sheet. In order to do so, a data collector should measure
and record each work done like, type and material used, type and number of workers,
daily material expense by using this format and report to site engineer.
The casting of concrete requires a careful inspection on the mix ratio, compacting and
falling of concrete in permissible height. In our site compaction is done by using needle
vibrator and mix ratio is well done by batching box. The falling of concrete is limited
with 3m height in order to reduce segregation. This means the separation of coarse
aggregate and cement paste.
Samara University By: Nhial Panom Puot Page 25
Final Internship Report
Concrete is the single most important material in modern building and concrete mix
proportions are the most important aspect of working with concrete. Without concrete,
residential homes and commercial skyscrapers fall, bridges have no anchor, piers or
abutments; tunnels, sidewalks, curbs, sewer systems…etc. Generally concrete is the
foundation of development of the concrete works.
Cement
Aggregate
Sand
Water
I have checked and controlled concrete mix proportion of concrete with the help of
supervisor and site engineer. Usually, the supervisor must check every mix ratio and
quality of ingredients before casting of concrete to approve the work on the site book.
Concrete: - In our site the construction of beams, columns, and shear wall was casted by
a compressive strength of 30MPa (C-30) which means one bag of cement (50kg), 2part
of sand and 3part of aggregate, but in terrace slab construction C-25Mpa is used which is
the same proportion to C-30 the only difference is the dimension of batching box.
It is necessary to check the quality of construction material on the site at the time of
primarily inspection. It is not possible to check all the engineering qualities of
construction material on the site, but there exists some field test which gives rough idea
of quality of construction material. Each construction material has its own field testes to
check their quality.
1) Date of packing:
Date of manufacture should be seen on the bag. It is important because the strength
of cement reduces with age. In our site this is controlled by using the principle of
“first in first out” which means first enter to the store must be out of store first.
2) Color:
The cement should be uniform in color. In general, the color of cement is gray with
light greenish shade. The color of cement is an indication of excess lime or clay and
the degree of burning.
3) Rubbing:
Take a pinch of cement between fingers and rub it. It should feel smooth while
rubbing. If it is rough, that means adulteration with sand.
This internship program gives me opportunity to observe work procedures of each task
in the site and in the office.. I have work most of the time at the site to become more
familiar with the site works and to get more practical knowledge. Site works in general
include very kind of work executed at the site starting from setting out till finishing
works based on the given specification and methodology. The site work that I have been
through in the entire internship period was the superstructure and some parts of finishing
works not in substructure . A normal building consists of two parts in general these are
the super structure and the sub structure.
Any structure below the ground floor slab level including the basement, retaining walls,
ground slabs, grade beam, and foundation is called sub structure. In most of the cases,
substructure work can be categorised as earthwork, concrete work and masonry work.
Super structure is the part of the building which extend above the grade beam or
everything above the sub structure includes slab, column, walls, roofs, etc. the purpose
of the super structure is to enclose and divide the space as well as spread load safely into
the sub structure. In this section of my report, I will try to describe the sequence of some
of the procedures I have performed while performing my work tasks given by
supervisors.
Setting Out
A building is set out to clearly define the outline of the excavation and the centerline of
the walls, so that the construction can be carried out exactly according to the plan.
Surveying is carried out by total station through skilled professional. Performing the job
by the cited instrument will enable the respective professional to decide and limit the
real topography of the site. I didn't saw this work but I tried to grasp some knowledge by
asking the engineer how it was worked and its main procedures.
Excavations
Excavation is the first step of construction. It refers to the process of removing soil or rock
from its original location, typically in preparation for constructing foundations, basements
and underground utility lines and for grading of ground surface. Excavated materials
required for back fill is stock piled on the side for subsequent use. Excavation work I have
been seen was the bulk excavation of the included STP site. The main aim of the
Samara University By: Nhial Panom Puot Page 29
Final Internship Report
excavation work is to remove organic soils or unwanted soils for the safety of the building
from chemical attacking. Excavation shall be carried out to the lines, level width & depth
as shown on the drawings, directed by the engineer or as appropriate to the work to be
placed in the excavation. I didn't saw the excavation work of the main project site but I
tried to grasp some knowledge by asking the engineer how it was worked and its main
procedures.
Fill
Fill work will follow the erection of foundation column. Excavation need to be back filled
with better soil type, which will have better compaction character and would bring
minimum required proctor density. The soil present beneath the surface was too clayey, so
it was not used for back filling. For better results a minimum quantity of water may also be
sprinkled for better compaction. I didn't saw this work but I tried to grasp some knowledge
by asking the engineer how it was worked and its main procedures.
Superstructure
2.7.1.1 Beam
A beam is a horizontal structural element that is capable of withstanding load primarily by
resisting bending. The bending force induced into the material of the beam as a result of
the external loads, own weight, span, and external reactions to these loads is called a
bending moment. Beams generally carry vertical gravitational forces but can also be used
to carry horizontal loads (i.e., loads due to an earthquake or wind).
The loads carried by a beam are transferred to columns, walls, which then transfer the
force to adjacent structural part.
Superstructure beams are subjected to moments and shear loads, based on this effect its
reinforcement and stirrups was provided on the design given. The width and the depth of
beam depend on the moment and shear load of the beam. As the depth of beam increases
its moment resistant capacity is also increases directly.
Also, Negative bars are provided in beams for the purpose of resisting tensile stresses
developed around supports. The negative bars are tied at 1/3 of the length of the span from
the center of the column. The overlaps of reinforcement bar were being at the bottom of
the support for compression moments and at mid span on top of beam for tension
momentum with overlap length of 40D (mm).
These beams are T-shaped and bar arrangement are inter- locked.
Beams have three zone:
Tension zone
Neutral zone
Compressive zone.
CHECK POINT
Bar diameter
Spacing of stirrups
Lapping length
Lapping position
Dimension of spacer
2.7.1.2 Column
A column is a vertical structural element that can carry and transfer the loads of beams
and floor to the foundation footings. In works of columns the first way is the over lapped
reinforcement bars were connected by stirrups within the given spacing from the
structural drawings and wooden form works related to a proper dimension of the
column. After these activities completed the concrete were filled by fixing at the proper
elevation of the columns. The reinforcement bar of columns can be over lapped with the
previous bars by the formula below: -
Overlap = 40*D
Where, D = diameter of the bars in mm the columns in our site were rectangular in shape.
The vertical reinforcement bars were tied by double legged and single legged stirrups. All
columns in our site had a height of 3.90m.
The spacing of stirrups was very close on the bottom and top of the column at c/c 10cm
and in relative to the middle part of a column 20 cm. The risen behind this is the shear
force.
Shear force is very high in top and bottom of the column in relative to the middle part of
the column this condition because the filler on the age of the column due to shear force
become high. To reduce this effect, we use more stirrups on the two ends of a column in
relative to the middle part of the Column.
2.7.1.4 Walls
Wall is any of various permanent upright constructions having a length much greater than
the thickness and presenting a continuous surface except were pierced by doors, windows,
etc… used for shelter, protection, or privacy, or to subdivide interior space, to support
floors, roofs, or the like, to retain earth, to fence in an area, etc.
The most used concrete block is the stretcher block with a nominal dimension of:
HCB those present in our site were used to construct external and partition wall of the
buildings. See the figure bellow.
Partition wall: are types of walls used to separate the internal space within the
building in to separate rooms.
External wall: are in the external side of rooms and used to provide privacy, afford
security, and give protection against cold, heat and sun.
According to the Ethiopian standard hollow concrete blocks are classified in to three these
are
roof covering. It may be truss, beam, slab, shell, or domes. A roof in our site satisfy a
requirement of a good roof and it is pitched or slopping roof in its type and shed roof in
its form. A steel truss roof is used and the steel sections are RHS and it is grouped under
north light truss.
2.7.1.6 Plastering
It is the process of covering the face of HCB walls using cementing material. Coating is
classified in to three layers. These are:
First coat
Second coat
Third coat (Gypsum)
1) First coat plastering
It is used to create a rough surface for the next coat to adhere effectively. The mortar to
be used for this first coat has a mix ratio of 1:3.
In our site plastering is carried out after chiseling for a good bonding. It has a minimum
thickness of 5mm. 1 up to 2 days of curing is needed for it to attain sufficient strength.
2) Second coat
It covers most of the body of the coating and creates a good base for the next coating.
Beam or any other structure can be balanced by the second coating type by using eriga.
On average it has a thickness of 2 cm. It is made with a ratio of 1:2 of mortar i.e. 1 Bag
of cement and 2 Box of coarse sand. It has maximum thickness of 12mm & cured at list
2 weeks and waited for 21 days before 3rd coat applied.
3) Third coating(gypsum)
In gypsum plaster, gypsum is used as a binding material instead of Portland cement.
Gypsum plaster is a white cementing material made by partial or complete dehydration
of the mineral gypsum. When dry gypsum powder is mixed with water it gets hardened.
This material can be applied over block, or concrete surface to form a smooth surface.
It is available in ready to use format and does not need sand. Only the addition of water
is required. It offers excellent acoustic and thermal properties while giving leveled
walls with the best finish.
Non-Structural elements are a component of structural element. That means they are
essential to construct structural element. Generally non-structural element includes:
spacers, form work and lean concrete.
In the site formwork material, we use was the plywood material which have a good
surface finish and steel support tubes for supporting the plywood.
2. Preparing the formwork in the desired shape based on the drawing or the size of the
structure that is going to be cast.
The type of formwork that would be utilized on our site was a combination of plywood
and steel tubes. The purpose of employing plywood and steel tubes is to make sure that
quality concrete with perfect alignment would result. For horizontal structures like
reinforced concrete slab the plywood without being cut was placed. For vertical
reinforced concrete structures plywood formwork with timber false works was used. As
most of the elevation columns assume uniform size, the plywood was cut in size and was
produced in a manner it could be easily fixed and dismantled. The bracing was done
from timberland nailed perfectly to confine fresh concrete. Dismantling of the formwork
commenced after allowable dates have elapsed since the day of the concrete casting. The
dates of dismantling for the soffit formworks were shortened by the use of fast curing
concrete admixtures.
Figure 3-15: column formwork Figure 3-16: Grade beam form work
2.8 Concrete
Concrete is one of a vital construction material in almost all civil work, which is the
mixtures of cement, water, sand, and aggregate.
Cement: -is the active ingredient that combines with water to form a
Paste.
Aggregates: -Since aggregates occupy about three quarters of the
volume of the concrete, it contributes significantly to the structural
performance of concrete, specially strength, durability and volume
stability. In general, aggregates in concrete have been grouped
according to their sizes into fine and coarse aggregates. It is common to
refer to fine aggregate as sand and coarse aggregate as stone.
Water
Water is necessary for the combination of the cement and aggregate. In a correctly
proportion concrete mix, only about half of the mixing water is needed to hydrate the
cement there main detracts as a lubricant to produce workability. If the water is fit to
drink, it is satisfactory to use in concrete. This is not to say that water to be used in
concrete must be completely ignore. But as much as possible we must use clean water
Impurities in water may cause Corrosion of steel,Surface discoloration, Efflorescence
2.10 Curing
To prevent formation of surface cracks due to rapid loss of water while the concrete
is fresh and weak.
To assure attainment of strength by providing enough moisture for the hydration of
the cement grains concrete.In our site curing of concrete starts from finishing of the
pouring and ends in 7 days.
For an intern student, active participation in every activates of the company is must, to
be able to grasp knowledge and experience on its career, as a result I was trying to be
part of the company by actively take parting on the work and discharging my
responsibilities accurately.
As I have tried to describe before, on the first month I was spending my time on
observation of the activities and making my-self adapted to the environment, but after
that I have assigned on specific tasks and responsibilities. While performing my tasks I
was trying to be accurate and speedy as much as possible and for this my supervisor and
other colleges are witnesses. Also, further responsibilities given for me are enough
indicators that I was active participant.
Construction Engineer is one of the types of engineering that is full of challenges which
need an engineering imagination to overcome through those challenges. Taught to be
curious and critical thinking I had many questions to ask my colleagues at times
however, they were simply too busy to answer them so I had to wait. This delayed work.
sometimes, I was given a great deal of administrative work although I preferred
engineering work but there are always certain parts of one’s job that one won’t enjoy
being an employee means doing them any ways. Secondly there is not engineer safety to
wear during the work on the site. Thirdly there were security problems which lead to
delay the work period.
Basically, the types of challenges are categorized as follows: -
Natural Challenges
Artificial (Manmade) Challenges
I. Natural Challenges: -As its name clearly shows that those challenges aroused from nature
i.e. there is no participation of human beings and animals on their creation. The
following are some of the natural challenges during my internship program staying.
The following are some of those types of Challenges I have been faced on: -
The condition of weather: - The site location was wet. I have taken the helmet to
protect us from rain. Or the whole site postponed the work day sometime during
rain.
The problem of rain: -The type of soil was expensive soil which is high plasticity
these soils are known for their peculiar of expanding or shrinking when exposed to
moisture changes. So, site was full of water and the work has been stopped. Bring
the vibrator and remove water from the site and start the work.
II. Artificial (Manmade) challenges: - Those challenges are the most widely occurred
challenges in every construction engineering activity. I personally face those artificial
(manmade) challenges in my work tasks. The following are some of those types of
challenges I have been faced with:
Lack of transportation: -The project sites were far from my home location. Beside
this there was no transportation service given in the project site.
Solving the transportation and other service by asking my family to help me.
Lack of motivation and willingness: - This is one of the big challenges I face in
the internship in my hosting company organization there is a permanent work
schedule. Therefore, the working staffs only calculate their work times rather than
their duties.
To improve the imitativeness and willingness of the workers I try to work
with them without any payment.
Lack of communication skill: -On the first time of my internship program I have
also lack of communication skill with worker that means lack of confidence with
communication skill.
I start to note down each work and tried to memorize them. By applying
them on the site then through time I become familiar with the work and site
words.
The project manager didn’t give us good support because he is busy due to having
many works.
I tried to understand about the work by asking other responsible personnel
instead of the project manager.
The project was being late to start at we are arranged to practice on it.
The project up to it start we have gone to another site and we start our
practice up to it start.
The aim of the internship is to address more practical knowledge for student. So, I found a
practical knowledge at site as much possible within the four weeks. The knowledge we have
learned in class is helpful to get those practical work in the site and totally different from the
actual knowledge gained from the class.
Some of the practical knowledge I gained from the internship class was:
From my internship I could have memorized my theoretical concepts which have taken
from the previous semester. While I practice our work the theoretical part was my
guidance. In general, theoretical knowledge has no use without being practiced and vice
versa.
Even if I h a v e some vision in various courses learnt in the class, briefly I k n o w more
while I saw really.
While I start to contact the site worker; I could not understand the name of construction
material. As an example of site name which was ambiguous were:
panel------------------------for formwork
Staffa------------------------for stair up
Tumbi-----------------------for plum bob
Fir fir------------------------for mortar
biaka-------------------------for net bond
Armata----------------------for concrete
And other problem was executed. But, through process I could know these materials by
creating good relation with workers and the workers also help to know this name of
material. If I had question, I could have asked site engineers, foremen and other workers.
The first time while I ask them; they give me an advice to avoid afraid they give
freedom. Then they described everything which was new. Thus, due to the above
discussions I could have removed my afraid and I could have improved my interpersonal
communication skills.
Work ethics is the first principle to be considered at any site to get value able end of any
work. Work ethics reflected from faithful, punctual, and hard worker person who works
effectively to gain the expected result of the work. If there is full application of the work
ethics economical work can be taken place:
loyalty,
honesty,
trustworthiness,
reliability,
initiative,
self-discipline,
self-responsibility and punctuality
As a general while we execute our internship, we would have help labor forces and we
give dignity for the work.
Because some work men were elder in age and alliterated, in the case of this they have
a feeling of tired and negative filling in psychologically. Therefore, we should have
empowered them by following their act.
In general, I could have respected the rules and regulations of the company.
Leadership is a process of leading the careers of the company. Problems in the company
come in all size, shape, and color indifferent period time. Thus, a person who is in the
position of leadership seeks optimal solution to problems and should be smart enough to
manage those individuals whom he/she is leading.
Leadership has broad knowledge of communicating with his worker, to in spire his /her
workers into higher levels of teamwork
There are certain things he/she must be, know, and, do. These are
Side, anyone who is willing to make the effort can become a good
leader.
Internships can provide ahead sup on what it’s like working in almost any career field
imaginable. It is an opportunity to meet those currently working in the field as well as
Seeing what’s involved in atypical work day. To get the most out of your internship, try
Following the rules below and continue extending yourself by stepping out of your
normal comfort zone. Although we all want to find careers that match our interests and
personality, we can also learn a great deal by not limiting ourselves to people and
situations that are familiar and comfortable to us. Many internship experiences have
acted as career builders by providing new and exciting career options not previously
considered.
Team playing skill for construction work Team works, especially for engineers, involve
in every piece of task and achieving good team playing skill is essential for Effective
completion of tasks and Increasing productivity. This skill already exists in my
personality in the campus due to different assignment and project works that I work
together with student. But this skill is more than this in the construction site. In the
construction site the work is already a team work and it needs more closeness of workers
to solve problems arise in different aspects, misunderstanding in the drawing or working
methodology and consult every work. We the student at the site also works together as a
team to get more understanding and share ideas. More or less I improve my team work
status by working together with different professionals, student and workers as a whole
in the civil engineering works and consulting.
Totally student must be entrepreneur for being effective engineer and to be problem
solver. The entrepreneur men have the ability of guess as construction is economical and
quality full structure or not. And if, we say entrepreneurs engineer, he should have
thought how can we economical for the constructed building and able to select the kinds
of material used for a given structure.
Chapter five
5.1 Conclusion
Internship period was the most valuable period for the students, which largely helped us
to be familiar with the industry and gain a great deal of experience. It is known that
without clear understanding of the construction industry one cannot be a successful
engineer in the construction projects.
In this four-month internship period what I realized is that, the country needs educated
Engineers, even the market needs us. This internship gave me a whole perspective of my
profession and this include how I can interact with my profession, and see what the
actual industry looks like. It has also taught me immeasurable lesson about social life
and professional attitude. So, I believe that I will apply what I gained from this program
and contribute something fruitful.
I also acquire practical knowledge on site by the help of our staff workers such as
How to relate drawing with site activities
How we should if we face construction problem and find the solutions
Finally, I conclude that concrete without steel reinforcement has only compressive
strength and low tensile strength the same principal hold is true students without practice
has only theoretical knowledge so reinforced them by practice.
3.7 Recommendation
From my point of view, I have tried to recommend the following to our construction
company Nile Lechwe General Construction Plc.
Most of site worker, particularly site engineers and daily laborers do not have
safety closes like safety shoes, helmets, etc. to protect them from sudden injuries.
Due to this problem, they are exposed to different injuries while working.
Therefore, we recommend the company to arrange safety tools for site workers
Use modern machineries and equipment’s, this will enable the projects to be
finished with a lot of speed and will save a lot money that will be taken out for
hiring labors.
And has the advantage of using the machineries for a longer period.
Materials should be stored at appropriate and safe places on the site to prevent
wastage.
The company reuses some materials such as wood and Niles which have
economic importance to the company. However, reuses of such staff have
difficulty for workers and delays the works.
highly professional skilled man powers, this enables the firm to attend projects
with a lot of speed and accuracy.
Universities are providing good opportunities for students in this internship program, but
our department needs very useful practice at the end of every course.
References
1) Exercise book & handout
2) Internet for future information
3) Building construction material and handouts
4) Reinforced concrete one and two handouts
5) Ethiopian Building code of standard (EBCS),1995
6) Company documents containing organizational structure and brief history
7) Frederick S, Jonathan T, Merritt and Ricketts, “Building Design and Construction
Handbook”, Sixth edition, New York: McGraw-Hill, 2001.