SHIFTING A/E #6 & ADDITIONAL PLATFORM FOR EMERGENCY GENERATOR TO ROOF DECK P SIDE AWB BAYU

SAPI PLATFORM

No Description Man Power


1

1 Obsevation & Preparation Crews 1


2 Open Man Hole WBT Port Side IWO Hot Work Area Crews 1
3 Dismantle Pumps & Pipe instalation on Deck Crews 2
4 Dismantle Step Ladder Crews 3
5 Dismantle & Remove to Port Side Main Block Hook Platform Crews 4
6 Disconnect Cable Power of Emg Generator Crews 1
7 Remove & Shifting Emg Gen to Main Deck Free Area Crews 4
8 Disconnect Cable Power of A/E #6 Crews 1
9 Dismantle & Remove Liveraft Cradles P Side Crews 4
10 Shifting A/E #6 to Position Crews 6
11 Reinstall Step Ledder Crews 4
12 Reinstall Liferaft Cradles P Side Crews 4
13 Wiring & Connection Cable Power A/E #6 to Position Crews 1
14 Reinstall Main Block Hook Platform Crews 4

15 Marking & Cutting material Crews 4


16 Brushing & Painting Crews
Steel plate deck & Brackets Crews 2
H Beam & Angle bar Deck Longitudinal Crews 2
17 Isulation cables IWO Fr #52 - Fr #64 Crews 1
18 Open & dismantle wall & ceiling mess room IWO Fr #52 - Fr #64 (if neded) Crews 4
19 Fitt Up Components Crews
Brackets Crews 2
H Beam pillar & doublers Crews 3
H Beam Frame/ Transversal Crews 4
H Beam Longitudinal Crews 4
Deck Plate Crews 4
20 Welding Components Crews
Bracket to wall Crews 2
H Beam pillar & doublers Crews 2
H Beam Frame/ Transversal Crews 2
H Beam Longitudinal Crews 2
Deck Plate Crews 2
21 Painting
Touch up Crews 2
2nd Caot Crews 2
Final Coat Crews 2

22 Shifting Emg Genset to New Platform Crews 6


23 Installation Crews
Wiring Crews 1
Termination Crews 1
Running Test Crews 2
DECK P SIDE AWB BAYU LAUT PROJECT

Number of Day
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
26 27 28 29 30 31
ADDITIONAL A/E CAT 3412 AWB BAYU LAUT PROJECT
SAPI PLATFORM

DO
Plan
Number of Day
No Description Man Power
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 Shipmet Engine BMB 10
2 Shifting A/E to Position Crews 5
3 Installation Crews 3

NE
Wiring 2
Termination 2
Running Test & Load 4

Action Plan
Number of Day
No Description Man Power
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 Shipmet Engine BMB 7
2 Shifting A/E to Position Crews 5
3 Installation Crews 3
Wiring 2
Termination 2
Running Test & Load 4