Professional Documents
Culture Documents
Project Integration Management
Project Integration Management
Materials in this course are based on the text, A Guide to the Project Management Body of Knowledge (PMBOK® Guide
Sixth ), Edition, published by the Project Management Institute, Inc
.© 2017
.
• * Project Integration Management includes the processes and activities to identify, define,
combine, unify, and coordinate the various processes and project management activities
within the Project Management Process Groups
• The accountability for Project Integration Management lies with the project manager and
should not be delegated. Although some other Knowledge Areas may be managed by
specialists, the ultimate responsibility for the project as a whole lies with the project
manager.
* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition,
Project Management Institute, Inc., 2017.
• *Develop Project Charter is the process of developing a document that formally authorizes the
existence of a project and provides the project manager with the authority to apply
organizational resources to project activities.
• The Project Charter is typically developed and issued by the project initiator or sponsor,
although the project manager often collaborates in its development. It provides the project
manager with authority to move forward with the project and is used as a starting point for
project planning.
The Project Charter should include high-level information about the project including:
Project purpose: Place for children to study
Measurable project objectives and related success criteria
High-level requirements and key deliverables: School for 500 students
High-level project description and boundaries
Preapproved budget: $10 million
Summary milestone schedule: 2 years
Overall project risk
Key stakeholders
Assigned project manager and his/her responsibility and authority
* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition,
Project Management Institute, Inc., 2017.
• The Business Case is a Business Document that is a key input to consider when developing
the Project Charter. It provides information about the project’s objectives and the justification
for the investment being made in the project. It includes the business need and the cost-
benefit analysis.
• The Business Case is used throughout the project life cycle. At the end of the project, it is also
useful for measuring project success.
• The Benefits Management Plan describes how and when the benefits of the project will be
delivered and how those benefits should be measured.
• The Assumption Log is an output that contains the high-level strategic and operational
project assumptions and constraints that are already known.
Figure 2-2: Develop Project Charter—Inputs, Tools & Techniques, and Outputs
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –
Sixth Edition, Project Management Institute, Inc., 2017, Figure 4-2, Page 75.
• The Project Management Plan is a comprehensive, integrative document that defines how
the project is executed, monitored and controlled, and closed. The Project Management Plan
is updated with Outputs from other processes, which refers to the subsidiary plans and
baselines that are created in the planning processes, or those updated as a result of change
control.
• In addition to the subsidiary Knowledge Area plans, the Project Management Plan may
include other plans and additional components that are integrated in this process, including
the:
• Along with the Project Management Plan, Project Documents are used to manage the
project.
* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition,
Project Management Institute, Inc., 2017.
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth
Edition, Project Management Institute, Inc., 2017, Table 4-1, Page 89.
Figure 2-3: Develop Project Management Plan—Inputs, Tools & Techniques, and Outputs
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –
Sixth Edition, Project Management Institute, Inc., 2017, Figure 4-4, Page 82 .
• Direct and Manage Project Work is the process of leading and performing the work defined in
the project management plan and implementing approved changes to achieve the project’s
objectives.
• *A Deliverable is any unique and verifiable product, result, or capability to perform a service
that is required to be produced to complete a process, phase.
• Work Performance Data are detailed data collected about deliverables during project
execution. Examples include work completed; schedule, cost, quality observations and
measurements.
• Work Performance Data is an input to Monitoring and Controlling processes where it will be
analyzed.
• An Issue Log captures and monitors details about each project issue such as type,
description, priority, who raised it, who is assigned to it, target resolution date, status, and the
solution.
• There are different types of changes that arise during project execution. In addition to updates
to the Project Management Plan and Project Documents, changes may also include
corrective action, preventive action, or defect repair.
* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition,
Project Management Institute, Inc., 2017.
• All Change Requests must go through the Perform Integrated Change Control process for
approval. Approved Change Requests then become an input to the Direct and Manage
Project Work process where they are implemented.
• An important tool used in the Direct and Manage Project Work process is the Project
Management Information System (PMIS). This system includes IT software tools used to
gather, integrate, and disseminate project management information (e.g., scheduling, cost,
and resource tools; project records; Configuration Management System; Work Authorization
System).
Figure 2-4: Direct and Manage Project Work—Inputs, Tools & Techniques, and Outputs
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute, Inc., 2017, Figure 4-6, Page 90.
• *Manage Project Knowledge is the process of using existing knowledge and creating new
knowledge to achieve the project’s objectives and contribute to organizational learning.
• The main output of this process is the Lessons Learned Register which is a Project
Document used to record important knowledge gained by the project team throughout the
project life cycle. Lessons learned should be considered for use in the current project and
should later be transferred into the lessons learned knowledge base or repository at the end
of each phase, or at the end of the project (as historical information).
Figure 2-5: Manage Project Knowledge—Inputs, Tools & Techniques, and Outputs
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth
Edition, Project Management Institute, Inc., 2017, Figure 4-8 Page 98.
• *Monitor and Control Project Work is the process of tracking, reviewing, and reporting the
overall progress to meet the performance objectives defined in the project management plan.
• The Monitor and Control Project Work process allows the project manager to understand the
current state of the project and to recognize any existing or potential performance issues.
o collect project information to be used for status reporting, forecasting, and progress
measurements (e.g., scope, schedule, cost, and quality performance data)
• An important input that is gathered from other monitoring and controlling processes is Work
Performance Information. Work Performance Information consists of Work Performance
Data that has already been analyzed by other monitoring and controlling processes.
• Data Analysis techniques are used to further evaluate the compiled Work Performance
Information. Examples include Variance Analysis, Earned Value Analysis, Root Cause
Analysis, Trend Analysis, Reserve Analysis, Technical Performance Analysis, Alternatives
Analysis, and Cost-Benefit Analysis.
• Relevant Work Performance Information from all Knowledge Areas must then be pulled
together and integrated to create Work Performance Reports, which show overall project
status. The reports are then distributed to stakeholders through the Manage Communications
process.
Figure 2-6: Flow of Work Performance, Work Performance Information, and Work Performance Reports
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth
Edition, Project Management Institute, Inc., 2017, Figure 1-7, Page 27.
Figure 2-7: Monitor and Control Project Work—Inputs, Tools & Techniques, and Outputs
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK ® Guide) – Sixth
Edition, Project Management Institute, Inc., 2017, Figure 4-10, Page 105.
• Formal change control should begin once the project baselines are established and approved.
Changes to the project may be requested by any project stakeholder and must be
documented in a Change Request. Requested changes must be considered in an integrated
manner. Thus, the impact to the overall project must be considered when changes are being
evaluated (i.e., impact to cost, schedule, resources, risks, and so on).
* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition,
Project Management Institute, Inc., 2017.
• The Configuration Management Plan describing how information about project components
will be identified, recorded, changed, and controlled is also important in this process.
• A Change Log is an important Project Document that tracks all changes that were
requested throughout a project, as well as the status of each Change Request.
Figure 2-8: Perform Integrated Change Control—Inputs, Tools & Techniques, and Outputs
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute, Inc., 2017, Figure 4-12, Page 113.
• *Close Project or Phase is the process of finalizing all activities for the project, phase, or
contract.
• In the Close Project or Phase process, the Final Product, Service, or Result expected from
the project or phase is reviewed and transitioned to the customer, or to the next phase. This
includes all the Accepted Deliverables from the Validate Scope process.
• Organizational Process Assets are updated with lessons learned as well as the final Project
Management Plan, Project Documents, and any relevant project records.
• It may be necessary for the team to create Operational and Support Documents that help
an organization maintain, operate, and support the delivered product or service.
* These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition,
Project Management Institute, Inc., 2017.
• The Close Project or Phase process is performed at the end of each phase, at the end of the
project, and in the case of a cancelled project. It includes following procedures to investigate
and document the reasons a project was terminated prior to completion.
• It is useful for the team to use Project or Phase Closure Documents to demonstrate the
completion of a project or phase and to confirm the transfer of the project deliverables. This
ensures all project requirements were satisfied (or provides the reasons for project
termination in the case of a cancelled project).
Figure 2-9: Close Project or Phase—Inputs, Tools & Techniques, and Outputs
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute, Inc., 2017, Figure 4-14, Page 121.