Attention to: Eng.

Derchaye Getachew
DDU, CPO D/Manager

Review of Contractor’s Unit Price Breakdown Analysis

Client: Dire Dawa University Review No.: 02+


Consultant: Ethiopian Construction Design & Supervision
Contractor: Eshetu Lemma RC
Project: Site Work & Landscape
Project location: Dire Dawa City, DDU Campus

1. The Unit Rate Breakdown Analysis, Equipment Cost section should not
include Pickup 4WD vehicle, because this equipment doesn’t have direct
input for the work items, it is rather an overhead cost of the contractor.

According to Standard Bidding Document (SBD) For Procurement of Works,


version 1, August 2011. Prepared by the Federal Democratic Republic of
Ethiopia, Federal Procurement and Property Administration (FPPA),

Part 2: Schedule of Requirements


Section 6: Schedule of Requirements
B. Technical Specification
1.2 The rates and prices entered in the Schedule of Rates shall be
deemed to be the full inclusive value of the work including the
following, unless expressly stated otherwise

(g) Traveling to, between and from different locations within the
Network.

(h) The provision and care of all staff and labor and their payment,
accommodation, transport, fares and other requirements
including First Aid, welfare and safety requirements,

(i) Setting out, including the location and preservation of survey


markers, measurement and supervision,
Refer to page 73 of 150