S.No. Task Name Duration Start Finish Predecessors Resouces


1 Document Submission 9 days 06‐10‐2008 16‐10‐2008 GHIAL Team
2 Documents Review 5 days 17‐10‐2008 23‐10‐2008 1 Appin Team
3 Documents Resubmission 2 days 24‐10‐2008 25‐10‐2008 2 Appin Team
4 Diwali Break 3 days 27‐10‐2008 29‐10‐2008
5 Process Implementation 5 days 27‐10‐2008 31‐10‐2008 3 GHIAL Team
6 Internal Audit  6 days 03‐11‐2008 07‐11‐2008 Appin
7      1.Internal Audit 5 days 03‐11‐2008 07‐11‐2008 Appin
8      2.ISMS Review Meeting 1 day 07‐11‐2008 07‐11‐2008 Appin & GHIAL
9 Process Implementation Review 6 days 10‐11‐2008 15‐11‐2008 7,8 GHIAL
10 ISMS Review Meeting 1 day 17‐11‐2008 17‐11‐2008 9 Appin & GHIAL
11 External Audit Phaze 1 3 days 24‐11‐2008 26‐11‐2008 Intertek
12      1. Policy Documents Audit 1 day 24‐11‐2008 24‐11‐2008 Intertek
13      2. Procedure Documents Audit 1 day 25‐11‐2008 25‐11‐2008 12 Intertek
14      3. Process Document Audit 1 day 26‐11‐2008 26‐11‐2008 13 Intertek
15 Resolving Non conformities 14 day 27‐11‐2008 16‐12‐2008 GHIAL & Appin
16 External Audit Phaze 2 10 days 16‐12‐2008 29‐12‐2008 Intertek
17 Certification 1 day 29‐12‐2008 29‐12‐2008 Intertek
`