Professional Documents
Culture Documents
Amendment To Scheduled H For EPC & HAM Projects
Amendment To Scheduled H For EPC & HAM Projects
waha)
SE,S&R(Roads)
For DG (RD)& SS
Copy to:
1. All ROs/ ELOsof MoRTHand all Technical Officers at MoRTHHeadquarter.
2. Sr. PPSto Secretary (RTH), Sr. PPSto DG (RD) ass, PSto AS&FA,PSto all ADGs.
Page 1of 7
It·
Amendments to J nnexure-I of Schedule G of Model Concession Agreement of Hybrid
Annexure
Annuity Model (Hj~) Projects.
Annexure-I of Schedule G
Format for contra ct price weightages for highways projects with Flexible Pavements.
1.2 Proportions of the contract price for different stages of construction of the project
highway shall be c s specify below.
Road works inc [!ding C- New culverts, minor c- New culverts, minor bridges,
culverts, minor bridges, underpasses, underpasses, overpasses on
bridges, underpasses, overpasses on existing existing road, realignments,
overpasses, road, realignments, bypasses:
approaches to bypasses:
ROB/RUB/Major (2) Minor bridges (2) Minor bridges
Bridges/Structure s (but (c) Super-structure (c) Super-structure (including crash
excluding service (including crash barriers barriers etc. complete) If pre-cast
roads) etc. complete) girders/ segments are used, 40% of
the weightage of the stage in
percentage to the bid project cost
is assigned to the casting of such
precast girders/segments.
(3) Cattle/Pedestrian (3) Cattle/Pedestrian underpasses
underpasses
(c) Super-structure (c) Super-structure (including crash
(including crash barriers barriers etc. complete) If pre-cast
etc. complete) gi rders/ segments are used, 40% of
the weightage of the stage in
percentage to the bid project cost
II is assigned to the casting of such
precast girders/segments.
II!
(4) Pedestrian (4) Pedestrian overpasses
overpasses
(c) Super-structure (c) Super-structure (including crash
(including crash barriers barriers etc. complete) If pre-cast
etc. complete) girders/ segments are used, 40% of
the weightage of the stage in
percentage to the bid project cost
is assigned to the casting of such
precast girders/segments.
(5) Grade separated (5) Grade separated structures
structures
(a)Underpasses (a)Underpasses
II
(iii) Super-structure (iii) Super-structure (including
(including crash barriers crash barriers etc. complete) If pre-
etc. complete) cast girders/ segments are used,
40% of the weightage of the stage
Page 2 of 7
in percentage to the bid project
cost is assigned to the casting of
such precast girders/segments.
(b) Overpass (b) Overpass
(iii) Super-structure (iii) Super-structure (including
(including crash barriers crash barriers etc. complete) If pre-
etc. complete) cast girders/ segments are used,
40% of the weightage of the stage
in percentage to the bid project
cost is assigned to the casting of
such precast girders/segments.
(c)Flyover (c)Flyover
(iii ) Super-structure (iii) Super-structure (including
(including crash barriers crash barriers etc. complete) If pre-
etc. complete) cast girders/ segments are used,
40% of the weightage of the stage
in percentage to the bid project
cost is assigned to the casting of
such precast girders/segments.
Major Bridge works and A. - Widening and Widening and repairs of Major
ROB/RUB repairs of Major Bridges
Bridges
a. ROB ROB
Page 3 of 7
is assigned to the casting of such
precast girders/segments.
C. - New Major New Major Bridges
Bridges
a. ROB ROB
1
Page 4 of 7
Format for contract price weightages for highways projects with Rigid Pavements.
1.2 Proportions of the contract price for different stages of construction of the project
highway shall be as specify below.
Page5of7
(iii) Super-structure (iii) Super-structure (including
)1
(including crash barriers crash barriers etc. complete) If pre-
etc. complete) cast girders/ segments are used,
40% of the weightage of the stage
in percentage to the bid project
cost is assigned to the casting of
such precast girders/segments.
(c)Flyover (c)Flyover
(iii) Super-structure (iii) Super-structure (including
(including crash barriers crash barriers etc. complete) If pre-
etc. complete) cast girders/ segments are used,
40% of the weightage of the stage
in percentage to the bid project
cost is assigned to the casting of
such precast girders/segments.
Major Bridge wor sand A- Widening and repairs A- Widening and repairs of Major
ROB/RUB of Major Bridges Bridges
(3) Super-structure (3) Super-structure (including crash
(including crash barriers barriers etc. complete) If pre-cast
etc. complete) girders/ segments are used, 40% of
Ii
the weightage of the stage in
percentage to the bid project cost
is assigned to the casting of such
precast girders/segments.
B- Widening of repair of B- Widening of repair of
(a) ROB (a) ROB
(3) Super-structure (3) Super-structure (including crash
(including crash barriers barriers etc. complete) If pre-cast
etc. complete) girders/ segments are used, 40% of
the weightage of the stage in
percentage to the bid project cost
II is assigned to the casting of such
precast girders/segments.
(b) RUB (b) RUB
(3) Super-structure (3) Super-structure (including crash
II (including crash barriers barriers etc. complete) If pre-cast
etc. complete) girders/ segments are used, 40% of
the weightage of the stage in
percentage to the bid project cost
is assigned to the casting of such
precast girders/segments.
c- New Major Bridges c- New Major Bridges
(3) Super-structure (3) Super-structure (including
(including crash barriers crash barriers etc. complete) If pre-
etc. complete) cast girders/ segments are used,
40% of the weightage of the stage
in percentage to the bid project
cost is assigned to the casting of
such precast girders/segments.
Page 6 of 7
D- New rail-road D- New rail-road bridges
bridges
(a) ROB (a) ROB
(3) Super-structure (3) Super-structure (including crash
(including crash barriers barriers etc. complete) If pre-cast
etc. complete) girders/ segments are used, 40% of
the weightage of the stage in
percentage to the bid project cost
is assigned to the casting of such
precast girders/segments.
(b) RUB (b) RUB
(3) Super-structure (3) Super-structure (including crash
(including crash barriers barriers etc. complete) If pre-cast
etc. complete) girders/ segments are used, 40% of
the weightage of the stage in
percentage to the bid project cost
. is assigned to the casting of such
precast girders/segments.
Structures (elevated (3) Super-structure (3) Super-structure (including crash
sections, reinforced (including crash barriers barriers etc. complete) If pre-cast
earth) etc. complete) girders/ segments are used, 40% of
the weightage of the stage in
percentage to the bid project cost
is assigned to the casting of such
precast girders/segments.
(4) Reinforces Earth Wall (4) Reinforces Earth Wall (includes
(includes Approaches of Approaches of ROB, Underpasses,
ROB, Underpasses, Overpasses, Flyover etc. If RE-wall is
Overpasses, Flyover etc. used with facia panels/blocks, 10%
of weightage of the stage in
percentage to bid project cost is
assigned to the casting of such facia
panels/blocks for one complete
approach.
*****
Page 7 of 7