Professional Documents
Culture Documents
02 Procedure For Reinforcement
02 Procedure For Reinforcement
1
Table of Contents
Chapte
Title of Page No.
r chapter
No.
Table of contents 2
History of Revisions 3
1 Purpose 4
2 Scope 4
3 Definitions 4
4 Responsibility 6
5 References 6
6 Flow Chart 7
7 Procedure 8
8 Quality Metrics 12
9 Records 12
10 Attachments 13
2
History of Revisions
Chapter/
Revisio Revision Clause no. &
n No. issue text affected Reason for revision
date
0 -- First Issue
Clause 9.0
3 Requirement of Factory cut bars.
Procedure
Critical Action Points from Learning’s of
Clause 10.0 Group Kaizens2012 incorporated: Cut
4
Procedure Length of the samples of Steel mentioned.
Number
of samples to be tested incorporated.
6 Cl 3, 4, 5, 7, 8, 9
3
1. PURPOSE:
To document a procedure for laying of reinforcement steel in RCC Structures. To ensure that
the laying of reinforcement in RCC Structures on site is as per the Technical Specifications of
the Company.
2. SCOPE:
To establish, monitor and control all activities during laying of reinforcement in RCC
Structures shall be applicable across all the projects of the Company.
3. DEFINITIONS:
Reinforcement: It may be defined as a mesh of high yield deformed steel bars or wires
used as a tensioning device in concrete structures holding the concrete in compression. It
is usually formed from carbon steel and is given ridges to form a better bond with the
concrete. The word rebar is used interchangeably with the word reinforcement. It is
normally termed as Fe 415, Fe 500, Fe 500 D etc. The nomenclature “Fe” indicates
Ferrous and the number followed by the nomenclature indicates the minimum Yield
Strength of the bar in N/mm2. The letter ‘D’ indicates the category with the same
specified yield stress but with enhanced specified minimum percentage elongation.
4
Typical picture of Reinforcement Bars
Bar Bending Schedule (BBS): It is a tabular statement showing the diameter wise length,
shape, numbers and spacing of rebar for a structural element. BBS shall be prepared in
accordance with IS 2502 (latest revision) i.e. Code of Practice for Bending and Fixing of
Bars for Concrete Reinforcement.
Binding Wire: It is a wire used to tie the rebar together at their points of intersection
with each other. 18 Gauge Galvanized Iron Binding Wire. Double knot tying of
binding wire
Cover Block: A block of suitable material and appropriate size used to position the rebar
such as to result in the required distance between the rebar and concrete surface (cover).
Stress – Strain curve of Steel: Stress Strain Curve is a behavior of steel when it is
subjected to load. In Stress – Strain Curve, stresses are plotted along the vertical axis and
strains on the horizontal axis.
5
o Elastic Limit (E): Indicates the value of stress up to which the material is
perfectly elastic. The material to return to its original position if unloaded
before crossing the point E.
o Yield Point (Y): The point after which the material extension takes place more
quickly with no or little increase in load. Stress associated with point Y is
called as Yield Stress.
o Ultimate Stress Point (U) : The maximum strength that the material bears
before breaking also called as Ultimate Stress Point.
o Breaking Stress (Point of Rupture)(B): The point where the material breaks.
The stress associated with this point is called as Breaking Stress
Elongation: The increase in length of a tensile test piece under stress. The elongation
at fracture is conventionally expressed as a percentage of the original gauge length of
a standard test piece.
Gauge Length: It is the length of the steel bar which is being tested. The length is
generally measured between the grips of the machine for the test.
4. RESPONSIBILITY:
Task Responsibility
Completion of works as per relevant WPM
(work procedure manual), Latest GFC Project Manager MIPCL- SAKTHI
drawings, latest approved revision of PQP ASSOCIATESS
(Project Quality Plan)
Initial checking and inspection of the Engineer In charge- SAKTHI ASSOCIATESS,
Reinforcement works Engineer in charge MIPCL
Final checking and inspection of
Engineer- In charge MIPCL.
reinforcement works
Random checking of BBS (50%) Quality-in-charge- MIPCL
Achieve Zero NCs in reinforcement activity Project Manager MIPCL- SAKTHI
ASSOCIATESS
5. References:
Technical Specifications
Approved latest Project Quality Plan
Contract Document and BOQ
Structural GFC Drawings
IS 1786 (Latest Revision) : High Strength deformed steel bars and wires for concrete
reinforcement.
IS 2502 (Latest Revision) : Code of Practice for Bending and Fixing of Bars for
Concrete Reinforcement.
IS 4082 (Latest Revision) : Stacking and Storage of Construction Materials and
Components at Site.
6. Flow Chart:
Start
Is the
Reject the Material
Report Satisfactory
No
Yes
Store dept in coordination with Quality department to take clearance from Quality Department to use of
==== =============================================================================
=
of 16
Preparation of Bar Bending Schedule (BBS)
by Contractor
Placing and fixing the steel as per Structural Drawing and Codal Requirements
Rectify
No
End
PROCEDURE:
Incoming Material:
All incoming steel should be accompanied with a Manufacturer Test Certificate. Identification
mark with batch production /cast etc. shall be available on the bundles. In addition to this, the
quality of the steel to be verified as per the Inspection and Test Plan (ITP) by testing the steel
in NABL Accredited Third Party Lab as per requirements of IS 1786 (Latest revision) and
report 300duly produced before utilizing the steel as required.
In case if the steel fails in any of the Physical or Chemical Test as per the Third-Party Test
Report, the material shall be rejected and the Supplier to take the steel back within 3 working
days.
Stacking of Material:
All reinforcement shall be clean, free from oil, paint, dirt or any other substances that will
destroy or reduce the bond and shall be stacked on either timber/ sleeper wood or MS frames,
concrete pedestals of height not less than 300 mm from the ground level.
The steel shall be stacked diameter wise separately and shall have the Tag of dia of steel,
grade of steel, status of testing like “UNDER TESTING, PASS, FAIL and HOLD. The steel
cleared by the quality department shall be issued to the contractors by stores.
Cut and bent steels shall be inspected as per BBS and tagged floor, tower and element wise
for shifting. This tag shall not be removed until placing the steel
Placing of Steel: Following points to be taken care while cutting, bending and placing of steel
Before placing of steel in the structural member, the structural member shall be made free
from dirt, loose scales, paint, oil and grease and kept clean to receive the reinforcement.
TWO LEVEL CHECKING- Preparation of Bar bending schedule shall be done by
Contractor as per the Structural Drawing. It shall be checked by Building-in-charge and Cross
checked by building-in-charge of other building. Sample (50%) checking of BBS shall be
done by Quality Manager. Similarly, placed reinforcement at site shall be checked by
building-in-charge and cross-checked by building-in-charge of another building. shall be
followed by building-in- charge for the placed reinforcement before concrete casting.
For factory cut bars, BBS shall be prepared and given to supplier.
To avoid mixing up between cut and bent steel going to different location other than intended
location, tagging shall be done by the BBS engineer tower wise, floor wise and element wise.
Fabrication of reinforcement shall be done mechanically or with hand but to the correct radius.
Bars with any visible defects such as cracks, splits shall not be used. Mandrel shall be used for
bending the steel 20 mm diameter and above. Diameter of Mandrel used for bending of bars
shall be as per Table 4 of IS 1786: 200
Cover blocks shall be of non-corrosive material such as plastic or PVC but not wooden or
stone. However, concrete cover blocks shall be of the same grade as of concrete pour. Cover
to the reinforcement shall be provided as per the Structural drawing. Actual Concrete cover
shall not deviate from the required nominal cover by + 10mm and – 0 mm.
Minimum Spacing of Reinforcement:
The minimum horizontal distance between parallel reinforcement shall not be less than as
follows:
o Diameter of bar when bars are of same diameter and diameter of thickest bar when
bars or more than one size are used.
o Maximum size of coarse aggregate plus 5 mm. A greater distance should be provided
when convenient.
The vertical distance between two horizontal main bars shall not be less than as follows:
o 15 mm.
o Two- third of the nominal maximum size of aggregate.
o Maximum size of the bar (whichever is the greatest).
Stirrup hooks shall be bent at 45 °. It is important during earthquakes or seismic activity. The
first link shall be at a distance of 50 mm from the bearing of the Structural Member.
Binding Wire: It shall be of gauge 18 galvanized iron confirming to IS 280 and shall be free
from rust, oil, paint, grease, loose mill scale or any other material undesirable for the
reinforcement and concrete or which may prevent adhesion of concrete with reinforcement.
Binding wire shall not protrude in the cover zone.
Reinforcement steel shall not sag between supports and shall not be displaced during
concreting. If required, steel chairs, supports, spacer bars, ties etc shall be placed at
appropriate spacing
Typical Arrangement of Chairs to support the bars
In case of vertical structural members like walls and columns, the reinforcement shall be kept
in position by adequate supports. Bars of full length shall be used to minimize wastage.
Mechanical Threaded Couplers: Couplers shall be used for bars over diameter 36 mm. In
such cases, lap splices shall not be used. However, bars may be welded for larger diameter,
but no welding is allowed for Secondary Steel.
Protective treatment shall be given to bars as per the following table depending upon the
duration for which the Bars are exposed to environment.
Sr Duration of Exposure
Protective Treatment
No to Environment
1 More than 2 months Brush Coat of Cement Slurry
2 More than 6 months Zinc rich Coat
3 More than 12 months Epoxy Coat
Samples that are cut for testing from the lots received shall be cut from the middle of the bar
i.e. in a 12 m length rebar, 3 m from both sides to be left out and the sample pieces shall be taken
from the middle 6 m length.
Strength ratio shall be checked (Proof stress/ Ultimate Tensile Strength) shall conform to Is
1786 (latest revision). Min strength ratio shall be 1.10.
A minimum of 2 test pieces shall be taken as sample for testing for every 50 MT (for primary
steel) or every change of heat no (for Secondary Steel)
Stacking of steel shall be done as procedure for handling, preservation and storage
8 Quality Metrics (Effectiveness and Efficiency Measures): There shall be no defect during
execution.
9 Records
10 Attachments
Bar Bending Schedule - FT. 04.WPM.B.05
Check list for Reinforcement- (CT.03. WPM.B.05)
SR DO DON’T
NO S S
1 Receipt of Incoming
Material
All incoming material shall have MTC Do not unload the vehicle until a
valid MTC is available along
with Material
2 Stacking of Material
Proper identification and tagging system Do not unload the steel on the
(“UNDER TESTING, PASS, FAIL” ) ground as it may come in contact
shall be with oil, paint, dirt or any other
established in the reinforcement stacking substance which might affect the
yard. Steel shall be stacked dia wise bond between steel and concrete.
separately at a height of min 300 mm
from ground level on concrete/ MS
pedestals.
3 Testing of Material
Use the steel only after receipt of valid Do not use the steel until receipt of
Third-Party Test Report for Steel a third party test report.
4 Cutting and Bending of
Steel
Cutting and bending of Steel shall be done Excessive bending of steel may
as per the Codal Provision lead to cracking of steel.
5 Cover to Reinforcement
Use noncorrosive material for cover Do not
blocks like PVC, plastic or concrete of 13 Use corrosive material as cover.
same grade used for the structural 14 Provide less cover to
member. Actual Cover shall not deviate reinforcement
from the nominal cover by + 10 mm and - It affects the durability of the
0mm. structure thereby reducing the life
of the structure.
6 Spacing of Reinforcement
Provide appropriate spacing between the Provision of inadequate spacing
rebars to enable concrete to flow through between reinforcement leads to
the rebars thereby enabling defect free congestion of reinforcement
concrete. leading to honey combing of
concrete thus affecting the
durability of concrete.