9.daily MFU
9.daily MFU
Start
1 Inspect the whole Condition of Unit
Finish
Start
2 Install Scaffolding
Finish
Start
3 Install Skillet/LOTO
Finish
Start
4 Open Manhole
Finish
Start
6 Cleaning Oil Box
Finish
Start
7 Cleaning Rotor Agitator
Finish
Start
8 Cleaning Skimmer Assembly
Finish
Start
9 Cleaning External MFU
Finish
Start
10 Repair Louder Cover and door Covered Plate
Finish
Start
11 Repair Skimmer Assembly
Finish
Re-paint The Lounder Cover and door by Using Switable paint or Start
12
designated by Company
Finish
Start
13 Replace All Cover Louder and door Gasket
Finish
Start
14 House Keeping
Finish
Start
15 Dismantle Skillet/Loto
Finish
Start
16 Runing test
Finish
Start :
Completed :
Prepared,By Reviewed,By
PT EFK-Supv PT TPE-CS