02 TT 02 CigreParis

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

TRANSMISSION

Cigre Paris 2008 feedback- Study


committee B2: Overhead lines
by D Muftic, on behalf of R Stephen, with assistance from Pierre Marais, Riaz Vajett and Viven Naidoo

This is a summary of the discussion which took place during the 2008 open session of the Cigre group B2: Overhead Lines. The session dealt
with three specific preferential subjects, two of which are covered here. 27 papers were published and 40 prepared discussions were given
showing a high interest in the preferential subjects.

The first preferential subject on increasing solutions. HSILL lines and environmental l Solutions for a quick recover y:
capacity of overhead lines was prepared impact had four submissions (B2-108, B2- e m e r g e n c y s t r u c t u r e s, details of
with the participation of SC C1 (System 109, B2-111, B2-107). The most interesting fault and emergency recovery pans;
development and economics). The second was discussion on the use of HSILL lines construction of temporary lines, etc.
preferential subject was on solutions to concept and the experience of about 20 On maintenance and refurbishment
improve the availability of overhead lines. years (Eletronorte), which provided large methods based on diagnostic tools and
The discussion meeting was divided into cost saving and gave good performance. methods, five papers were submitted
two parts, each dealing with a preferential One question from the reporter was about (B2-207, B2-208, B-2-209 B2.2-10 and
subject. SC B2 Chairman, B Dalle chaired the point at which the HVDC solution B2-213), dealing with different diagnostic
the session, the special reporters were becoming more economical than HSILL methods and preventive maintenance
P Pramayon (PS 1) and G Brennan (PS 2). AC. JWG-B2/B4/C1.17 is dealing in-depth approaches.
Dalle opened the meeting with a summary with that question and their latest discussion
of SC B2 activities and brief information on that is given in Appendix 1. In increasing reliability and security by
about ongoing organizational changes improving electrical and mechanical
Conversion of AC lines into DC was the per formances: mechanical strength
in Cigre. subject of two papers. One related to coordination, foundation assessment,
Preferential subject number one : conversions of a 300 kV line in Norway de-icing methods, anti-cascading towers,
Pierre Pramayon (B2-110), and another with the conversion mechanical fuses, etc. (papers B2-203
of 275 kV lines in South African (B2-104). Our to B2-206 and B2-211 to B2-215) several
Preferential subject one dealt with increasing (South African) paper was a compilation up-rating and upgrading techniques were
the capacity of overhead lines. Papers of two interrelated issues in that regard: discussed. The topic provided a ver y
received under this preferential subject are network planners and designers interaction interesting group of practical problems and
classified into four categories: and feasibility of AC/DC conversion on engineering solution in present international
l High temperature conductors or new one specific example of lines in KZN. It practice.
type of conductors was proven, through discussion, that such
conversion is feasible, but to make it cost One of the most interesting contributions
l Transmission capacity increase by use in this subgroup was on raising of towers
effective and reliable requires in-depth
of weather records and predictions, without removing conductors. Mr. Suzuki
studies and well coordinated efforts. On
probability based rating or real time Kanji from Japan presented discussion
the issue of comparison of clearances
monitoring equipment which dealt with the development of a
and right-of-way (ROW) for AC and DC lines
l General papers on overhead line (one of the questions from the reporter), hydraulic device that could lift a tower while
(OHL) transmission capacity increase more detailed analysis was done, which the conductors are still attached so that
solutions, High Surge Impedance proved among others, that clearances and the bottom of the tower could be repaired,
Loading Lines(HSILL) and environmental ROW are not fully consistent in our current strengthened, or a body extension put in.
impact practice (see details in Appendix 2). When the equipment is used it is possible
to raise a tower by up to 9 m in one day.
l Conversion of AC lines into DC On the same subject of clearances, a more Already over 100 towers have been raised
Under high temperature conductors or recent compilation of tower top geometry using the device. This device could be
new type of conductors two papers and mid-span clearances was produced useful for instances were towers have to
(B2-106 and B2-112), were presented by TB 348, WG B2.06 (the excerpt is given be raised to obtain additional ground
dealing with the application of composite in Appendix 3). clearances such as on abnormal load
core and aluminium conductor steel Preferential subject number two: routes. It can also be used to raise towers
supported ( ACSS) conductors. There was in cases where a line is being up-rated and
Gary Brennan
nothing significantly new in that area. requires additional ground clearance.
Transmission capacity increase by use This Preferential subject dealt with solutions
Finally, it is worthwhile mentioning that a
of weather records and predictions and to improve the availability of lines, important
rather interesting exhibition was presented
probability based rating or real time to the economic well being and social
during Cigre conference on visually
monitoring equipment is a subgroup with stability of modern societies.The following
improved towers designs. Some details
three papers (B2-101, B2-102 and B2-105), special topics were identified :
are given in Appendix 4.
dealing mostly with indirect methods of l Maintenance and refurbishment
dynamic rating. The issue of applications methods based on diagnostic tools Appendix A1: Impacts of HVDC lines on the
that are acceptable for system operators and methods economics of HVDC projects
was emphasized as well as the use of l Increasing reliability and security by R i a z Va j e t h, D z e v a d M u f t i c and Pat
forecasting techniques which anticipate improving electrical and mechanical Naidoo are corresponding members of
requirements set by the Regulator in the performances: mechanical strength this important workgroup. Riaz and Pat
best way. coordination, foundation assessment, attended the workgroup meeting in Paris.
There was a group of general papers de-icing methods, anti-cascading The draft final report was reviewed at this
on OHL transmission capacity increase towers, mechanical fuses, etc. meeting. The workgroup was formed in

energize - November 2008 - Page 27


TRANSMISSION

Umax Un Vpeak, Normal Switching Lightning ROW


(kV) (kV) VDC operation clearance clearance (m)
(kV) clearance (m) (m)
(m)
145 132 118 0,35 1,3 1,45 36
245 220 200 0,6 1,88 2,1 (43)
300 275 245 0,7 2,2 2,5 47
362 330 295 0,86 2,6 2,9 (51)
420 400 342 1 2,9 3,2 55
(491) (400) 1,2 3,35 3,7 (60)
(654) 533 1,55 4,3 3,7(4,6) 30(70)
800 765 652 1,9 5,2 5,5 (70)80

Table. 1: Figures in brackets represent interpolated values.

of the tower top to ensure that the electrical


clearances required at the tower and mid-
Fig. 1: Economic voltages ($-million per year) as a function of
span are achieved.Wind is a significant
power and length. factor in determining the position of the
conductors in the span as well as the position
of the insulators at the tower and hence a
2005, after it was realised that HVDC will start We used Umax AC voltages as a reference for
good understanding of the expected winds
increasing in usage, because of IGBT’s and the analysis because of the simple reason
is essential to a good design. The approach
other high speed devices and at a relatively that normal operation voltages in an AC
used to calculate the conductor and
lower cost than before. The main purpose system are standardized, but not in DC. That
insulator positions is a probabilistic one. The
was to look into the cost of the transmission is why in the case of a given DC voltage,
paper comprises five parts as follows:
line and converter station as a whole, and corresponding (hypothetical) AC operating
study which voltage will be most economical, voltages are calculated. Table 1 shows the l Analysis of existing methods
over a life cycle of 30 years. Voltages from relationship between clearances and related l Determination of swing angles for set
±300 kV to ±800 kV were considered, these voltages in AC and DC, as well as relationship wind loads
being the current state of the art. to the ROW, or servitude width.
l Comparison of available information on
Issues like capital costs and maintenance We can come to the conclusion from the clearances for different overvoltages
costs of lines and substations were carefully overview, among others, that the maximum
evaluated, based on real data from utilities l Proposals for co-ordination of conductor
normal operating voltage which can be
and manufacturers around the world. positions and electrical clearances
reached by upgrading a 275 kV existing line,
Converter station losses, typically 2%, and described in paper B2-104, using the same l Examples
line losses (both joule and corona) were overvoltage levels on DC as on AC (rather This approach is very different to that which
considered in the evaluation. The study is conservative assumption), will be on the is currently applied in South Africa where
meant to provide a useful guide on how
level of ± 250 kV. The increase of this level standard wind pressures (100 Pa and 500 Pa)
to evaluate a project when HVDC is being
to about ± 350 kV, maintaining the same are used to determine the insulator swing.
considered. Planners faced with a task
clearances (existing tower) is possible only by These different pressures are then associated
of transporting 500 MW to 6000 MW, over
reducing ( the assumption) of overvoltages, with different overvoltage stresses that can
distances from 750 km to 3000 km, will find
both switching and lightning. The required occur in the system. Wind with a 50 year
this report a very useful guide indeed.
ROW will be slightly reduced, on the level of return period is used for the calculations.
A summary of the results of the report is approximately 45 m. Wind values are adjusted for height above
shown in Fig. 1. ground in accordance with IEC 60826.
If the decision will be in favor of more radical
In the figure Red-> ±-800 kV; Green-> solution, by changing tower top geometry, Standard values for overvoltages as given
±-600 kV; Pink->±-500 kV; Blue->±-300 kV. in IEC 60071 are used in the calculations.
and choosing DC voltage on the level of
The black (±-300 kV) curve shows the area The clearances to be maintained under
± 500 kV, which is quite close to our existing
below which ±-300 kV is the economical the different overvoltages are calculated
HVDC voltage. The blue and pink curves Apollo-Cahora Bassa ± 533 kV system, the
in accordance with the Cigre TB 72. The
shows the breakeven point between 300 kV equivalent hypothetical AC voltage will be
GAP factors that are recommended for the
and 500 kV, when considering transmission about 654 kV (Umax), related clearances are calculations are given In Table 2.
d i s t a n c e s o f 7 5 0 0 k m, 1 5 0 0 k m a n d as for ± 533 kV. It should also be considered
3000 km. For example if one wants to being on more conservative side. The equations used to calculate the required
transfer 700 MW over 1500 km, ±-300 kV clearances are given in the Technical
The ROW for all voltage levels is estimated Brochure.
will be a likely choice. Similarly, if 4500 MW
needs to be transferred over 750 km, 800 using typical line and tower configurations
Phase-to-earth clearances
kV is most economic. (mostly flat phase configuration). The rather
low figure for ROW for the Apollo-Cahora The corresponding phase-to-earth clearances
Appendix A2. D pe_ff and D pe_sf are calculated using the
Bassa example is a result of the monopole
A relation between the required clearance configuration applied here. The results formulae (3.1) and (3.2):
for AC and DC voltage and width of ROW correspond fairly well with the more extensive Fast front overvoltages:
is analysed on the example from Eskom’s analyses of clearances and ROW for HVDC
practice, related laboratory tests on high (3.1)
system within B2-06(JWG17) .
altitude and a more recent investigation
into the subject. The effect of pollution on Appendix A3: tower top geometry and Slow front overvoltages:
clearances and tower geometry (the issue midspan clearances
of differences between insulation in polluted (3.2)
environment between AC and DC) is not The paper gives guidance on the method
anticipated here. for calculation of the geometric dimensions where:

energize - November 2008 - Page 28


TRANSMISSION

Figs. 2, 3 and 4: Overhead lines as industrial art.

Configuration kg Pierre Marais, Riaz Vajett and Viven Naidoo.

Conductor-window, e. g. air gap configuration between a conductor inside a tower and the Contact Ken King, Merz & Mclellan,
tower structure Tel 011 886-6573, king@merz.co.za v
1,25
- vertical string or V string inside the window
Conductor-structure, e. g. air gap clearance between a conductor, connected to a free 1,45
swinging insulator string at the extremity of a cross arm, and the tower structure
- vertical string at the extremity of a cross arm
- V-strings
Conductor-conductor 1,60
(1) The gap factor in this table are typical values only. In practice, other values supported by 6
experiments may be used. Typical gap factor values can also be obtained from IEC 60071-2,
annex G.

Table 2: Gap factors Kg for slow-front overvoltages (1).

U 50%_ff is the fast front (lightning impulse)


over voltage being withstood with 50%
probability (kV);
Umax_sf is the maximum slow front (switching)
over voltage which can occur on the
transmission line (kV);
kg is the gap factor (for slow front overvoltages
see Table 2);
ka is the altitude factor for altitude H:

(3.3)

The exponent m follows from the CIGRE


Technical Brochure No. 72 and is between Fig. 5: Concept aesthic/ decorative tower.
0,7 and 1,0.
Phase-to phase clearances
especially in areas were longs spans exist as
The required phase-to-phase clearances
the swing angle for the conductor and that
D pp-ff and D pp-sf between conductors can
for the insulator are different.
be obtained modifying equations (3.2) and
(3.3) as follows: Appendix A4: Exhibition – overhead lines as
“Industrial Art”
Fast front overvoltages
(3.4) An interesting exhibition on “decorated towers”
was hosted by a local French artist. A series of
Slow front overvoltages towers in a highly visible portion of a local town
were decorated and illuminated.
(3.5)
This served as inspiration for the creation of
In equations (3.4) and (3.5) a gap factor the concept tower, Fig. 5 which could be
kg = 1,60 should be used to calculate the used by Eskom if the opportunity arose.
clearances between conductors.
Acknowledgement
This method of checking insulator and
conductor swing can prove to be quite useful This report was prepared with assistance from

energize - November 2008 - Page 30

You might also like