KPGF CCI

TRANSMITTAL No:

MS-ORA-HRL-JV-KPGF-001
METHOD STATEMENT FOR EXCAVATION

Checked by Approved by

Designation: Site Engr. Designation: HSE Engr CCI


Name: Bilal Khan Name: Awais Bashir

Signature: Signature:

CONTROLLER COMMENTS/REMARKS:

DELIEVERED RECEIVED
REV.
DATE
NO
REASON FOR REVISION
ORA-HRL CC
1. INTRODUCTION
This procedure has been produced to provide site engineers with the necessary guidelines
and conditions to ensure that the work covered in this method statement is carried out in a
controlled and professional manner.

2. SCOPE OF WORK
The scope of work applies to all excavations with depth upto 10 ft at pet line area for pipe
installation.

3. RESPONSIBILITIES
The Site Engineer is responsible for the supervision of excavations.Site Engineer will bear
the overall responsibility. Site Engineer and will supervise the excavation works as
stipulated in the procedure.

4. METHOD OF EXCAVATION

• The excavation works will start from the lower part of the slope and move towards
the lowest embankment.
• A level instrument will be available on site throughout the overallprocess.

• Demarcate the excavation setting out plan with reference co-ordinates and levels.
Please note that the survey bench marks are away from the excavation in order to
prevent the damage to markers and to maintain accuracy.
• Protect and support underground utilities e.g live electric line and excavation at that place will
be handled manually.
• Mobilize the machinery for excavation.
• Stack the soil away o n e m e t e r from the excavation edge to prevent soil
collapsing to theexcavation area.
• In case of soil disposal, appoint banks man to guide the machinery movement.
• If there is ground water percolating to excavation, please inform the Client and find
out suitable preventive measures.
• All the excavation area is to be barricaded (hard barrication by using scaffolding
pipes ) with sign boards such as “excavation is in progress, stay away” to be kept
in all languages (English & Urdu) which can understand by workers easily.
• Complete the excavation as per the levels mentioned in the drawing.
5. EQUIPMENT AND WORKFORCE

5.1 Major Equipment

Equipment Specification Quantity Remarks

Excavator 1
Quantity may be
Tractor Trolley 1 increased according to
distance.
Hilti 1

5.2 Major Workforce

Job Classification Number Remarks


Foreman 1
Same as number of the
Operator machines
7
Labour

6. SAFETY MEASURES

• All the workers at the excavation shall wear PPE at all times such as Safety helmets,
safety shoes and Gloves etc.
• All the workers have to be briefed about the excavation and safety measures
required for excavation through pre-work trainings.
• The soil shall be stacked away 1 meter from the edge of excavation to prevent
collapse ofsoil on to workers working at bottom.
• All the excavation area shall be barricaded with sign boards and warning tape.
• Sign boards to be kept at all visible places and to be protected.
• Close supervision and recording by site engineer/ supervisor is required.
The speed limit of tractor trolley to be controlled