Professional Documents
Culture Documents
Understanding EIA
Understanding EIA
1. Mining Projects
2. Industrial Projects
3. Thermal Power Projects
4. River Valley, Multipurpose, Irrigation and H.E. Projects
5. Infrastructure Development and Miscellaneous Projects
6. Nuclear Power Projects
Once an application has been submitted by a project authority alongwith all the requisite
documents specified in the EIA Notification, it is scrutinised by the technical staff of the Ministry
prior to placing it before the Environmental Appraisal Committees. The Appraisal Committees
evaluate the impact of the project based on the data furnished by the project authorities and if
necessary, site visits or on-the-spot assessment of various environmental aspects are also
undertaken. Based on such examination, the Committees make recommendations for approval
or rejection of the project, which are then processed in the Ministry for approval or rejection.
In case of site specific projects such as Mining, River Valley, Ports and Harbours etc., a two
stage clearance procedure has been adopted whereby the project authorities have to obtain site
clearance before applying for environmental clearance of their projects. This is to ensure
avoiding areas which are ecologically fragile and environmentally sensitive. In case of projects
where complete information has been submitted by the project proponents, a decision is taken
within 90 days.
Monitoring
After considering all the facets of a project, environmental clearance is accorded subject to
implementation of the stipulated environmental safeguards. Monitoring of cleared projects is
undertaken by the six regional offices of the Ministry functioning at Shillong, Bhubaneshwar,
Chandigarh, Bangalore, Lucknow and Bhopal. The primary objective of such a procedure is to
ensure adequacy of the suggested safeguards and also to undertake mid-course corrections
required, if any. The procedure adopted for monitoring is as follows:
1. Project authorities are required to report every six months on the progress of implementation
of the conditions/safeguards stipulated, while according clearance to the project.
2. Field visits of officers and expert teams from the Ministry and/ or its Regional Offices are
undertaken to collect and analyse performance data of development projects, so that
difficulties encountered are discussed with the proponents with a view to finding solutions.
3. In case of substantial deviations and poor or no response, the matter is taken up with the
concerned State Government.
4. Changes in scope of project are identified to check whether review of earlier decision is called
for or not.
Understanding EIA
Environment Impact Assessment or EIA can be defined as the study to
predict the effect of a proposed activity/project on the environment. A
decision making tool, EIA compares various alternatives for a project and
seeks to identify the one which represents the best combination of economic
and environmental costs and benefits.
• What is EIA?
• Evolution of EIA
• History of EIA in India
• The EIA process
• Forms of impact assessment
• Comparative review of EIA procedures and practices
1. What is EIA?
Environment Impact Assessment or EIA can be defined as the study to
predict the effect of a proposed activity/project on the environment. A
decision making tool, EIA compares various alternatives for a project and
seeks to identify the one which represents the best combination of economic
and environmental costs and benefits.
EIA systematically examines both beneficial and adverse consequences of
the project and ensures that these effects are taken into account during project
design. It helps to identify possible environmental effects of the proposed
project, proposes measures to mitigate adverse effects and predicts whether
there will be significant adverse environmental effects, even after the
mitigation is implemented. By considering the environmental effects of the
project and their mitigation early in the project planning cycle, environmental
assessment has many benefits, such as protection of environment, optimum
utilisation of resources and saving of time and cost of the project. Properly
conducted EIA also lessens conflicts by promoting community participation,
informing decision makers, and helping lay the base for environmentally
sound projects. Benefits of integrating EIA have been observed in all stages
of a project, from exploration and planning, through construction, operations,
decommissioning, and beyond site closure.
2. Evolution of EIA
EIA is one of the successful policy innovations of the 20th Century for
environmental conservation. Thirty-seven years ago, there was no EIA but
today, it is a formal process in many countries and is currently practiced in
more than 100 countries. EIA as a mandatory regulatory procedure originated
in the early 1970s, with the implementation of the National Environment
Policy Act (NEPA) 1969 in the US. A large part of the initial development
took place in a few high-income countries, like Canada, Australia, and New
Zealand (1973-74). However, there were some developing countries as well,
which introduced EIA relatively early - Columbia (1974), Philippines
(1978).
The EIA process really took off after the mid-1980s. In 1989, the World
Bank adopted EIA for major development projects, in which a borrower
country had to undertake an EIA under the Bank's supervision (see table 1:
Evaluation and history of EIA).
The MoEF recently notified new EIA legislation in September 2006. The
notification makes it mandatory for various projects such as mining, thermal
power plants, river valley, infrastructure (road, highway, ports, harbours and
airports) and industries including very small electroplating or foundry units
to get environment clearance. However, unlike the EIA Notification of 1994,
the new legislation has put the onus of clearing projects on the state
government depending on the size/capacity of the project.
Certain activities permissible under the Coastal Regulation Zone Act, 1991
also require similar clearance. Additionally, donor agencies operating in
India like the World Bank and the ADB have a different set of requirements
for giving environmental clearance to projects that are funded by them.
4. The EIA process
The stages of an EIA process will depend upon the requirements of the
country or donor. However, most EIA processes have a common structure
and the application of the main stages is a basic standard of good practice.
The environment impact assessment consists of eight steps with each step
equally important in determining the overall performance of the project.
Typically, the EIA process begins with screening to ensure time and
resources are directed at the proposals that matter environmentally and ends
with some form of follow up on the implementation of the decisions and
actions taken as a result of an EIA report. The eight steps of the EIA process
are presented in brief below:
• Scoping: This stage identifies the key issues and impacts that should
be further investigated. This stage also defines the boundary and time
limit of the study.
• Impact analysis: This stage of EIA identifies and predicts the likely
environmental and social impact of the proposed project and evaluates
the significance.
• Mitigation: This step in EIA recommends the actions to reduce and
avoid the potential adverse environmental consequences of
development activities.
• Post monitoring: This stage comes into play once the project is
commissioned. It checks to ensure that the impacts of the project do
not exceed the legal standards and implementation of the mitigation
measures are in the manner as described in the EIA report.