Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

WESTERN TAXIWAY AND STAND DEVELOPMENT WORKS

PACKAGE NO HIAEP-0012

Activity ID Activity Name Original Start Finish 2019 2020


Duration
p Oct Nov Dec Jan Feb
HIAEPSC0012 - Hamad International Airport
A Expansion Project (Package No:012) 182 14-Oct-19 12-Apr-20

Milestone 0 14-Oct-19 14-Oct-19


Contractual Milestone 0 14-Oct-19 14-Oct-19
Contract Commencement 0 14-Oct-19 14-Oct-19
HIAEP-C-CS01-A-1000 Contract Signature 0 14-Oct-19
HIAEP-C-CD01-A-1010 Commencement Date 0 14-Oct-19

Mobilization 72 20-Oct-19 13-Jan-20


Western Taxiway & Stand Development
Developmen Working 72 20-Oct-19 13-Jan-20
HIAEP-C-00-01-1050 Plants & Equipment Mobilization 40 20-Oct-19 05-Dec-19
HIAEP-C-00-01-1040 Installation of Temporary Utilities of Electricity, Fibre, Potable Water, Waste W 24 02-Nov-19 28-Nov-19
HIAEP-C-00-01-1010 Establishment of Site Offices and Accommodation 28 10-Nov-19 12-Dec-19
HIAEP-C-00-01-1020 Establishment of Carpentery Shop, Steel Yard, PMV, Precast 24 28-Nov-19 28-Dec-19
HIAEP-C-00-01-1030 Main Road Access and others (Pedestrian Roads) 28 10-Dec-19 13-Jan-20
General Requirements 30 14-Oct-19 12-Nov-19
HIAEP-C-00-11-1010 General Method Statement 7 14-Oct-19 20-Oct-19
HIAEP-C-00-11-1020 Contractors Representative 7 14-Oct-19 20-Oct-19
HIAEP-C-00-11-1030 Organization Chart 7 14-Oct-19 20-Oct-19
HIAEP-C-00-11-1040 On / Off Site Management Structure 7 14-Oct-19 20-Oct-19
HIAEP-C-00-11-1050 Plant & Equipment Schedule 7 14-Oct-19 20-Oct-19
HIAEP-C-00-11-1060 HSE Manual 7 14-Oct-19 20-Oct-19
HIAEP-C-00-11-1070 Parent Company Guarantee 10 14-Oct-19 23-Oct-19
HIAEP-C-00-11-1080 Management CV's 14 14-Oct-19 27-Oct-19
HIAEP-C-00-11-1090 Logistics Management Plan 14 14-Oct-19 27-Oct-19
HIAEP-C-00-11-1100 Programme of Work 28 14-Oct-19 10-Nov-19
HIAEP-C-00-11-1110 Quality Plan 28 14-Oct-19 10-Nov-19
HIAEP-C-00-11-1120 MS for Verification of Services 28 14-Oct-19 10-Nov-19
HIAEP-C-00-11-1130 Method Statement Register 28 14-Oct-19 10-Nov-19
HIAEP-C-00-11-1140 Traffic Management Plan 30 14-Oct-19 12-Nov-19
HIAEP-C-00-11-1150 Logistic Plan 30 14-Oct-19 12-Nov-19
Permits 61 10-Nov-19 20-Jan-20
Issue of Permits 61 10-Nov-19 20-Jan-20
HIAEP-C-00-08-1000 Environmental permit for the Project 22 10-Nov-19 05-Dec-19
HIAEP-C-00-08-1010 Municipality permit for Demolitions 30 17-Nov-19 23-Dec-19
HIAEP-C-00-08-1020 Kahramma permits for Electricity 18 24-Nov-19 15-Dec-19
HIAEP-C-00-08-1030 Kahramma permits for Water 20 01-Dec-19 25-Dec-19
HIAEP-C-00-08-1040 MOI permits -Traffic diversion 17 08-Dec-19 29-Dec-19
HIAEP-C-00-08-1050 Dewatering Permit 25 15-Dec-19 14-Jan-20
HIAEP-C-00-08-1060 Communications Regulatory Authority(CRA) 16 23-Dec-19 11-Jan-20
HIAEP-C-00-08-1070 Qatar National Broad Network(QNBN) 18 31-Dec-19 20-Jan-20
Engineering 182 14-Oct-19 12-Apr-20
Method of Statement 47 12-Dec-19 27-Jan-20
Traffic Management 32 12-Dec-19 12-Jan-20

Remaining Level of Effort Critical Remaining Work Page 1 of 4 Date: 27-Oct-19


Actual Work Milestone
Doc. Ref. No.: 25045-C4230-11-33S-X-00001
Remaining Work
Subject: 90 days lookahead schedule
WESTERN TAXIWAY AND STAND DEVELOPMENT WORKS
PACKAGE NO HIAEP-0012

Activity ID Activity Name Original Start Finish 2019 2020


Duration
p Oct Nov Dec Jan Feb
HIAEP-C-00-09-1000 Traffic Management-Prepare & submit to Engineer 5 12-Dec-19 17-Dec-19
HIAEP-C-00-09-1010 Traffic Management- Engineer Review and comments 17 19-Dec-19 12-Jan-20
Site clearance & Demolition 29 23-Dec-19 20-Jan-20
HIAEP-C-00-09-1040 Site clearance-Prepare & submit to Engineer 5 23-Dec-19 28-Dec-19
HIAEP-C-00-09-1050 Site clearance- Engineer Review and comments 17 29-Dec-19 20-Jan-20
Earthworks 29 26-Dec-19 23-Jan-20
HIAEP-C-00-09-1080 Earthworks-Prepare & submit to Engineer 5 26-Dec-19 01-Jan-20
HIAEP-C-00-09-1090 Earthworks- Engineer Review and comments 17 01-Jan-20 23-Jan-20
Stockpile 5 07-Jan-20 12-Jan-20
HIAEP-C-00-09-1120 Stockpile-Prepare & submit to Engineer 5 07-Jan-20 12-Jan-20
Dewatering Works 30 29-Dec-19 27-Jan-20
HIAEP-C-00-09-1880 Dewatering works-Prepare & submit to Engineer 5 29-Dec-19 02-Jan-20
HIAEP-C-00-09-1890 Dewatering works- Engineer Review and comments 17 02-Jan-20 27-Jan-20
Design 182 14-Oct-19 12-Apr-20
PCA Point of Use Unit, Underground Ducting
Du and Pop-up Pit 57 21-Nov-19 16-Jan-20
HIAEP-C-00-05-1040 Preparation and Submission The Design of PCA Point of Use Unit, Undergrou 30 21-Nov-19 28-Dec-19
HIAEP-C-00-05-1050 Design Approval of PCA Point of Use Unit, Underground Ducting and Pop-up 15 29-Dec-19 16-Jan-20
Fire Water Storage Tank 46 21-Nov-19 06-Jan-20
HIAEP-C-00-05-1060 Preparation and Submission The Design of Water Tank 20 21-Nov-19 15-Dec-19
HIAEP-C-00-05-1070 Design Approval of Water Tank 15 15-Dec-19 06-Jan-20
Fire Pump House 45 02-Dec-19 16-Jan-20
HIAEP-C-00-05-1080 Preparation and Submission The Design of Fire Pump House 20 02-Dec-19 26-Dec-19
HIAEP-C-00-05-1090 Design Approval of Fire Pump House 15 26-Dec-19 16-Jan-20
GPU Pop-up Pit / 400HZ Ground Power U
Unit (GPU) 57 27-Nov-19 23-Jan-20
HIAEP-C-00-05-1100 Preparation and Submission The Design of 400HZ Ground Power Unit (GPU 30 27-Nov-19 02-Jan-20
HIAEP-C-00-05-1110 Design Approval of 400HZ Ground Power Unit (GPU)/Pop-up Pit 15 02-Jan-20 23-Jan-20
HML 51 09-Dec-19 29-Jan-20
HIAEP-C-00-05-1120 Preparation and Submission The Design of HML 25 09-Dec-19 08-Jan-20
HIAEP-C-00-05-1130 Design Approval of HML 15 08-Jan-20 29-Jan-20
Temporary Airside/Landside Fencing and
an Surveillance Infrastructure 25 12-Dec-19 12-Jan-20
HIAEP-C-00-05-1140 Preparation and Submission The Design of Temporary Airside/Landside Fenc 25 12-Dec-19 12-Jan-20
VDGS (Visual Docking Guidance System
System) 30 15-Dec-19 20-Jan-20
HIAEP-C-00-05-1160 Preparation and Submission The Design of VDGS (Visual Docking Guidance 30 15-Dec-19 20-Jan-20
SNI (Server Name Indication) 30 22-Dec-19 26-Jan-20
HIAEP-C-00-05-1180 Preparation and Submission The Design of SNI (Server Name Indication) 30 22-Dec-19 26-Jan-20
66/11kV Transformers 60 24-Dec-19 04-Mar-20
HIAEP-C-00-05-1200 Preparation and Submission The Design of 66//11kV Transformers 60 24-Dec-19 04-Mar-20
General Aviation Stormwater System Improvements
Imp 40 02-Jan-20 19-Feb-20
HIAEP-C-00-05-1220 Preparation and Submission The Design of General Aviation Stormwater Syst 40 02-Jan-20 19-Feb-20
66kV GIS Insulated Switchgear 60 08-Jan-20 19-Mar-20
HIAEP-C-00-05-1240 Preparation and Submission The Design of 66kV GIS Insulated Switchgear 60 08-Jan-20 19-Mar-20
WUZ Pumping Station 50 22-Dec-19 19-Feb-20
HIAEP-C-00-05-1380 Preparation and Submission The Design of WUZ Pumping Station 50 22-Dec-19 19-Feb-20
MOI Tetra Mast 40 22-Dec-19 06-Feb-20
HIAEP-C-00-05-1400 Preparation and Submission The Design of MOI Tetra Mast 40 22-Dec-19 06-Feb-20
Remaining Level of Effort Critical Remaining Work Page 2 of 4 Date: 27-Oct-19
Actual Work Milestone
Doc. Ref. No.: 25045-C4230-11-33S-X-00001
Remaining Work
Subject: 90 days lookahead schedule
WESTERN TAXIWAY AND STAND DEVELOPMENT WORKS
PACKAGE NO HIAEP-0012

Activity ID Activity Name Original Start Finish 2019 2020


Duration
p Oct Nov Dec Jan Feb
General Supply and Fire Water Substations
Substatio 36 28-Dec-19 08-Feb-20
HIAEP-C-00-05-1420 Preparation and Submission The Design of General Supply and Fire Water S 36 28-Dec-19 08-Feb-20
Fire Water Pumping Station 40 28-Dec-19 13-Feb-20
HIAEP-C-00-05-1440 Preparation and Submission The Design of Fire Water Pumping Station 40 28-Dec-19 13-Feb-20
Terminal Pumping Station 40 02-Jan-20 19-Feb-20
HIAEP-C-00-05-1460 Preparation and Submission The Design of Terminal Pumping Station 40 02-Jan-20 19-Feb-20
Fire Water Hydrant Pump Building 40 27-Nov-19 14-Jan-20
HIAEP-C-00-05-1540 Preparation and Submission The Design of Fire Water Hydrant Pump Building 40 27-Nov-19 14-Jan-20
AGL Constant Current Regulators (CCR'S)
(CCR' & Control 40 12-Dec-19 29-Jan-20
HIAEP-C-00-05-1560 Preparation and Submission The Design of AGL Constant Current Regulators 40 12-Dec-19 29-Jan-20
AGL South West Substation Facility Code
Cod D1000 (D1200) 40 25-Dec-19 10-Feb-20
HIAEP-C-00-05-1580 Preparation and Submission The Design of AGL South West Substation Facil 40 25-Dec-19 10-Feb-20
ATC Virtual Tower Cameras Connection backup ACT Building/Fire Stations 40 02-Jan-20 19-Feb-20
HIAEP-C-00-05-1600 Preparation and Submission The Design of ATC Virtual Tower Cameras Conn 40 02-Jan-20 19-Feb-20
Grounding and Lightning Protection 40 06-Jan-20 23-Feb-20
HIAEP-C-00-05-1620 Preparation and Submission The Design of Grounding and Lightning Protectio 40 06-Jan-20 23-Feb-20
Permanent Fencing Afer Issuance The D
Design of PIDPS 180 14-Oct-19 12-Apr-20
HIAEP-C-00-05-1820 Employer Design work for PIDPS 180 14-Oct-19 12-Apr-20
Design Verification 68 10-Nov-19 29-Jan-20
Western Landside Highway - South (MS Section1) 20 19-Dec-19 12-Jan-20
HIAEP-C-00-05-1880 Design Verification: Landside Highway - South 20 19-Dec-19 12-Jan-20
Western Develpoment 20 12-Dec-19 06-Jan-20
HIAEP-C-00-05-1910 Design Verification: Western Development Landside Infrastructure 20 12-Dec-19 06-Jan-20
Water Tank 20 10-Nov-19 02-Dec-19
HIAEP-C-00-05-1940 Design Verification: Water Tank 20 10-Nov-19 02-Dec-19
Airside GSE Roads 20 31-Dec-19 23-Jan-20
HIAEP-C-00-05-1930 Design Verification: Airside GSE Roads 20 31-Dec-19 23-Jan-20
Western Fuel Farm 20 19-Dec-19 12-Jan-20
HIAEP-C-00-05-1960 Design Verification: Western Fuel Farm Hydrant Pumps 20 19-Dec-19 12-Jan-20
Surface Water Drainage System 20 12-Dec-19 06-Jan-20
HIAEP-C-00-05-1970 Design Verification: Surface Water Drainage 20 12-Dec-19 06-Jan-20
Midfield Tunnel 20 06-Jan-20 29-Jan-20
HIAEP-C-00-05-1990 Design Verification: Midfield Tunnel Portal Reconstruction 20 06-Jan-20 29-Jan-20
Foul Water System 20 12-Dec-19 06-Jan-20
HIAEP-C-00-05-2000 Design Verification: Foul Pumping Station 2 20 12-Dec-19 06-Jan-20
Shop Drawing 36 06-Jan-20 18-Feb-20
Western Develpoment 25 06-Jan-20 04-Feb-20
HIAEP-C-00-07-1110 Shop Drawing: Western Development Landside Infrastructure 25 06-Jan-20 04-Feb-20
Surface Water Drainage System 36 06-Jan-20 18-Feb-20
HIAEP-C-00-07-1200 Shop Drawing: Surface Water Drainage 36 06-Jan-20 18-Feb-20
Procurement 46 12-Dec-19 27-Jan-20
Local Materials 45 12-Dec-19 26-Jan-20
Base Course 33 12-Dec-19 13-Jan-20
HIAEP-C-00-06-1000 Technical material Submital of Base Course 3 12-Dec-19 16-Dec-19

Remaining Level of Effort Critical Remaining Work Page 3 of 4 Date: 27-Oct-19


Actual Work Milestone
Doc. Ref. No.: 25045-C4230-11-33S-X-00001
Remaining Work
Subject: 90 days lookahead schedule
WESTERN TAXIWAY AND STAND DEVELOPMENT WORKS
PACKAGE NO HIAEP-0012

Activity ID Activity Name Original Start Finish 2019 2020


Duration
p Oct Nov Dec Jan Feb
HIAEP-C-00-06-1010 Engineer Review and Comments of Base Course 12 16-Dec-19 02-Jan-20
HIAEP-C-00-06-1020 Resubmit Base Course Incorporate Comments 10 02-Jan-20 13-Jan-20
UPVC Ducts 18 08-Jan-20 26-Jan-20
HIAEP-C-00-06-1700 Technical material Submital of UPVC Ducts 3 08-Jan-20 12-Jan-20
HIAEP-C-00-06-1710 Engineer Review and Comments of UPVC Ducts 12 08-Jan-20 26-Jan-20
Traffic Signage 18 08-Jan-20 26-Jan-20
HIAEP-C-00-06-1810 Technical Submital of Traffic Signage 6 08-Jan-20 15-Jan-20
HIAEP-C-00-06-1820 Engineer Review and Comments of Traffic Signage 12 08-Jan-20 26-Jan-20
Long Lead Items (International Supply) 21 06-Jan-20 27-Jan-20
Stand Equipment 18 08-Jan-20 26-Jan-20
VDGS Equipment 6 08-Jan-20 15-Jan-20
HIAEP-C-00-06-1870 Technical Submital of VDGS Equipment 6 08-Jan-20 15-Jan-20
Pre-Conditioned Air (PCA) Units - Out Door
Do Type 18 08-Jan-20 26-Jan-20
HIAEP-C-00-06-2050 Technical Submital of Fuel Main Pipes 6 08-Jan-20 15-Jan-20
HIAEP-C-00-06-2060 Engineer Review and Comments of Fuel Main Pipes 12 08-Jan-20 26-Jan-20
HIAEP-C-00-06-2070 Resubmit Fuel Main Pipes Incorporate Comments 10 08-Jan-20 19-Jan-20
Pre Formed Strakes of Water Tank 21 06-Jan-20 27-Jan-20
HIAEP-C-00-06-2830 Technical Submital of Pre Formed Strakes 3 06-Jan-20 09-Jan-20
HIAEP-C-00-06-2840 Engineer Review and Comments of Pre Formed Strakes 12 09-Jan-20 27-Jan-20
Construction 92 03-Dec-19 22-Mar-20
Landside Highway 32 04-Dec-19 12-Jan-20
Site Preparation 32 04-Dec-19 12-Jan-20
Landside Highway 32 04-Dec-19 12-Jan-20
HIAEP-C-70-01-1350 Access Permit to Site by the Engineer - Western Landside Highway - South 14 04-Dec-19 22-Dec-19
HIAEP-C-70-01-1320 Site Surveying and Setting Out - Western Landside Highway - South 6 22-Dec-19 29-Dec-19
HIAEP-C-70-01-1340 GPR Scanning and Verification of Existing U/G Services - Western Landside H 5 29-Dec-19 04-Jan-20
HIAEP-C-70-01-1330 Site Clearance - Western Landside Highway - South 7 04-Jan-20 12-Jan-20
Western Central Utility Plant Zone 92 03-Dec-19 22-Mar-20
Site Preparation 32 03-Dec-19 11-Jan-20
Western Utility Zone 32 04-Dec-19 11-Jan-20
HIAEP-C-70-01-1470 Access Permit to Site by the Engineer - Western Central Utility Plant Zone 14 04-Dec-19 22-Dec-19
HIAEP-C-70-01-1440 Site Surveying and Setting Out - Western Central Utility Plant Zone 6 22-Dec-19 29-Dec-19
HIAEP-C-70-01-1460 GPR Scanning and Verification of Existing U/G Services - Western Central Ut 5 29-Dec-19 04-Jan-20
HIAEP-C-70-01-1450 Site Clearance - Western Central Utility Plant Zone 7 04-Jan-20 11-Jan-20
Western Fuel Farm 32 03-Dec-19 11-Jan-20
HIAEP-C-70-01-1510 Access Permit to Site by the Engineer - Western Fuel Farm 14 03-Dec-19 21-Dec-19
HIAEP-C-70-01-1480 Site Surveying and Setting Out - Western Fuel Farm 6 21-Dec-19 28-Dec-19
HIAEP-C-70-01-1500 GPR Scanning and Verification of Existing U/G Services - Western Fuel Farm 5 28-Dec-19 02-Jan-20
HIAEP-C-70-01-1490 Site Clearance - Western Fuel Farm 7 02-Jan-20 11-Jan-20
Earthworks 66 04-Jan-20 22-Mar-20
Western Utility Zone 66 04-Jan-20 22-Mar-20
HIAEP-C-20-08-1220 Excavation & Disposal to Dumping Areas & Temp Stock Piles - Western Cent 66 04-Jan-20 22-Mar-20

Remaining Level of Effort Critical Remaining Work Page 4 of 4 Date: 27-Oct-19


Actual Work Milestone
Doc. Ref. No.: 25045-C4230-11-33S-X-00001
Remaining Work
Subject: 90 days lookahead schedule

You might also like