Method Statement
For
Installation of Vent Piping
And Accessories
Table of Contents
DESCRIPTION PAGE
i. Front Page 1
ii. Table of Contents 2
1. Purpose 3
2. Scope 3
3. Definition 3
4. Reference Documents 4
5. Tools & Equipments 4
6. Manpower 5
7. Responsibilities 5
8. Material Inspection Storage 6
9. Construction Sequence and Methodology 6
10. Jointing Method 7
11. Inspection / Testing 7
12. Health, Safety and Environment 8
13. QC Approval Report Requirements 10
14. Attachments
14.1 Risk Assessment
14.2 Inspection and Test Plan
14.3 Installation Check List
1.0 Purpose
The purpose of this Method Statement is to describe the details used and controls to
be carried out for the installation of Copper pipes, fittings and accessories Vent
Piping System to ensure that it complies with Project requirements, Project
Specifications (Section 22-1005 Part 2) and standards.
2.0 Scope
This Method Statement is applicable to all pipes, fittings and accessories for Vent
Piping System at Doha Convention Center & Tower Project.
Manpower and Equipments shall be organized to meet the schedule as per approved
Construction program.
3.0 Definition
3.1 “Abbreviation “
QAQC - Quality Assurance Quality Control
MS - Method Statement
MEP - Mechanical, Electrical, Plumbing
RFIA - Request for Inspection & Approval
MIR - Materials Inspection Request
ITP - Inspection and Test Plan
TBT - Tool Box Talk
3.2 “Approved” or “Approval”
“Approved” or “Approvals” means approved in writing by the applicable Engineers
Assistant acting within the scope of their delegate authority.
3.5 “Materials”
“Materials” means all items covering the materials or equipments delivered to site
that must be incorporated in the project.
5.2 Tools
5.2.1 Scaffolding with wheels
5.2.2 Brazing tools
5.2.3 Hack saw frame
5.2.4 Chalk line / marking pen
5.2.5 Measuring Tape
5.2.6 Pipe cutter
5.2.7 Screw Driver set
5.2.8 Cleaning Pad/Brushes
5.2.9 Drilling Machine
5.2.10 Sand paper/ steel wool
5.2.11 Ladders
6.0 Manpower
6.1 Staff:
6.1.1 Construction Manager
6.1.2 Site Engineer
6.1.3 Supervisor
Method Statement – Installation of Vent Piping and Accessories
DOCUMENT NUMBER: ED-D-M-D-A-GN-0003-00
Page 4
DOHA
CONVENTION
CENTER &
TOWER
PROJECT
6.2 Labour
6.2.1 Foreman
6.2.2 Trade workers
6.2.3 Helpers / Labours
6.2.4 Drivers
7.0 Responsibilities
7.1 The Project Manager shall be responsible for the overall construction,
coordination site activities and implementation this method statement.
7.2 The Construction Manager, Site Engineers, Supervisors and Foremen shall
implement and execute this Method Statement.
7.3 The Material Controller shall be responsible for receiving all materials on site
warehouse.
7.4 Site Engineer / Supervisor shall check all the materials as per approved material
submittal & manufacturer’s recommendation prior to installation and shall be
responsible for the installation as per approved shop drawings.
7.5 Safety Officer shall ensure that appropriate / necessary measures are in place at
work location to avoid any unexpected accidents / events.
7.6 QAQC Engineer / Inspector shall be responsible for carrying out inspections for
the materials delivered on site. He shall document such inspections.
7.7 QAQC Engineer / Inspector shall monitor the installation activities progressively
and shall record all deviation from specification in a form of snags list or non-
conformance notification.
10.3.3 Place the Neoprene of the sleeve on the end of the pipe or fitting and
place the stainless steel shield on the component.
10.3.4 Insert the other pipe or fitting to the neoprene sealing sleeve and
make sure that both sides are firmly seated in the couplings.
10.3.5 Slide the stainless steel shield over the neoprene sleeve and tighten
the clamp assembly by using screwdriver until the two sided are firmly
fixed.
11.2 After Site Engineer & Supervisor completed their inspection and testing , RFIA
shall be submitted to QAQC Department who shall check and process the
documents to have completed work inspected by Supervision Consultant for
their approval.
11.4 Before applying the gravity test, ensure that all safety precautions are in
place.
11.5 After ensuring that safety precautions are in place, check that all pipe ends
are closed with test plugs except for water filling point.
11.6 Clean the pipes for any dust or debris on the joint surface for easy
identification of leak if there is any.
11.7 Applying /conducting gravity leak test for Vertical risers and horizontal
installation have to maintain 0.3 Bar pressure for duration of 4 hours. Additional
3 meters length of pipe should be provided on the test pipe. Repair if any leak
occurs prior for Submittal of RFIA .
Method Statement – Installation of Vent Piping and Accessories
DOCUMENT NUMBER: ED-D-M-D-A-GN-0003-00
Page 8
DOHA
CONVENTION
CENTER &
TOWER
PROJECT
12.4 Housekeeping
Housekeeping shall be maintained by all personnel working at site.
Housekeeping for fabrication and installation shall be as per project safety
plan and ETA-Debbas Safety Manual.
12.5 Signage
All necessary safety warning and caution signs shall be displayed at work
locations.
12.6 Environment
MSDS for COSHH materials shall be kept by the storekeeper and a copy given
To HSE Dept. The MSDS shall be followed as per Qatar labour law.
Waste Disposal shall be segregated and disposed by a Certified
Subcontractor
And send it to the municipality stockyard for COSH material as per Qatar law.