Professional Documents
Culture Documents
L.P.B-32 Install of The Nitrogen Vessel
L.P.B-32 Install of The Nitrogen Vessel
LIFT PLAN Load & offload of the nitrogen vessel and install on the base it
PTW #
TITLE
METHODOLOGY: The questionnaire must be answered from top to bottom. Every question has to be answered.
The first question that is answered “Yes” identifies the lift category indicated in the right columns.
2 Does the Lift exceed 80% of the crane capacity on working radius? √
Is the fixed equipment (Overhead crane, Runway beams)used above 90% of its
3 √
capacity (including weight contingencies and dynamic factor)
Has the load to travel over process area or to be lifted over or close to live facilities
4 √
/wells?
Does the lifting operation require the design, the fabrication or the use of special
6 √
lifting equipment (Special tool, spreader bar)?
7 Does the lift have limited boom clearance (i.e. less than 1 m)? √
Is the lift subject to proximity hazard (Public road, overhead power line, underground
8 √
facilities)?
12 Does the lift over 20 tons requiring walking the load with a crawler crane? √
17 Does the load have an offset center of gravity, (Non symmetrical rigging) √
None of the above factors apply, the load is pre slung or easy to sling without external
21 √ ROUTINE
ROUTINE
factors that complicate the operations.
Risk Assessment Performed: YES Diagram of Lifting Operations Attached Slinging Method Attached
Lay down
Crane Position Area
SIDE VIEEW
SIDE VIEEW
SIDE VIEEW
SIDE VIEEW
18.6 M
SIDE VIEEW
8M