Annual Implementation Plan
Annual Implementation Plan
Purchased science
apparatus and equipment
Schedule of review
classes with specified Conduct review classes twice a
teachers to handle the week.
classes BLGU
To increase NAT Students
Increase NAT June-October MOOE
Performance of the Teachers 30,000.00
Performance Educational tour of 2022 PTA Funds
students. Teachers and students' Principal
teachers and students to
educational tour to schools or
different schools and
places once a year.
places
KRA 2: LEARNING ENVIRONMENT
Reproduce reading materials
for the students.
School-based Students,
Symposium/ Orientation School Funds
Child Protection Educate both teachers Teachers,
0% Bullying incidence Jan.- Dec MOOE PLGU
and Anti- and students about Anti- LGU, GPTA 10,000.00
in school 2022 BLGU
Bullying bullying program. and DSWD
Anti-Bullying Campaign GPTA FUNDS
Program
Orientation on the proper
To provide clean water disposal and segregation of
Constructed Comfort
and practice hygiene and garbage
rooms
sanitation in school.
Implementation School Head
Whole Year MOOE
of PROJECT Acquired clean water Teachers 15,390.00
Round PTA Fund
WINS source Sudents Parents
Handwashing, toothbrushing;
waste segragating
Provided hand washing
facility
To implement basic
Provision of • Teachers • June - Dec MOOE
computer education for 100,000.00
Computer Units School Head 2022 Fund Raising
students.
MOOE, PTA,
To ensure safety and Skilled Masons NGO,LGU &
Establishment of security of the school Carpenters Fund Raising
On-going Constrution of
Concrete and its properties and Concrete Parameter Fence School Head Jan-Dec 2022 100,000.00 Other sources
Perimeter Fence Perimeter Fence
refrain students from
cutting classes.
To maintain cleanliness
and sanitation of the Mason and
Establishment of school.
Established Material Laborers MOOE, SSG
Concrete Material
Recovery Facility
Construction of MRF School Head
Jan-Dec 2022 25,000.00
Recovery Facility Funds
To create an income Fund Raising
generating project Other sources
Skilled Masons
and carpenters
Major repairs of Make program of works for repair Principal PTA, MOOE,
To ensure the safety of the Repaired school
school buildings, of school building. Finance Officers LGU, NGO &
students from falling rotten buildings, ceilings and Jan-Dec 2022 250,000.00
ceilings and Purchase materials needed for the Fund Raising
debris of the building. roofing
roofing project.
Skilled Masons
Make program of works for the and Carpenters
To properly channel the
Construction of rain water so as to avoid
establishment of a drainage Principal PTA, MOOE,
Constructed school system. Finance Officers Jan-Dec 2022 LGU, NGO &
School drainage seepage of rooms that
drainage system
100,000.00 Fund Raising
system cause diseases, electrical
shock and discomfort.
Purchase the materials needed.
Hired
Installation and To avoid the risk of health
Repairperson PTA, MOOE,
Repair of problems and negative Installed and repaired Installation and Repair of
Classroom effects on learning among classroom ventilator
School Head Jan-Dec 2022 50,000.00 LGU, NGO &
Classroom Ventilation Fund Raising
Ventilation students.
Installation of Skilled Masons
To provide potable and PTA, MOOE,
Senior High Installation of Senior High Installation of Senior High and carpenters
School Water
sufficient water in CR’s School water system School water system Principal
Jan-Dec 2022 20,000.00 LGU, NGO &
and façade cleanliness Fund Raising
System Finance Officers
Skilled Masons
and Carpenters
To provide clean and
Repair of School School Head
hygienic rooms for Complete repair of school Repair the school CRs and
CRs, Lavatory
students and teachers' CR’s and septic tanks
Jan-Dec 2022 50,000.00 MOOE
and Septic Tank septic tanks
personal necessities.
Reimbursement of Training
Expenses
Principal
Ensure that the planned
• MOOE Liquidation • Monthly and On - time Book keeper
MOOE budget is disbursed
Report Liquidation Report Disbursing
Jan-Dec 2022 5,000.00 MOOE
properly
Students
To intensify the 100% MOOE
Teachers
preparation for the opening • Prepared school NGO’s
Conduct of Parents
Brigada Eskwela
of classes ensuring the • Attendance Conduct f Brigada Eskwela
School Head
May '2022 5,000.00 LGU
most conducive • MOV’s PTA
Bookkeeper
environment for learnig
GPP Coordinator
To decrease the number of TLE teachers School funds
• Sustained school feeding
Implementation wasted and severely wasted Students MOOE
program Implement GPP (Gulayan Ng
of GPP (Gulayan students and teach students
• MOV’s Paaralan Program)
School Head Jan-Dec 2022 56,260.00 Dept. of
ng Paaralan) the importance of Dept. of Agriculture
agriculture to sustain life. Agriculture LGU
Purchased of
Purchased materials for Purchase materials and orient School Head
Survival Kit for To implement disaster risk
Disaster reduction management.
survival kit in case of students for the use of such Students Jan-Dec 2022 16,600.00 MOOE
emergency situation. materials. Teachers
Preparedness
Skilled workers
Repair and
To provide the teachers a (masons and
place to do their works, carpenters)
Improvement of Constructed Faculty Room Construction of Facuty Office Jan-Dec 2022 50,000.00 MOOE
School Head
Faculty Office preparations and to safe
keep the students’ outputs.