Professional Documents
Culture Documents
Celec Proj
Celec Proj
CE 12
CE LAWS, CODES AND CONTRACTS
Submitted By:
Cerda, Queen Mary C.
Galura, Mariane Joyce L.
Jaucian, John Michael P.
Puga, Jefferson S.
Madarang Jr., Grover S.
Nakila, Zyril John E.
San Juan, Michael Angelo M.
Soliman, Rome Jigger C.
Venadas, Marzela Sophia A.
Villaruel, Francis L.
Submitted To:
Engr. Mary Grace Tutor, RCE
Date Submitted:
December 03, 2022
1
RA 9184: GOVERNMENT PROCUREMENT LAW
Preparation of Pre-
Bidding Advertising of Pre-Bid
Procurement
Documents Invitation to Bid Conference
Conference
With this process, first and foremost part is the contract documents or
bidding documents.
2
RA 9184: GOVERNMENT PROCUREMENT LAW
a) ABC;
c) Eligibility Requirements;
17.2. The specifications and other terms in the Bidding Documents shall
reflect the necessary specifications required to meet the needs of the
Procuring Entity in clear and unambiguous terms.
3
RA 9184: GOVERNMENT PROCUREMENT LAW
make the Bidding Documents available from the time the Invitation to Bid /
Request for Expression of Interest is first advertised/posted until the deadline
for the submission and receipt of bids. (a)
17.4. Bidders may be asked to pay a fee to recover the cost for the
preparation and development of the Bidding Documents pursuant to the
Guidelines on the Sale of Bidding Documents. The Procuring Entity shall post
the complete Bidding Documents at its website and the PhilGEPS website
from the time the Invitation to Bid/Request for Expression of Interest is
advertised. Bidding Documents may be downloaded from any of the said
websites: Provided, that upon submission of their bids, the bidders shall pay
the applicable fee, if required. The Bidding Documents may also be secured
from the BAC Secretariat upon payment of the corresponding fee, if required.
(a)
4
RA 9184: GOVERNMENT PROCUREMENT LAW
a) Confirm the description and scope of the contract, the ABC, and contract
duration;
b) Ensure that the procurement is in accordance with the PPMP and APP;
5
RA 9184: GOVERNMENT PROCUREMENT LAW
___________________________________________________________________________
______
CONTRACT AGREEMENT
THIS AGREEMENT, made this [insert date] day of [insert month], [insert year]
between [name and address of PROCURING ENTITY] (hereinafter called the “Entity”) and
[name and address of Contractor] (hereinafter called the “Contractor”).
WHEREAS, the Entity is desirous that the Contractor execute [name and
identification number of contract] (hereinafter called “the Works”) and the Entity has
accepted the Bid for [contract price in words and figures in specified currency] by the
Contractor for the execution and completion of such Works and the remedying of any
defects therein.
6
RA 9184: GOVERNMENT PROCUREMENT LAW
1. In this Agreement, words and expressions shall have the same meanings as are
respectively assigned to them in the Conditions of Contract hereinafter referred
to.
i. Drawings/Plans;
ii. Specifications;
c. Performance Security;
e. Other contract documents that may be required by existing laws and/or the
Procuring Entity concerned in the PBDs. Winning bidder agrees that
additional contract documents or information prescribed by the GPPB
that are subsequently required for submission after the contract
execution, such as the Notice to Proceed, Variation Orders, and Warranty
Security, shall likewise form part of the Contract.
3. In consideration for the sum of [total contract price in words and figures] or such
other sums as may be ascertained, [Named of the bidder] agrees to [state the
object of the contract] in accordance with his/her/its Bid.
4. The [Name of the procuring entity] agrees to pay the above-mentioned sum in
accordance with the terms of the Bidding.
IN WITNESS whereof the parties thereto have caused this Agreement to be executed
the day and year first before written.
7
RA 9184: GOVERNMENT PROCUREMENT LAW
for:
for:
[Insert Name of Supplier]
[Insert Procuring Entity]
Acknowledgment
8
RA 9184: GOVERNMENT PROCUREMENT LAW
Subcontracts
9
RA 9184: GOVERNMENT PROCUREMENT LAW
The GCC in Section IV, read in conjunction with the SCC in Section V
and other documents listed therein, should be a complete document
expressing all the rights and obligations of the parties.
Interpretation
10
RA 9184: GOVERNMENT PROCUREMENT LAW
a) Contract Agreement;
c) Instructions to Bidders;
g) Specifications;
i) Drawings.
Similar to the Section III. Bid Data Sheet, the clauses in this Section
are intended to assist the Procuring Entity in providing contract-specific
information in relation to corresponding clauses in the GCC.
11
RA 9184: GOVERNMENT PROCUREMENT LAW
Bid Form
Date: ___________________________
IB1 No: __________________________
(a) We have examined and have no reservation to the Bidding Documents, including
Addenda, for the Contract [insert name of contract];
(b) We offer to execute the Works for this Contract in accordance with the Bid and Bid Data
Sheet, General and Special Conditions of Contract accompanying this Bid;
The total price of our Bid, excluding any discounts offered below is: [insert information];
The discounts offered and the methodology for their application are: [insert
information];
(c) Our Bid shall be valid for a period of [insert number] days from the date fixed for the Bid
submission deadline in accordance with the Bidding Documents, and it shall remain
binding upon us and may be accepted at any time before the expiration of that period;
(d) If our Bid is accepted, we commit to obtain a Performance Security in the amount of
[insert percentage amount] percent of the Contract Price for the due performance of
the Contract;
(e) Our firm, including any subcontractors or suppliers for any part of the Contract, have
nationalities from the following eligible countries: [insert information];
(f) We are not participating, as Bidders, in more than one Bid in this bidding process, other
than alternative offers in accordance with the Bidding Documents;
(g) Our firm, its affiliates or subsidiaries, including any subcontractors or suppliers for any
part of the Contract, has not been declared ineligible by the Funding Source;
1
If ADB, JICA and WB funded projects, use IFB.
12
RA 9184: GOVERNMENT PROCUREMENT LAW
(h) We understand that this Bid, together with your written acceptance thereof included in
your notification of award, shall constitute a binding contract between us, until a formal
Contract is prepared and executed; and
(i) We understand that you are not bound to accept the Lowest Calculated Bid or any
other Bid that you may receive.
(k) We acknowledge that failure to sign each and every page of this Bid Form, including
the Bill of Quantities, shall be a ground for the rejection of our bid.
Name:
Signed:
Date: ___________
13
RA 9184: GOVERNMENT PROCUREMENT LAW
THIS AGREEMENT, made this [insert date] day of [insert month], [insert year] between
[name and address of PROCURING ENTITY] (hereinafter called the“Entity”) and [name and address of
Contractor] (hereinafter called the “Contractor”).
WHEREAS, the Entity is desirous that the Contractor execute [name and identification
number of contract] (hereinafter called “the Works”) and the Entity has accepted the Bid for [insert
the amount in specified currency in numbers and words] by the Contractor for the execution and
completion of such Works and the remedying of any defects therein.
1. In this Agreement, words and expressions shall have the same meanings as are
respectively assigned to them in the Conditions of Contract hereinafter referred to.
2. The following documents shall be attached, deemed to form, and be read and
construed as integral part of this Agreement, to wit:
4. The Entity hereby covenants to pay the Contractor in consideration of the execution
and completion of the Works and the remedying of defects wherein, the Contract
Price or such other sum as may become payable under the provisions of this
Contract at the times and in the manner prescribed by this Contract.
14
RA 9184: GOVERNMENT PROCUREMENT LAW
IN WITNESS whereof the parties thereto have caused this Agreement to be executed the day
and year first before written.
________________________________________________
_____________________________________________
[Addendum showing the corrections, if any, made during the Bid evaluation should be attached with
this agreement]
15
Omnibus Sworn Statement
AFFIDAVIT
I, [Name of Affiant], of legal age, [Civil Status], [Nationality], and residing at [Address of Affiant],
after having been duly sworn in accordance with law, do hereby depose and state that:
3. [Name of Bidder] is not “blacklisted” or barred from bidding by the Government of the
Philippines or any of its agencies, offices, corporations, or Local Government Units, foreign
government/foreign or international financing institution whose blacklisting rules have been
recognized by the Government Procurement Policy Board;
5. [Name of Bidder] is authorizing the Head of the Procuring Entity or its duly authorized
representative(s) to verify all the documents submitted;
If a sole proprietorship: The owner or sole proprietor is not related to the Head of the
Procuring Entity, members of the Bids and Awards Committee (BAC), the Technical Working
Group, and the BAC Secretariat, the head of the Project Management Office or the end-user
unit, and the project consultants by consanguinity or affinity up to the third civil degree;
16
If a partnership or cooperative: None of the officers and members of [Name of Bidder] is
related to the Head of the Procuring Entity, members of the Bids and Awards Committee
(BAC), the Technical Working Group, and the BAC Secretariat, the head of the Project
Management Office or the end-user unit, and the project consultants by consanguinity or
affinity up to the third civil degree;
If a corporation or joint venture: None of the officers, directors, and controlling stockholders
of [Name of Bidder] is related to the Head of the Procuring Entity, members of the Bids and
Awards Committee (BAC), the Technical Working Group, and the BAC Secretariat, the head
of the Project Management Office or the end-user unit, and the project consultants by
consanguinity or affinity up to the third civil degree;
7. [Name of Bidder] complies with existing labor laws and standards; and
8. [Name of Bidder] is aware of and has undertaken the following responsibilities as a Bidder:
c) Made an estimate of the facilities available and needed for the contract to be bid, if any;
and
d) Inquire or secure Supplemental/Bid Bulletin(s) issued for the [Name of the Project].
9. [Name of Bidder] did not give or pay directly or indirectly, any commission, amount, fee, or
any form of consideration, pecuniary or otherwise, to any person or official, personnel or
representative of the government in relation to any procurement project or activity.
IN WITNESS WHEREOF, I have hereunto set my hand this __ day of ___, 20__ at ____________,
Philippines.
_____________________________________
Bidder’s Representative/Authorized Signatory
SUBSCRIBED AND SWORN to before me this ___ day of [month] [year] at [place of
execution], Philippines. Affiant/s is/are personally known to me and was/were identified by me
through competent evidence of identity as defined in the 2004 Rules on Notarial Practice (A.M. No.
02-8-13-SC). Affiant/s exhibited to me his/her [insert type of government identification card used],
with his/her photograph and signature appearing thereon, with no. ________ and his/her
Community Tax Certificate No. _______ issued on ____ at ______.
18
RA 9184: GOVERNMENT PROCUREMENT LAW
Bid-Securing Declaration
1. I/We understand that, according to your conditions, bids must be supported by a Bid
Security, which may be in the form of a Bid-Securing Declaration.
2. I/We accept that: (a) I/we will be automatically disqualified from bidding for any contract
with any procuring entity for a period of two (2) years upon receipt of your Blacklisting
Order; and, (b) I/we will pay the applicable fine provided under Section 6 of the Guidelines
on the Use of Bid Securing Declaration, within fifteen (15) days from receipt of written
demand by the procuring entity for the commission of acts resulting to the enforcement of
the bid securing declaration under Sections 23.1(b), 34.2, 40.1 and 69.1, except 69.1 (f), of
the IRR of RA 9184; without prejudice to other legal action the government may undertake.
3. I/We understand that this Bid-Securing Declaration shall cease to be valid on the following
circumstances:
a. Upon expiration of the bid validity period, or any extension thereof pursuant to your
request;
b. I am/we are declared ineligible or post-disqualified upon receipt of your notice to such
effect, and (i) I/we failed to timely file a request for reconsideration or (ii) I/we filed a
waiver to avail of said right;
c. I am/we are declared as the bidder with the Lowest Calculated Responsive Bid, and
I/we have furnished the performance security and signed the Contract.
19
RA 9184: GOVERNMENT PROCUREMENT LAW
IN WITNESS WHEREOF, I/We have hereunto set my/our hand/s this ____ day of [month] [year]
at [place of execution].
Affiant
SUBSCRIBED AND SWORN to before me this __ day of [month] [year] at [place of execution],
Philippines. Affiant/s is/are personally known to me and was/were identified by me through
competent evidence of identity as defined in the 2004 Rules on Notarial Practice (A.M. No. 02-8-
13-SC). Affiant/s exhibited to me his/her [insert type of government identification card used],
with his/her photograph and signature appearing thereon, with no. ______.
20
RA 9184: GOVERNMENT PROCUREMENT LAW
The Contractor shall take all necessary precautions for the safety of
employees and workmen on the Work, and comply with all Laws to prevent injury
to persons on, about, or adjacent to the premises where the Work is being
performed.
The Contractor shall erect and properly maintain at all times, as required
by the conditions and progress of the work, such as barriers, shoring, supports,
braces, lights, danger signs and necessary safeguards, as will protect workmen
and the public and as will effectively prevent any injury to persons and damage to
property in consequence of his work.
2. Will the owner be responsible for the death or injury of the Contractor or his
employees from any source or cause by or to the Contractor's plant or materials?
What about damages caused by the Contractor or his employees to any property
of the Owner and adjoining property?
21
RA 9184: GOVERNMENT PROCUREMENT LAW
No. Article 30.02(a) states that the Contractor shall indemnify and save
harmless the Owner from and against all losses and all claims, demands,
payments, suits, actions, recoveries, and judgment of every nature and
description brought or recovered against him, for any act or omission of said
Contractor, or of his agents or employees, in the execution of the Work or the
guarding of it.
3. Who will pay for the repair and damages of the Contractor?
Claims for payment and repairs for damages for which the Contractor is
liable shall be settled by the Contractor at his own expense. (30.02[b])
The Owner may repair the same and pay the claims, and deduct the entire
cost of such repairs and claims from the payments due the Contractor.
The Owner shall have the right to undertake reasonable safety and
protection measures, and charge the cost of such measures to the Contractor.
(30.03)
To protect himself, his sub-contractors, and the Owner from claims for
bodily injury, death or property damage.
Can the Contractor commence work without insurance and subsequently acquire
one?
22
RA 9184: GOVERNMENT PROCUREMENT LAW
No, the Contractor shall not commence work under the Contract until he
has obtained the insurance coverage required and shall have filed the insurance.
Is there any special clause that should be provided for in the Insurance policy?
Yes, the insurance policy shall contain a clause providing that it shall not
be cancelled by the insurance company without written notice to and approval of
the Owner. The nature, extent and amount of such insurance coverage shall be
as agreed upon between the Owner and the Contractor. The Contractor shall
ensure that such insurance policy is effective during the execution of the Work.
23
RA 9184: GOVERNMENT PROCUREMENT LAW
• 15% of the Contract amount for the faithful performance of his work; and
• 15% bond covering Contractor's obligations arising from the Contract to its
workers, subcontractors and suppliers.
For how long should the Guarantee Bond be held by the Owner?
For a period of one (1) year commencing from the date of posting as a
guarantee that all materials and workmanship installed under the Contract are of
acceptable quality.
31.06 Guarantee-Warranty
What if the Contractor gets a sub-contractor to do its work, who shall guarantee
for the sub-contractor?
• All work performed by him directly and for which guarantees are required.
24
RA 9184: GOVERNMENT PROCUREMENT LAW
• For a period of one year, or for a longer period where so provided in the
Specifications, all materials and workmanship installed under the Contract are to
be of acceptable quality in every respect and to remain so during the guarantee
period.
The Owner may have the work done by another contractor and charge the
cost against monies retained as provided for in the Contract and/or against his
sureties.
What is the effect of the surety or bondsman issuing any bond called for in the
Contract?
The bond issued shall continue to have force and effect beyond the
effectivity period stated in the bond if the work or the obligation for which it was
issued has not been completely performed. This is without prejudice to the right
of the surety or bondsman to demand from the Contractor the payment of the
premium on the bond or to the right of the Owner to pay such unpaid premium for
the Contractor.
The additional premium on the bond for an extension of the Contract time
due to reasons other than the fault or negligence of the Contractor shall be billed
at cost to the Owner. The bond may not be cancelled or otherwise terminated by
the bondsman or surety without the express written consent of both the Owner
and the Contractor. The right of the surety shall be limited to demand the
payment of unpaid premium.
The Owner shall have a right of recourse against the surety on the bond
until (a) it is cancelled by the Owner and returned to the Contractor, (b) it is
replaced by another bond unless the Owner reserves the right to recover against
the former bond due to default of the Contractor, (c) the Owner issues to the
Contractor an unconditional Certificate of Acceptance of the Work.
Until the Owner takes over the work or terminates the Contract, the
Contractor shall not be deemed in default notwithstanding the reduction of the
Contractor's scope of work and any assistance provided by the Owner to enable
the Contractor to catch up and complete the remaining work. The Owner's
assistance to the Contractor shall not prejudice nor limit the right of the Owner to
have a later recourse against the bond.
26
RA 9184: GOVERNMENT PROCUREMENT LAW
The Contractor shall use the advance payment for mobilization, purchase
of materials, and the like for the project. This shall be recouped pro rata in the
progress billings.
A bond is callable on demand when the surety is obliged to pay the Owner
upon its call. It means payable on demand.
The Owner shall be responsible for and shall maintain such insurance as
will protect him from liability for personal injury including disease and death of
27
RA 9184: GOVERNMENT PROCUREMENT LAW
To protect him from his contingent liability for damages, for personal
injury, including death, which may arise from the work under the Contract.
The Owner shall, at the request of the Contractor, at the time of the
execution of the Contract, furnish to the Contractor reasonable evidence that the
Owner can fulfill its obligations under the Contract. Unless such reasonable
evidence is furnished, the Contractor may not be required to execute the
Contract or to commence or continue the Work.
33.01 LIENS
Can the Contractor release the Work even though there are legal liens attached
to it?
No. The Contractor shall release the Work from any legal liens attaching
therewith as a result of unpaid claims of subcontractors and/or suppliers for the
supply of materials and/or equipment to the Contractor for the project.
What will happen if any of such claims remain unpaid as of the time of executing
the sworn statement?
The Contractor shall furnish the Owner with an indemnity bond equal to
the amount of the claims still unpaid. The indemnity bond may be issued by the
surety which previously issued the Contractor's performance bond or any other
bond required under the Contract or by any other surety acceptable to the
Owner. The Owner may recover against the Contractor and/or surety, on the
latter's indemnity bond, any amount paid by the Owner to discharge such liens,
including costs incurred incident thereto and a reasonable amount of attorney's
fees.
33.02 ASSIGNMENT
No, the Contract may not be assigned in whole or in part. Any purported
assignment made of the Contract or any part thereof without the consent of either
party shall be void and ineffective. (33.02[A])
May the Owner exact full compliance from both the Contractor and assignee?
Yes, he may do so even without waiving his right at any time thereafter to
reduce the Contractor's scope of work by removing from the Contractor the part
of the work which was assigned and giving it to any other contractor and/or
terminating the Contract in either case, without any further cause than the
assignment. [33.02(B)]
29
RA 9184: GOVERNMENT PROCUREMENT LAW
May the Owner request for contracts entered into by the Contractor with any
other person?
Yes, the Owner may request any contract, agreement or binding written
commitment entered into by the Contractor either before or after the execution of
the Contract, with any other person as co-operator, consortium member, joint
venture member, or supplier of equipment, technology, materials or services for
the joint execution of the Work. (33.02[C])
What if the Owner finds that such contract entered into by the is a disguised
assignment of the Contract?
The Owner shall notify the Contractor and shall have the rights under
Article 33.02(B).
33.03 SUBCONTRACTING
Yes. The Contractor may subcontract any part of the Contract with the
approval of the Owner
What are the conditions the Owner may impose for the approval of the
subcontract?
That the subcontract shall be submitted to the Owner and the subcontract
must require the subcontractor to obtain the same bonds and insurance
coverage as are required of the Contractor under the Contract,
That the Contractor furnish the Owner copies of these insurance policies
and bonds
30
RA 9184: GOVERNMENT PROCUREMENT LAW
33.04 DISPUTES
Yes, the Owner may, within a period of 15 days, entrust these to his
authorized representative who shall act as his agent and whose determination
binds the Owner.
What if the Contractor disagrees with the determination by the Owner or his
representative?
31
RA 9184: GOVERNMENT PROCUREMENT LAW
B. Substituted Service
32
RA 9184: GOVERNMENT PROCUREMENT LAW
Such service shall be made upon the said party by filing the same with the
Construction Industry Authority of the Philippines (CIAP) at its office address, and
filing the claim, notice, or process shall complete the service upon the party
concerned.
33
RA 9184: GOVERNMENT PROCUREMENT LAW
ARTICLE II
For this purpose, the GPPB shall pursue the development of generic
procurement manuals and standard bidding forms, the use of which once issued
shall be mandatory upon all Procuring Entities.
PROCUREMENT PLANNING
34
RA 9184: GOVERNMENT PROCUREMENT LAW
ARTICLE III
35
RA 9184: GOVERNMENT PROCUREMENT LAW
ARTICLE VIII
The bid opening process starts after the receipt of bids and concludes
when the bids are collected for further evaluation. The Long Form or Brief Form
bidding documents are used for competitive bidding. The Instructions to Bidders
states that bids will be opened publicly. Bid Opening: Stage in project
advertisement process where sealed bids, received by prospective bidders
(Contractors) are opening and examined by the County. Bidder: An individual,
partnership, firm, corporation, or joint venture, submitting a proposal or bid.
36
RA 9184: GOVERNMENT PROCUREMENT LAW
23.4.1.1. The following shall be eligible to participate in the bidding for the supply
of goods:
a) Duly licensed Filipino citizens/sole proprietorships;
b) Partnerships duly organized under the laws of the Philippines and of which at
least sixty percent (60%) of the interest belongs to citizens of the Philippines;
c) Corporations duly organized under the laws of the Philippines, and of which at
least sixty percent (60%) of the outstanding capital stock belongs to citizens of
the Philippines;
SEC. 24. Eligibility Requirements and Short Listing for Consulting Services.
The eligibility of prospective bidders for the Procurement of Consulting
Services shall be determined by their compliance with the eligibility requirements
prescribed for the Competitive Bidding concerned, within the period stated in the
Invitation to Bid. The eligibility requirements shall provide for fair and equal
access to all prospective bidders. The prospective bidder shall certify under oath
37
RA 9184: GOVERNMENT PROCUREMENT LAW
38
RA 9184: GOVERNMENT PROCUREMENT LAW
procurement by a Philippine Foreign Service Office or Post, which shall The 2016
Revised Implementing Rules and Regulations 66 submit their eligibility
documents under Section 23.1 of this IRR: Provided, That the winning bidder
shall register with the PhilGEPS in accordance with Section 37.1.4 of this IRR;
vi) Bid security in the prescribed form, amount and validity period;
viii) Omnibus Sworn Statement in accordance with Section 25.3 of this IRR; and
ix) For foreign bidders claiming eligibility by reason of their country’s extension of
reciprocal rights to Filipinos, a certification from the relevant government office of
their country stating that Filipinos are allowed to participate in their government
procurement activities for the same item or product.
27.1. All bids shall be accompanied by a bid security, payable to the Procuring
Entity concerned as a guarantee that the successful bidder shall, within ten (10)
calendar days from receipt of the notice of award, enter into contract with the
39
RA 9184: GOVERNMENT PROCUREMENT LAW
27.2 The bidder shall submit a Bid Securing Declaration, or any form of Bid
Security, in an amount not less than the required percentage of the ABC in
accordance with the following schedule:
40
RA 9184: GOVERNMENT PROCUREMENT LAW
28.1. Bids and bid securities shall be valid for a reasonable period as determined
by the HoPE concerned, which shall be indicated in the Bidding Documents, but
in no case shall the period exceed one hundred twenty (120) calendar days from
the date of the opening of bids.
The BAC shall open the bids immediately after the deadline for the
submission and receipt of bids. The time, date, and place of the opening of bids
shall be specified in the Bidding Documents.
In case the bids cannot be opened as scheduled due to justifiable reasons, the
BAC shall take custody of the bids submitted and reschedule the opening of bids
on the next working day or at the soonest possible time through the issuance of a
Notice of Postponement to be posted in the PhilGEPS website and the website of
the Procuring Entity concerned.
The bidders or their duly authorized representatives may attend the opening of
bids. The BAC shall ensure the integrity, security, and confidentiality of all
41
RA 9184: GOVERNMENT PROCUREMENT LAW
submitted bids. The abstract of bids as read and the minutes of the bid opening
shall be made available to the public upon written request and payment of a
specified fee to recover cost of materials.
Section 32. Bid Evaluation for the Procurement of Goods and Infrastructure
Projects
32.1. Members of the BAC, its staff and personnel, Secretariat and TWG, as well
as Observers, are prohibited from making or accepting any communication with
any bidder regarding the evaluation of their bids until the issuance of the Notice
of Award. However, the BAC, through its Secretariat, may ask in writing the
bidder for a clarification of its bid. All responses to requests for clarification shall
be in writing.
32.2. For the procurement of Goods and Infrastructure Projects, the BAC shall
evaluate the financial component of the bids to determine the Lowest Calculated
Bid using the following steps:
32.2.1. The BAC shall immediately conduct a detailed evaluation of all bids using
non-discretionary criteria in considering the following:
42
RA 9184: GOVERNMENT PROCUREMENT LAW
Section 33. Bid Evaluation of Short Listed Bidders for Consulting Services
33.1. From submission and receipt of bids until the approval by the HoPE of the
ranking of short listed bidders, those that have submitted their bids are prohibited
from making any communication with any BAC member, including its staff and
personnel, as well as its Secretariat and TWG, regarding matters connected to
their bids. However, the BAC, through its Secretariat, may ask in writing the
bidder for a clarification of its bid. All responses to requests for clarification shall
be in writing.
33.2. The purpose of bid evaluation is to determine the Highest Rated Bid using
the following steps:
33.2.1. The BAC shall conduct a detailed evaluation of bids using either of the
following evaluation procedures as specified in the Bidding Documents:
43
RA 9184: GOVERNMENT PROCUREMENT LAW
iv) After approval by the HoPE of the Highest Rated Bid, its financial
proposal shall then be opened. The BAC shall, within three (3) calendar
days, notify and invite the consultant with the Highest Rated Bid for the
opening of financial proposal for the purpose of conducting negotiations
with the said consultant. In the letter of notification, the BAC shall inform
the consultant of the issues in the technical proposal the BAC may wish to
clarify during negotiations.
44
RA 9184: GOVERNMENT PROCUREMENT LAW
INFRASTRUCTURE PROJECTS
1.1. Variation Orders may be issued by the procuring entity to cover any
increase/decrease in quantities.
1.2. A Change Order may be issued by the implementing official to cover any
increase/decrease in quantities of original work items in the contract.
1.3. An Extra Work Order may be issued by the implementing official to cover the
introduction of new work necessary for the completion, improvement or
protection of the project which was not included as items of work in the original
contract.
1.4. Any cumulative positive Variation Order beyond ten percent (10%) of the
original contract price shall be subject of another contract to be bid out if the
works are separable from the original contract.
1.5. In claiming for any Variation Order, the contractor shall, within seven (7)
calendar days after such work has been commenced pursuant to Item 3.2 hereof;
or, within twenty-eight (28) calendar days after the circumstances or reasons
justifying a claim for extra cost shall have occurred, deliver a notice giving full
and detailed particulars of any extra cost in order that it may be investigated at
that time. Failure to provide either of such notices in the time stipulated shall
constitute a waiver by the contractor for any claim. The preparation and
submission of Variation Orders are as follows:
45
RA 9184: GOVERNMENT PROCUREMENT LAW
b) The Head of the Procuring Entity or his duly authorized representative upon
receipt of the proposed Change Order or Extra Work Order shall immediately
instruct the appropriate technical staff or office of the procuring entity to conduct
an on-the-spot investigation to verify the need for the work to be prosecuted and
to review the proposed plan, and prices of the work involved.
c) The technical staff of appropriate office of the procuring entity shall submit a
report of their findings and recommendations, together with the supporting
documents, to the Head of the Procuring Entity or his duly authorized
representative for consideration.
d) The Head of the Procuring Entity or his duly authorized representative, acting
upon the recommendation of the technical staff or appropriate office, shall
approve the Change Order or Extra Work Order after being satisfied that the
same is justified, necessary, and in order.
e) The timeframe for the processing of Variation Orders from the preparation up
to the approval by the procuring entity concerned shall not exceed thirty (30)
calendar days.
2.1. For Variation Orders, the contractor shall be paid for additional work items
whose unit prices shall be derived based on the following:
46
RA 9184: GOVERNMENT PROCUREMENT LAW
b. For additional/extra works duly covered by Extra Work Orders involving new
work items that are not in the original contract, the unit prices of the new work
items shall be based on the direct unit costs used in the original contract (e.g.,
unit cost of cement, rebars, form lumber, labor rate, equipment rental, etc.). All
new components of the new work item shall be fixed prices, provided the same is
acceptable to both the Government and the contractor, and provided further that
the direct unit costs of new components shall be based on the contractor's
estimate as validated by the procuring entity concerned via documented canvass
in accordance with existing rules and regulations. The direct cost of the new work
item shall then be combined with the mark-up factor (i.e., taxes and profit) used
by the contractor in his bid to determine the unit price of the new work item.
2.2. Request for payment by the contractor for any extra work shall be
accompanied by a statement, with the approved supporting forms, giving a
detailed accounting and record of amount for which, he claims payment. Said
request for payment shall be included with the contractor's statement for
progress payment.
3.2. However, under any of the following conditions, the procuring entity’s
representative/Project Engineer may, subject to the availability of funds and
within the limits of his delegated authority, allow the immediate start of work
under any Change Order or Extra Work Order:
47
RA 9184: GOVERNMENT PROCUREMENT LAW
Provided, finally, that for a Change Order or Extra Work Order involving a
cumulative amount exceeding five percent (5%) of the original contract price, no
work thereon may be commenced unless said Change Order or Extra Work
Order has been approved by the Head of the Procuring Entity or his duly
authorized representative.
4. ADVANCE PAYMENT
4.1. The procuring entity shall, upon a written request of the contractor.
4.2. The advance payment shall be made only upon the submission to and
acceptance by the procuring entity of an irrevocable standby letter of credit of
equivalent value from a commercial bank.
4.3. The advance payment shall be repaid by the contractor by deducting fifteen
percent (15%) from his periodic progress payments a percentage equal to the
percentage of the total contract price used for the advance payment.
48
RA 9184: GOVERNMENT PROCUREMENT LAW
4.4. The contractor may reduce his standby letter of credit or guarantee
instrument by the amounts refunded by the Monthly Certificates in the advance
payment.
5. PROGRESS PAYMENT
5.1. Once a month, the contractor may submit a statement of work accomplished
(SWA) or progress billing and corresponding request for progress payment for
work accomplished.
5.3. The procuring entity shall deduct the following from the certified gross
amounts to be paid to the contractor as progress payment:
6. RETENTION MONEY
6.1. Progress payments are subject to retention of ten percent (10%) referred to
as the "retention money."
6.2. The total "retention money" shall be due for release upon final acceptance of
the works.
7. CONTRACT COMPLETION
49
RA 9184: GOVERNMENT PROCUREMENT LAW
8. NEGATIVE SLIPPAGE
9. LIQUIDATED DAMAGES
9.1. Once the contract duration expires, including any time extension duly
granted, and the contractor refuses or fails to satisfactorily complete the work,
the Procuring Entity shall impose upon the contractor in default liquidated
damages.
9.2. In computing for liquidated damages, the Procuring Entity determines the
usability of the project.
9.3. To be entitled to such liquidated damages, the Procuring Entity does not
have to prove that it has incurred actual damages.
9.4. In case the total sum of liquidated damages reaches ten percent (10%) of
the total contract price, the Procuring Entity has the following options:
9.4.2. Allow the contractor to continue the works without prejudice to the
continued imposition of liquidated damages until the works have been completed.
50
RA 9184: GOVERNMENT PROCUREMENT LAW
This does not, however, preclude the Procuring Entity in resorting to Termination
of Contract under Annex I of the 2016 revised IRR of RA No. 9184.
10.2. The contractor or its duly authorized representative shall have the right to
suspend work operation on any or all projects/activities along the critical path of
activities after fifteen (15) calendar days from date of receipt of written notice
from the contractor to the district engineer/regional director/consultant or
equivalent official, as the case may be, due to the following:
e. Delay in the payment of contractor's claim for progress billing beyond forty-five
(45) calendar days from the time the contractor's claim has been certified to by
the procuring entity’s authorized representative that the documents are complete
unless there are justifiable reasons thereof which shall be communicated in
writing to the contractor.
51
RA 9184: GOVERNMENT PROCUREMENT LAW
11.1. Should the amount of additional work of any kind or other special
circumstances of any kind whatsoever occur such as to fairly entitle the
contractor to an extension of contract time, the procuring entity shall determine
the amount of such extension.
11.2. No extension of contract time shall be granted the contractor due to (a)
ordinary unfavorable weather conditions and (b) inexcusable failure or
negligence of contractor to provide the required equipment, supplies or materials.
11.3. Extension of contract time may be granted only when the affected activities
fall within the critical path of the PERT/CPM network.
11.4. No extension of contract time shall be granted when the reason given to
support the request for extension was already considered in the determination of
the original contract time during the conduct of detailed engineering and in the
preparation of the contract documents as agreed upon by the parties before
contract perfection.
12.1. To help ensure the quality of materials being used in infrastructure projects,
the Bureau of Research and Standards (BRS) of the DPWH, Department of
Science and Technology (DOST), or Department of Trade and Industry (DTI)
shall accredit, in accordance with industry guidelines, the testing laboratories
whose services are engaged or to be engaged in infrastructure projects. All
government infrastructure project owners must accept results of material test(s)
coming only from DOST/BRS accredited laboratories.
For project types which do not have specific CPES Guidelines, the
Procuring Entities concerned may formulate and adopt their own implementing
Guidelines specific to their needs provided the NEDA-INFRACOM poses no
objections to their adoption, and provided further that said Guidelines are made
known to all prospective bidders.
13.5. Utilization of Evaluation Results the CIAP shall consolidate all of the CPES
evaluation results received and shall disseminate the same to all Procuring
Entities concerned.
The rules and regulations for the other aspects of contract implementation
shall be included in the manuals to be issued by the GPPB, such as, but not
limited to, the following:
a) Sub-contracting;
e) Daywork;
53
RA 9184: GOVERNMENT PROCUREMENT LAW
Comparative Matrix of the 2009 and 2016: Revised Implementing Rules and
Regulations of R.A. 9184
Before the 2016 Revised IRR, R.A. 9184's 2009 Implementing Rules and
Regulations served as its last set of regulations. Some provisions, such a portion
of section 5, remain the same (Definition of terms). However, a new provision
that was not there in the 2009 IRR of R.A. has been inserted for 2016. Like
section 4.5. Finally, a number of adjustments were made and are currently in
effect.
https://www.bsp.gov.ph/Procurement_Docs/RA9184%20ChangeMatrix.pdf
54
RA 9184: GOVERNMENT PROCUREMENT LAW
A. EXTRAORDINARY CIRCUMSTANCES
Extraordinary circumstances refers to an event or occurrence, or series of
events or occurrences during contract implementation which give/s rise to price
escalation as may be determined by the NEDA, in accordance with the
provisions of the Civil Code of the Philippines.
For purposes of these Guidelines, the term “extraordinary circumstances” shall
refer to the following articles of the Civil Code of the Philippines:
55
RA 9184: GOVERNMENT PROCUREMENT LAW
56
RA 9184: GOVERNMENT PROCUREMENT LAW
57
RA 9184: GOVERNMENT PROCUREMENT LAW
a. The value K varies for each item of work and is represented by:
K = a + b (Xi/Xo) + c (Yi/Yo) + d (Zi/Zo) + ... n (Ni/No)
Where:
a = is a 0.15 fixed coefficient representing contractor’s
profit, and other non-adjustable items.
b, c, d, ... n = are the coefficients representing the
proportionate value of each pay item to the total. b + c +
d... + n = 0.85.
Xi, Yi, Zi, ... Ni = are variables representing the current
price indices of the cost of labor, materials and other
components of the contract during the period under
consideration at the time of the request for price
escalation.
Xo, Yo, Zo, ... No = are variables representing the current
price indices of the cost of labor, materials and other
components of the contract on the date of bid opening or
approval of variation order.
58
RA 9184: GOVERNMENT PROCUREMENT LAW
59
RA 9184: GOVERNMENT PROCUREMENT LAW
for appropriate action. The GPPB shall then approve/act upon the request
for price escalation during one of its meetings.
a value equal to the amount of recoupment of advance payment; and the amount
of materials for which advance payment was made.
The GPPB may amend these Guidelines as may be necessary.
Nonetheless, the GPPB may formulate supplemental guidelines in the form of
addenda or annexes for the review process as stipulated in the Two-Stage
Review Process without need of amending these Guidelines.
F. TRANSITORY CLAUSE
1. Claims for price escalation for contracts completed after the
effectiveness of these Guidelines shall be filed within two (2) years
from completion of the contract concerned.
2. Claims for price escalation for contracts the Invitation to Apply for
Eligibility and to Bid (IAEB) for which were issued after the
effectivity of R.A. 9184 and completed before the effectivity of these
Guidelines shall be filed not later than two (2) years from the date
of effectivity of these Guidelines.
3. The thirty (30) – month historical data prescribed in computing for
two (2) standard deviations as provided in Section 5.2.2.a shall
apply to price escalation claims for contracts the IAEB for which
were issued after the effectiveness of these Guidelines.
61
RA 9184: GOVERNMENT PROCUREMENT LAW
63
RA 9184: GOVERNMENT PROCUREMENT LAW
project and the provisional sum. The ABC will be the total of both
funds.
c. All charges for the opening of the LC and/or incidental expenses (i.e., bank
commission, documentary stamp tax, cable, etc.) are for the supplier's
account and must be specified in the bidding documents.
64
RA 9184: GOVERNMENT PROCUREMENT LAW
C. CONTRACT PRICES
65
RA 9184: GOVERNMENT PROCUREMENT LAW
less than the original contract price; provided, however, that the price is
still the most advantageous to the Government after price comparison and
verification.
E. EFFECTIVITY
66
RA 9184: GOVERNMENT PROCUREMENT LAW
Defects are defined as part of the work that was not constructed in
accordance with the contract, such as errors that may lead to failure. According
to Contract Implementations in Annex G, any errors, omissions, inconsistencies,
inadequacies or failures submitted by the contractor that do not comply with the
requirements shall be rectified, resubmitted and reviewed at the contractor’s cost.
67
RA 9184: GOVERNMENT PROCUREMENT LAW
Section 34 contains the qualifications that the bidder needs to meet in line
with the contract.
In the occurrence that any of the following defects are proven to be due to
the contractor’s fault or negligence, the contractor shall be disqualified from the
award of the procurement of the infrastructure project.
68
RA 9184: GOVERNMENT PROCUREMENT LAW
69
RA 9184: GOVERNMENT PROCUREMENT LAW
works (except for those caused by force majeure) and the safety, protection,
security and convenience of the people involved in the construction work.
The defects liability period, in line with the performance security of the
contractor shall guarantee that the contractor performs his responsibilities.
Failure to comply means that the Procuring Entity shall forfeit its performance
security, subject its properties to attachment and disqualify it from participating in
any competitive bidding.
70
RA 9184: GOVERNMENT PROCUREMENT LAW
71
RA 9184: GOVERNMENT PROCUREMENT LAW
Termination of Contract
It is a ground for termination of contract for infrastructure projects when
the contractor does not execute the works in accordance with the contract and
refuses to perform a new work after being rejected and labeled defective.
72
RA 9184: GOVERNMENT PROCUREMENT LAW
55.1 Decisions of the BAC at any stage of the procurement process may be
questioned by filing a request for reconsideration within the three (3) calendar
days upon receipt of written notice or upon verbal notification. The BAC shall
decide on the request for reconsideration within seven (7) calendar days from
receipt thereof. The bidder shall not be allowed to submit additional documents to
correct any defects in the bid submitted. If a failed bidder signifies his intent to file
a request for reconsideration, the BAC shall keep the bid envelopes of the said
failed bidder unopened and/or duly sealed until such time that the request for
reconsideration has been resolved.
55.2 In the event that the request for reconsideration is denied, decisions of the
BAC may be protested in writing to the HoPE: Provided, however, That a prior
request for reconsideration should have been filed by the party concerned in
accordance with the preceding Section, and the same has been resolved.
55.3 The protest must be filed within seven (7) calendar days from receipt by the
party concerned of the resolution of the BAC denying its request for
reconsideration. A protest shall be made by filing a verified position paper with
the HoPE concerned, accompanied by the payment of a non-refundable protest
fee, which shall be paid in cash in accordance with the following schedule:
55.4 The verified position paper shall contain the following information:
a) The name of bidder;
b) The office address of the bidder;
c) The name of project/contract;
d) The implementing office/agency or Procuring Entity;
e) A brief statement of facts;
f) The issue to be resolved; and
g) Such other matters and information pertinent and relevant to the proper
resolution of the protest.
The position paper is verified by an affidavit that the affiant has read and
understood the contents thereof and that the allegations therein are true and
correct of his personal knowledge or based on authentic records. An unverified
position paper shall be considered unsigned, produces no legal effect, and
results to the outright dismissal of the protest.
74
RA 9184: GOVERNMENT PROCUREMENT LAW
The protests shall be resolved strictly on the basis of records of the BAC.
The HoPE shall resolve the protest within seven (7) calendar days from receipt
thereof. Subject to the provisions of existing laws on the authority of Department
Secretaries and the heads of agencies, branches, constitutional commissions, or
instrumentalities of the GoP to approve contracts, the decisions of the HoPE
concerned shall be final up to the limit of his contract approving authority. With
respect to LGUs, the decision of the local chief executive shall be final.
In no case shall any protest taken from any decision treated in this Rule
stay or delay the bidding process: Provided, however, That protests must first be
resolved before any award is made.
58.1 Court action may be resorted to only after the protests contemplated in this
Rule shall have been completed, i.e., resolved by the HoPE with finality. The
regional trial court shall have jurisdiction over final decisions of the HoPE. Court
actions shall be governed by Rule 65 of the 1997 Rules of Civil Procedure.
58.2 This provision is without prejudice to any law conferring on the Supreme
Court the sole jurisdiction to issue temporary restraining orders and injunctions
relating to Infrastructure Projects of the GoP.
58.3 The head of the BAC Secretariat of the Procuring Entity concerned shall
ensure that the GPPB shall be furnished a copy of the cases filed in accordance
with this Section.
75
RA 9184: GOVERNMENT PROCUREMENT LAW
59.1 If any dispute or difference of any kind whatsoever shall arise between the
parties in connection with the implementation of the contract covered by the Act
and this IRR, the parties shall make every effort to resolve amicably such dispute
or difference by mutual consultation.
59.2 Any and all disputes arising from the implementation of a contract covered
by the Act and this IRR shall be submitted to arbitration in the Philippines
according to the provisions of R.A. 876, otherwise known as the "Arbitration Law"
and R.A. 9285, otherwise known as the “Alternative Dispute Resolution Act of
2004”: Provided, however, That disputes that are within the competence of the
Construction Industry Arbitration Commission to resolve shall be referred thereto.
The process of arbitration shall be incorporated as a provision in the contract that
will be executed pursuant to the provisions of the Act and this IRR: Provided,
further, That by mutual agreement, the parties may agree in writing to resort to
other alternative modes of dispute resolution.
76
RA 9184: GOVERNMENT PROCUREMENT LAW
77
RA 9184: GOVERNMENT PROCUREMENT LAW
The arbitral award and any decision rendered in accordance with the
foregoing Section shall be appealable by way of a petition for review to the Court
of Appeals. The petition shall raise pure questions of law and shall be governed
by the Rules of the Court.
78
RA 9184: GOVERNMENT PROCUREMENT LAW
79
RA 9184: GOVERNMENT PROCUREMENT LAW
Within a period not exceeding fifteen (15) calendar days from the
determination by the Bids and Awards Committee (BAC) of the bidder with the
LCRB, HRRB, SCRB, or SRRB, and the recommendation to award the contract,
the Head of Procuring Entity (HoPE) or his duly authorized representative shall
approve or disapprove the said recommendation. In case of approval, the HoPE
shall immediately issue the Notice of Award to the bidder with the LCRB, HRRB,
SCRB or SRRB. Within ten (10) days from receipt of by the winning bidder of the
Notice of Award, there are additional documents and conditions should be
complied before the contract may be awarded; posting of performance security,
signing of the contract, approval of higher authority if required. In the event of
disapproval, which shall be based only on valid, reasonable, and justifiable
grounds as provided for under Section 41 of this IRR, the HoPE shall notify the
BAC and the bidder in writing of such decision and the grounds for it.
A request for reconsideration may be filed by the bidder with the HoPE
within three (3) calendar days from receipt of the notice of disapproval. The
HoPE shall resolve with finality the request for reconsideration within seven (7)
calendar days from the filing thereof and furnish the bidder a copy of the
resolution immediately from its promulgation. If recommended bidder is not
accepted, the BAC shall conduct a post-qualification of the bidder with the next
Lowest Calculated Bid or Highest Rated Bid.
The BAC, through the Secretariat, shall post, within three (3) calendar
days from its issuance, the Notice of Award in the PhilGEPS, the website of the
Procuring Entity, if any, and any conspicuous place in the premises of the
Procuring Entity.
The winning bidder shall post the required Performance Security and enter
into contract with the Procuring Entity within ten (10) calendar days from receipt
by the winning bidder of the Notice of Award. When further approval of higher
authority is required, the approving authority for the contract or his duly
authorized representative shall be given a maximum of twenty (20) calendar days
from receipt thereof to approve or disapprove it. In the case of Government-
80
RA 9184: GOVERNMENT PROCUREMENT LAW
81
RA 9184: GOVERNMENT PROCUREMENT LAW
Head of the Procuring Entity refers to: (i) the head of the agency or his
duly authorized official, for national government agencies; (ii) the governing
board or its duly authorized official, for government-owned and/or controlled
corporations; or (iii) the local chief executive, for local government units.
Provided, that in a department, office or agency where the procurement is
decentralized, the Head of each decentralized unit shall be considered as the
Head of the Procuring Entity subject to the limitations and authority delegated by
the head of the department, office or agency.
Termination in Part means the termination of a part but not all, of the work
that has not been completed and accepted under a contract.
Termination in Whole means the termination of all of the work that has not
been completed and accepted under a contract.
3. Show Cause. Within a period of seven (7) calendar days from receipt of
the Notice of Termination, the Supplier/Contractor/Consultant shall submit
to the Head of the Procuring Entity a verified position paper stating why
the contract should not be terminated. If the
Supplier/Contractor/Consultant fails to show cause after the lapse of the
seven (7) day period, either by inaction or by default, the Head of the
Procuring Entity shall issue an order terminating the contract.
4. Rescission of Notice of Termination. The Procuring Entity may, at any
time before receipt of the Supplier’s/Contractor’s/Consultant’s verified
position paper to withdraw the Notice to Terminate if it is determined that
certain items or works subject of the notice had been completed,
delivered, or performed before the Supplier’s/Contractor’s/Consultant’s
receipt of the notice.
5. Decision. Within a non-extendible period of ten (10) calendar days from
receipt of the verified position paper, the Head of the Procuring Entity shall
decide whether or not to terminate the contract. It shall serve a written
notice to the Supplier/Contractor/Consultant of its decision and, unless
otherwise provided, the Contract is deemed terminated from receipt of the
Supplier/Contractor/Consultant of the notice of decision. The termination
shall only be based on the ground(s) stated in the Notice to Terminate.
6. Contract Termination Review Committee (CTRC). The Head of the
Procuring Entity may create a committee to assist him in the discharge of
his function under these Guidelines. All decisions recommended by the
CTRC shall be subject to the approval of the Head of the Procuring Entity.
7. Take-over of Contracts. If a Procuring Entity terminates the contract due
to default, insolvency, or for cause, it may enter into a Negotiated
Procurement pursuant to Section 53(c) of R.A. 9184 and 53.3 of its IRR.
8. Procuring Entity’s Options in Termination for Convenience in
Contracts for Goods. The goods that have been performed or are ready
for delivery within thirty (30) calendar days after the Supplier’s receipt of
84
RA 9184: GOVERNMENT PROCUREMENT LAW
References
85
RA 9184: GOVERNMENT PROCUREMENT LAW
BSP (2021). Comparative Matrix of the 2009 and 2016 Revised Implementing
Rules and Regulations of R.A. 9184. Bangko Sentral ng Pilipinas. Retrieved from
https://www.bsp.gov.ph/Procurement_Docs/RA9184%20ChangeMatrix.pdf
86