Professional Documents
Culture Documents
Engineering Management Finals Reviwer
Engineering Management Finals Reviwer
You will have several project limitations ● “Risk” the term refers to prospective
fighting for your attention on every project. outside occurrences that, if they
Cost, scope, quality, risk, resources, and happen, could harm your enterprise.
time are some of them. Risk is the result of weighing the
likelihood that an event will take Once the recommended solution is
place against its potential effects on approved, a project is initiated and a project
the project. You should classify the manager is appointed.
prospective event as a risk and put a
proactive plan in place to manage Planning Phase
the risk if the probability of the
occurrence and the impact on the Also referred as "scope management" a
project are too high. project's tasks and resource requirements
are identified, along with the strategy for
● Resources - to complete the producing them. Risk management
responsibilities of the project, identifies and tries to deal with anything that
resources are needed. They can be might pose a threat to the successful
any definable resource—typically completion of the project. This is also a
something other than labor—needed good time to identify all project stakeholders
to complete a project activity, and establish a communication plan. At this
including people, tools, point, the project would have been planned
infrastructure, money, and other in detail and is ready to be executed.
resources.
Implementation (Execution) Phase
● Time - the duration of the project is
referred to as time. The most In any project, a project manager spends
frequent project oversight in most of the time in the implementation
emerging projects is frequently time. phase. Progress is continuously monitored
Deadlines that are missed and and appropriate adjustments are made and
deliverables that aren't complete recorded as variances from the original
indicate this. In order to effectively plan. Once all of the deliverables have been
manage the schedule, it is produced and the customer has accepted
necessary to carefully identify the the final solution, the project is ready for
tasks that need to be completed as closure.
well as estimate their durations,
completion order, and resource Closing Phase
allocation.
The last remaining step is to conduct
PROJECT LIFE CYCLE (PHASES) lessons-learned studies to examine what
went well and what didn't. Through this type
Initiation Phase of analysis, the wisdom of experience is
transferred from the project organization to
The project objective or need is identified. future teams.
An appropriate response to the need is
documented in a business case with
recommended solution options. A feasibility
study is conducted to investigate whether
each option addresses the project
objectives.
KEY SKILLS OF THE PROJECT Project Management Institute Overview
MANAGER
Project Management Institute (PMI) was
founded by five volunteers in 1969. Today,
PMI is the most widely recognized
organization promoting project management
best practices. PMI first began offering the
Project Management Professional (PMP)
certification exam in 1984. More than
500,000 individuals around the world hold
the PMP designation.
In 1991, Hans Thamhain researched the
training of project managers and, based on Project Management Body of Knowledge
the finding, categorized project (PMBOK) is a body of knowledge on project
management into interpersonal, technical, management. PMBOK was created by
and administrative skills: Project Management Institute (PMI) in 1987
to help keep project management terms and
Interpersonal skills - These skills include concepts clear and consistent. In 2008, PMI
providing direction, communicating, reported more than 260,000 members in
assisting with problem solving, and dealing over 171 countries. The highly regarded
effectively with people without having Institute of Electrical and Electronics
authority. Engineers (IEEE) has adopted it as their
project management standard. The PMI is
Administrative skills - These skills include responsible for developing and promoting
planning, organizing, and controlling the PMBOK, PMI also administers a
work. professional certification program for project
managers, the PMP.
Technical expertise - Technical knowledge
gives the project manager the creditability to PMBOK is the fundamental knowledge you
provide leadership on a technically based need for managing a project, categorized
project, the ability to understand important into 10 knowledge areas:
aspects of the project, and the ability to
communicate in the language of the 1.Managing integration: Managing
technicians. integration is about developing the project
charter, scope statement, and plan to direct,
FRAMEWORK FOR PROJECT manage, monitor, and control project
MANAGEMENT change. All types of activities are going on
and there is a need to keep the “whole”
There are two major organizations with thing moving collectively-integrating all of
worldwide impact on the practice of project the dynamics that take place.
management: Project Management Institute
(PMI), with world headquarters in the United 2. Managing scope: Projects need to have
States, and the International Project a defined parameter or scope, and this must
Management Association (IPMA), with world
headquarters in Switzerland.
be broken down and managed through a 9. Managing procurement: Projects
work breakdown structure or WBS. procure the services of outside vendors and
contractors, including the purchase of
3. Managing time/schedule: Managing equipment. There is a need to manage how
time/schedule is about definition, vendors are selected and managed within
sequencing, resource and duration the project life cycle. Managing procurement
estimating. Schedule development, and is about acquisition and contracting plans,
schedule control. sellers’ responses and selections, contract
administration, and contract closure.
4. Managing costs: Projects consume
resources, and therefore, there is a need to 10. Managing stakeholders: Every project
manage the investment with the realization impacts people and organizations and is
of creating value.Managing costs is about impacted by people and organizations.
resource planning, cost estimating, Identifying these stakeholders early, and as
budgeting, and control. they arise and change throughout the
project, is a key success factor. Managing
5. Managing quality: Projects involve stakeholders is about identifying
specific deliverables or work products. stakeholders, their interest level, and their
These deliverables need to meet project potential to influence the project; and
objectives and performance standards. managing and controlling the relationships
Managing quality is about quality planning, and communications between stakeholders
quality assurance, and quality control. and the project.
• To promote the ideals of good governance • Bid – refers to a signed offer or proposal
in all its branches, departments, agencies, submitted by a supplier, manufacturer,
instrumentalities, including GOCC’s and distributor, contractor or consultant in
LGU’s. response to the Bidding Documents.
• No government Procurement shall be • The BAC shall have at least five (5)
undertaken unless it is in accordance with members, but not more than seven (7)
the approved Annual Procurement Plan of members.
the Procuring Entity. • It shall be chaired by at least a third
ranking permanent official.
• The Annual Procurement Plan (APP) shall • Members of the BAC shall have a fixed
be approved by the Head of the Procuring term of one (1) year reckoned from the date
Entity and must be consistent with its duly of appointment, renewable at the discretion
approved yearly budget. of the Head of the Procuring Entity.
ARTICLE V. • The GPPB shall establish a sustained
Section 12. Functions of the BAC training program for developing the capacity
of the BACs, BAC Secretariats and
• advertise and/or post the invitation to bid Technical Working Groups of Procuring
• conduct pre-procurement and pre-bid Entities, and professionalize the same.
conferences
• determine the eligibility of prospective ARTICLE VI.
bidders Section 17. Form and Contents of
• receive bids Bidding
• conduct the evaluation of bids Documents
• undertake post-qualification proceedings
•recommend award of contracts to the Head a) Approved Budget for the Contract;
of the Procuring Entity. (b) Instructions to Bidders, including criteria
for eligibility, bid evaluation and
ARTICLE V. post-qualification, as well as the date, time
Section 13. Observers and place of the pre-bid Conference (where
applicable), submission of bids and opening
1. COA representative of bids;
2. Atleast one (1) observer from a duly (c) Terms of Reference;
recognized private group. (d) Eligibility Requirements;
3. Atleast one (1) observer from an NGO.
ARTICLE VI.
ARTICLE V. Section 17. Form and Contents of
Section 14. BAC Secretariat Bidding
Documents
• To assist the BAC in the conduct of its
functions, the Head of the Procuring Entity (e) Plans and Technical Specifications;
shall create a Secretariat that will serve as (f) Form of Bid, Price Form, and List of
the main support unit of the BAC. Goods or Bill of
Quantities;
ARTICLE V. (g) Delivery Time or Completion Schedule;
Section 15. Honoraria of BAC Members (h) Form and Amount of Bid Security;
(i) Form and Amount of Performance
• The Procuring Entity may grant payment of Security and Warranty; and,
honoraria to the BAC members in an (j) Form of Contract, and General and
amount not to exceed twenty five percent Special Conditions of
(25%) of their respective basic monthly Contract.
salary subject to availability of funds.
ARTICLE VI.
ARTICLE V. Section 19. Access to Information
Section 16. Professionalization of BAC,
BAC Secretariat and Technical Working • The Procuring Entity shall ensure equal
Group Members access to information.
Control
PROJECT MONITORING AND CONTROL
● Based on a comparison of baseline
What is Project Monitoring and Control? plans and contracts with actual
events.
Project monitoring and control will help the
project manager to measure project ● Deciding what to do when there is a
performance. He/she can know the deviation.
progress and status of the project until its
completion at any given point in What is controlled?
time.
● Performance
This phase coincides with the execution
phase of the project lifecycle. ● Costs
WHEREAS, the present policies, rules and regulations covering government contracts for
infrastructure and other construction projects are generally fragmented and have been found to
be inadequate to cope with the intricate and complex process involved;
WHEREAS, there is a need to adopt a comprehensive, uniform, and updated set of policies,
guidelines, rules and regulations covering government contracts for infrastructure and other
construction projects in order to achieve a more efficient and effective implementation of these
projects.
Section 1. Policy Objectives. It is the policy of the government to adopt a set rules and
regulations covering government contracts for infrastructure and other construction projects which
shall:
(b) promote a healthy partnership between the government and the private
sector in furthering national development; and
(c) enhance the growth of the local construction industry and optimize the
use of indigenous manpower, materials and other sources.
(a) Legal Requirements. The prospective contractor must have been licensed as
a contractor for the current year pursuant to Republic Act No. 4566, must have
paid his privilege tax to practice or engage in the contracting business for the
current year, must comply with the Administrative Order No. 66 of the Office of
the President of the Philippines, and must comply with other existing pertinent
laws, rules and regulations.
(b) Technical Requirements. The prospective contractor must meet the following
technical requirements to be established in accordance with the rules and
regulations to be promulgated pursuant to Section 12 of this Decree, to
enable him to satisfactorily prosecute the subject project:
(c) Financial Requirements. The net worth and liquid assets of the
prospective contractor must meet the requirements, to be established in
accordance with the rules and regulations to be promulgated pursuant to Section
12 of this Decree, to enable him to satisfactorily execute the subject project. The
prospective contractor may be allowed to cover the deficiency in the required net
worth through a line of credit fully committed to the subject project by a bank or
financial institution acceptable to the Ministry concerned.
Section 5. Award and Contract. The contract may be awarded to the lowest prequalified
bidder whose bid as evaluated complies with all the terms and conditions in the call for bid
and is the most advantageous to the Government. To guarantee the faithful performance of the
contractor, he shall, prior to the award, post a performance bond, in an amount to be established
in accordance with the rules and regulations to be promulgated under Section 12 of this
Decree. All awards and contracts duly executed in accordance with the provisions of this
Decree shall be subject to the approval of the Minister of Public Works, Transportation and
Communications, the Minister of Public Highways, or the Minister of Energy, as the case may be.
Section 6. Assignment and Subcontract. The contractor shall not assign, transfer, pledge,
subcontract or make any other disposition of the contract or any part of interest therein except
with the approval of the Minister of Public Works, Transportation and Communications, the
Minister of Public Highways, or the Minister of Energy, as the case may be. Approval of the
subcontract shall not relieve the main contractor from any liability or obligation under his contract
with the Government nor shall it create any contractual relation between the subcontractor and
the Government.
Section 7. Responsibility of the Contractor. The contractor shall assume full responsibility for
the contract work until its final acceptance by the Government and shall be held responsible for
any damage or destruction of works except those occasioned by force majeure. Except likewise
for force majeure, the contractor shall be fully responsible for the safety, protection, security, and
convenience of his personnel, third parties, and the public at large, as well as the works,
equipment, installation and the like to be affected by his construction work.
Section 8. Adjustment Contract Price. Adjustment of contract price for construction projects may
be authorized by the Minister of Public Works, Transportation and Communications, the
Minister of Public Highways, or the Minister of Energy, as the case may be, upon
recommendation of the National Economic and Development Authority, if during the effectivity
of the contract, the cost of labor, equipment, materials and supplies required for the construction
should increase or decrease due to direct acts of the Government. The adjustments of the
contract price shall be made using appropriate formulas established in accordance with the
rules and regulations to be promulgated under Section 12 of this Decree.
Section 9. Change Order and Extra Work Order. A change order or extra work order may be
issued only for works necessary for the completion of the project and, therefore, shall be within
the general scope of the contract as bidded and awarded. All change orders and extra work
orders shall be subject to the approval of the Minister of Public Works, Transportation and
Communications, the Minister of Public Highways, or the Minister of Energy, as the case may
be.
Section 10. Inspection and Construction of Contract Work. Inspection of the contract work shall
be made by the Government while such contract work is in progress to ascertain that the
completed works comply in all respects with the standards and requirements set forth in the
contract documents. Notwithstanding such inspection, the contractor shall be held responsible
for the acceptability of the finished works. The contractor shall promptly replace all materials and
correct all works determined by the Government as failing to meet contract requirements.
Section 11. Government's Right to Take Over Contract Work. The Government may take over
the contract work should the contractor abandon the contract work, or unduly delay the
prosecution of the contract work, or become insolvent, or assign his assets for the benefit of his
creditors, or be adjudged bankrupt, or assign the contract work without written approval by the
Government, or violate any condition or term of the contract. In any of these cases, the
Government may terminate the employment of the contractor and take over the contract work
after giving due notice to the contractor and his sureties.
Section 12. Implementing Rules and Regulations. The Minister of Public Works, Transportation
and Communications, as the lead official, the Minister of Public Highways, the Minister of
Energy, and the Director- General of the National Economic and Development Authority, shall
jointly promulgate the rules and regulations to implement the provisions of this Decree. Once
approved by the President of the Philippines, these implementing rules and regulations shall be
applicable to all contracts for infrastructure and other construction projects of all government
agencies including government-owned or controlled corporations and other instrumentalities.
Section 13. Separability Clause. If any provision of this Decree is held unconstitutional, the other
provisions shall remain valid.
Section 14. Repealing Clause. All Acts, Charters, Decrees, Letters of Instructions, Executive
Orders, Proclamations, rules and regulations or parts thereof in conflict with the provisions of this
Decree are hereby repealed or modified accordingly.
Done in the City of Manila, this 11th day of June, in the year of Our Lord, nineteen hundred and
seventy-eight.