AL DHAFRA PETROLEUM OPERATIONS COMPANY LTD.

CONSTRUCTION WORKS FOR HALIBA WELLS TIE-INS FOR MAIN BODY & NEAR HALIBA
PROSPECTS
Project No. 8043
DOCUMENT / DRAWING COMMENTS RESOLUTION SHEET (CRS)
Projects Engineering Division

COMPANY Transmittal Reference: Date CONSULTANT Transmittal Reference: Date


ADPA‐WTRAN‐018274 18.01.2023 ‐
Document / Drawing Title COMPANY Document / Drawing Number with Rev. No. Review code
GAD for Chemical Injection Code 2 – Reviewed with
Package Including Skid Lifting P8043-30-71-21-5606-Rev-B
Comments

S. No. Page No. / Clause No. COMPANY Comments SUPPLIER Response Status / Remarks
Height of the platform increased to access the
PRV

Increase the height of platform and keep the


1. Sheet-1 of 3
PSV at 1.5m height from grating

Provide Shed for complete CI Skid with lighting


2. Sheet-2 of 3 Shed & Lighting are not Part of Scope.
arrangement

3. Sheet-2 of 3 Align with P&ID and Design Basis Noted and confirmed as per P&ID

Checked By Job Title Date Signature

B MANOJ KUMAR Deputy Project Manager 24.01.2023

Approved By Job Title Date Signature

SEKAR G K Engineering Manager 24.01.2023

TEC-PE-FRM-016_Rev.00_Comments Resolution Sheet (CRS)