GBRG1-MX7771-00001-R02-Mech Spec For Mobile NAG Well Equalisation and Killing Facility Package
GBRG1-MX7771-00001-R02-Mech Spec For Mobile NAG Well Equalisation and Killing Facility Package
Re-Issued for
R02 27 May 2019 M. Jibril E. Aneke O. Raji
Review/Comments
Restricted
ECCN: EAR 99 Deminimus
This document is made available subject to the condition that the recipient will neither use nor disclose the contents except as agreed in
writing with the copyright owner. Copyright is vested in Shell International Petroleum Co. Ltd.© All rights reserved.
Neither the whole nor any part of this document may be reproduced or distributed in any form or by any means (electronic, mechanical,
reprographic, recording or otherwise) without the prior written consent of the copyright owner.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
Guidelines:
1. Please consider using hyperlinks rather than embedding large documents.
2. Fonts must not be altered from the standard styles.
3. Graphs to be without borders.
4. Use non-breaking spaces between numbers and units Ctrl+Shift+Space
5. Special Characters such as degree (°C) refer to: http://www.alt-codes.net/
6. Maps to follow Shell mapping standards.
7. Figures & tables to be incorporated in the text, with attachments if a larger figure will
benefit (reference attachment in caption). Captions below figure using the Insert Caption
command.
8. Units are Oil Field Metric. If Oil field standard units are used (e.g. ft and psi, then the
metric translation must be put straight afterwards e.g. 1000ft [305m])
9. Use m3 rather than bbl/ft3
Revision Philosophy:
a. All FEED documents for review shall be issued at R01, with subsequent R02, R03, etc as
required.
b. All documents approved for issue or approved for design shall be issued at A01with
subsequent A02, A03, etc as required. (Management of Change is required for A02, A03,
etc).
c. All Detailed Design documents for review shall be issued at D01, with subsequent D02,
D03, etc as required.
d. All documents approved for construction shall be issued at C01with subsequent C02,
C03, etc as required. (Management of Change is required for C02, C03, etc).
e. All approved “As Built” documents shall be issued at Z01, with subsequent Z02, Z03,
etc as required. (Management of Change is required for Z02, Z03, etc).
Revision History
SWO-SCiNDO-GBRG1-MX7771-00001 Page 2 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
Table of Contents
1. INTRODUCTION 4
2. PROJECT OVERVIEW 5
2.1. Project Location 5
2.1.1. Background 5
2.2. Definitions 6
2.3. Abbreviations 8
3. DESIGN STANDARDS 8
3.1. Shell DEPs (Version 43) 8
3.2. Project Documents 9
3.3. Conflicting Requirements 9
3.4. Deviations/Exceptions to Specifications 10
4. SCOPE OF SUPPLY 10
4.1. General 10
4.2. Extent of Supply 10
4.3. Exclusions 11
4.4. QA/QC Requirements 11
4.5. Documentation/Certification 12
4.6. Sub-Contracting 12
4.7. Spares 12
5. ENVIRONMENTAL DESIGN CRITERIA 13
5.1. General 13
5.2. Site Environmental Data 13
Air Temperature 13
Wind Data 13
6. TECHNICAL REQUIREMENTS 14
6.1. General 14
6.2. Design Loading 14
6.3. Design Requirements 15
6.3.1. Process Design 15
6.3.2. Mechanical Design 15
6.3.3. Instrumentation and Control 15
6.3.4. Structural 15
6.4. Materials 15
6.5. Operating and Maintenance Requirement 16
6.6. Weight control 16
6.7. Training 16
6.8. Nameplates 16
6.9. HSE 17
6.9.1. Operating Conditions 17
6.10. Noise 17
7. GUARANTEES 18
7.1. Warranty/Process Guarantee 18
8. INSPECTION, TESTING AND CERTIFICATION 18
SWO-SCiNDO-GBRG1-MX7771-00001 Page 3 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
8.1. General 18
8.2. Inspection 18
8.3. Material Testing & Certification 18
9. PAINTING AND PREPARATION FOR SHIPMENT 18
9.1. Painting & Protective Coating 18
9.2. Preparation for Shipment 19
10. TRANSPORTATION 19
11. SPECIAL TOOLS 20
12. QUALITY ASSURANCE 20
13. INFORMATION AND DOCUMENTATION 21
14. APPENDICES: APPENDIX A: DEVIATION REQUEST FORM 21
1. INTRODUCTION
This specification defines the minimum technical requirements for the mechanical
design, manufacture, inspection & testing, documentation, preparation for shipment and
delivery of NAG Well Equalization& Killing Facility Package for the Gbaran Single Well
Opportunities Project.
SWO-SCiNDO-GBRG1-MX7771-00001 Page 4 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
The NAG Well Equalization& Killing Facility Package covered in this document shall be
designed to meet the requirements of this specification and comply with the
specifications, standards and codes referred herein.
The scope of this specification shall define all services and materials necessary for the
following activities:
2. PROJECT OVERVIEW
2.1. Project Location
The Gbaran field was discovered in 1967 by Gbaran-001 and is located in OML 28 about
110 km west of Port Harcourt and 13 km North-West of Yenagoa.
2.1.1. Background
The Gbaran-026 Hook-up and F1B/F22B Development opportunity is part of SPDC‟s
Single Wells opportunities portfolio for quick win delivery of gas to fill the gap in Shell
JV export gas value stream (NLNG T1-T6) from 2020 at competitive CAPEX. The
opportunity entails developing ca. 284.9Bscf of gas and 11.7MMstb of condensate from
the Gbaran F1000B and F2200B reservoirs and understanding the deliverability of the
High Pressure play in Nigeria. The Gbaran-26 well, drilled in 2015, is part of SPDC‟s
campaign to develop High Pressure High Temperature (HPHT) reservoirs around the
Gbaran Area in a bid to increase its hydrocarbon resource volumes. The drilling of
Gbaran-026 confirmed the presence of hydrocarbon in the F2200B reservoir and was
also used to appraise the already proven F1000B reservoir. It is proposed to drill a
second NAG well (Gbaran-F1F22) from the Gbaran 23/25/26 well cluster to carry out a
6-month Extended Well Test (EWT) of the F2200B reservoir through the Gbaran CPF.
Data gathered during the EWT will be used to develop and secure approval for the
F2200B RDP. Subsequently, the F2200B reservoir will be fully developed by producing
through the Gbaran CPF. Once F2200B is depleted, the Gbaran-F1F22 well will be re-
completed to target the crestal volumes on F1000B.
The Gbaran-026 Hook-up and F1B/F22B Gas Development opportunity involves the
following:
Drilling of GBAR-F1F22 NAG well from the GBAR-23/25well cluster and initial
completion on F2200B to develop 49Bscf of gas and 1.6MMstb of condensate. When
SWO-SCiNDO-GBRG1-MX7771-00001 Page 5 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
F2200 is depleted, the well will be re-completed on the shallower F1000B reservoir to
develop 160 Bscf of gas and 5MMstb of condensate.
Completion of GBAR-026 on the F1000B reservoir to develop 79.5Bscf of gas and
2.7MMstb of condensate.
Laying of 10” x 5km bulkline from the Gbaran well cluster to Gbaran CPF and tie-in of
the 2 wells (GBAR-26 and GBAR-F1F22) to the bulkline via standardized HPHT well
hook-up system for production through the CPF.
The well and reservoir pressures for F1000B and F2200B are circa 11,000psi and
13,000psi, respectively. These pressures are higher than those previously experienced in
SPDC.
The project value drivers are:
I. Increase gas wells capacity to guarantee Supply Commitment
II. Grow Reserves
III. Reduce life cycle cost (CAPEX/OPEX)
IV. Schedule
2.2. Definitions
For this Specification, the following definitions shall have the meanings stated:
SWO-SCiNDO-GBRG1-MX7771-00001 Page 6 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
The party that initiates the project and ultimately pays for its
design and construction, in this case, the Shell Petroleum
SHELL/ Development Company of Nigeria Ltd (SPDC).
PURCHASER:
The Purchaser may either be the Principal, its
agent/consultant or Contractor.
INSPECTION Third party.
AUTHORITY:
The party that carries out all or part of the design,
engineering, procurement, construction, commissioning or
CONTRACTOR: management of a project or operation of a facility. The
Principal may undertake all or part of the duties of the
Contractor.
The party that manufactures and supplies equipment and
VENDOR:
services to perform the duties specified by the Contractor.
The contracting company that carries out pre-assembly of the
SYSTEM
work package at a dedicated site in Europe prior to equipment
INTEGRATOR:
shipment to the Nigerian construction site.
SHALL: This indicates a mandatory requirement.
This indicates a preferred (but not mandatory) course of
SHOULD:
action.
MAY: This indicates a possible course of action
The party who initiates the project and ultimately specifies the
technical requirements, which is SPDC. The principal may
PRINCIPAL:
also include an agent or consultant, authorised to act for the
principal.
The party who supplies the equipment to perform the duties
SUB- specified by the Contractor. The party shall also be considered
CONTRACTOR: synonymous with the term manufacturer but may not
necessarily be the Manufacturer.
The party who manufactures the equipment to perform the
MANUFACTURER: duties specified by the Contractor/Purchaser. Not necessarily
the Sub-Contractor.
The body/organization, appointed to carry out an
INSPECTING
independent design review, and ensure compliance to QA
AUTHORITY:
processes, as required by the Codes and Specifications.
SWO-SCiNDO-GBRG1-MX7771-00001 Page 7 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
2.3. Abbreviations
ASME American Society of Mechanical Engineers
DEP Design and engineering practices
EIA Environmental Impact Assessment
FAT Factory Acceptance Test
FEED Front End Engineering and Design
HPHT High Pressure High Temperature
HSE Health, Safety, Security and Environment
ISO International Organization for Standardization
MESC Material and Equipment Standards and Codes
NAG Non-associated Gas
NDE Nondestructive Examination
PEFS Process Engineering Flow Scheme
QMS Quality Management System
SCiN-DO Shell Companies in Nigeria Design Office
SDRL Supplier Document Requirement Listing
SPDC Shell Petroleum Development Company (Nigeria)
UFS Utility Flow scheme
3. DESIGN STANDARDS
The design shall comply fully with the regulations, standards and codes. The Vendor
shall list in detail any comments or exceptions to the applicable DEPs which apply to his
offer. Unless otherwise specified, DEP versions 42 shall be used.
SWO-SCiNDO-GBRG1-MX7771-00001 Page 8 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
Latest editions of all Codes and Standards shall be applicable in accordance the date that
the contract is signed.
Further clarifications in case of any unresolved conflict shall be referred to the Principal.
SWO-SCiNDO-GBRG1-MX7771-00001 Page 9 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
The written application on a Deviation Request Form (blank copy included in Appendix
A) shall identify the document affected, details of the deviation and the reason for it, the
proposed alternative, and the cost and delivery implications. The deviation request shall
be submitted to the PRINCIPAL for processing.
The PRINCIPAL‟s approval of the Deviation Request Form shall be required before
work affected by the deviation can proceed. Where no deviations from this specification
or referenced datasheets are stated, it shall be assumed that the equipment complies with
this specification in all respects.
4. SCOPE OF SUPPLY
4.1. General
The Package shall be supplied, and tested, complete with all necessary accessory
equipment and materials for safe and satisfactory operation and maintenance. All
equipment shall be supplied complete and requiring minimum site work to install. The
Package shall meet the requirement of the specifications referred to in section 3. of this
document.
The Mobile Package shall include but not limited to the following:
SWO-SCiNDO-GBRG1-MX7771-00001 Page 10 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
4.3. Exclusions
The following items are excluded from the scope of supply:
SWO-SCiNDO-GBRG1-MX7771-00001 Page 11 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
4.5. Documentation/Certification
The Vendor shall develop a Supplier Document Schedule (SDS) and ensure that the
documents are provided within the stated time scale and in the correct quantity. Review
of Supplier documents will be subject to a turn-around period as agreed with the
Principal (from document receipt to dispatch from the Purchaser). This shall be allowed
for in the Supplier‟s manufacturing program.
The Vendor shall review this Specification and advise of any documents which are not
considered appropriate to the Scope of Supply or which can be combined with other
documents.
4.6. Sub-Contracting
The PRINCIPAL/CONTRACTOR shall be provided with “un-priced” copies of all
major sub-orders together with technical details including material specification.
Sub-orders for main items shall be accompanied with a detailed material specification
which specifies the requirements for heat treatment, chemical composition constraints,
impact testing, certification, NDE and hardness limitations, etc.
4.7. Spares
A detailed list of commissioning/start-up spares, insurance spares and 2 years operations
spares shall be provided with the tender. The commissioning/start-up spares shall be
included in the base scope of supply.
SWO-SCiNDO-GBRG1-MX7771-00001 Page 12 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
Spares shall be supplied for any diagnostics equipment and specialized tools required for
local maintenance, as applicable.
All required equipment, tools and spares shall be available prior to any post
commissioning activities.
Spare parts shall be specified in the Electronic Spare Parts Inter-Changeability Record
(E-SPIR), a copy of which shall be provided with the Sub-Contractor/Manufacturer‟s
bid.
The E-SPIR and spares quotation should cover all the equipment within the Package,
including but not limited to mechanical, electrical, instrumentation and electronic
components.
Air Temperature
Mean minimum temperature: 23oC
Minimum temperature: 18oC (Design Value)
Mean maximum temperature: 31oC
Maximum temperature: 38oC (Design Value)
Minimum swamp temperature 25°C (NB 23°C to be used
wherever a margin is required)
Ground temperature: 25 - 27.5oC
Black-bulb temperature for oil: 80oC (Design Value)
Relative Humidity: 45 – 100% (Design Value
at 100%)
Wind Data
Design Wind Speed: 35.6m/s
Location specific wind direction data and other detailed information are available in the
Gbaran Ubie EIA report.
The Gbaran Ubie project location is situated in the Niger Delta. The Niger delta area is
flat with river/creek crossings. Production stations may be located in swamp, land,
SWO-SCiNDO-GBRG1-MX7771-00001 Page 13 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
seasonally flooded land, or dry land. It is noted that drainage is poor particularly in the
April to October rainy season.
Rainfall
Heavy rainfall can be expected in the wet season during months of April through
October.
Dust:
During November/December of every year, in the Harmattan season, the atmosphere is
laden with extremely fine dust (particle size of 5 microns or less), which can penetrate
equipment, block air filters, etc.
Lightning
Very frequent in the rainy season
6. TECHNICAL REQUIREMENTS
6.1. General
The NAG Well Equalization Package shall be designed and constructed in accordance
with this specification for an operating life of 25 years.
Manufacturing and fabrication methods, and personnel involved in the process shall be
qualified in accordance to the Codes and Standards as referenced in section 2.0. All
welding shall be done by qualified welders, and in accordance to qualified procedure.
Qualification tests for welders and welding procedures shall comply with ASME IX
specification.
All necessary transportation and installation lifting aids, lifting beams if required, lifting
lugs, slings and shackles shall be provided.
SWO-SCiNDO-GBRG1-MX7771-00001 Page 14 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
6.3.4. Structural
Supplier shall refer to (SWO-SCiNDO-GBRS1-CX7880-00003) - StructuralSteel
Specification, with respect to design, materials and lifting requirements and arrangements
for structural steelwork.
6.4. Materials
All materials to be used for manufacturing and fabrication of the Well Equalization
Package shall be suitable for the intended service. Materials shall be selected in
SWO-SCiNDO-GBRG1-MX7771-00001 Page 15 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
The materials for manufacturing of equipment shall be stated in the Technical Bid for
review by the Purchaser.
The Contractor shall ensure that the most effective layout for maintenance within and
around the package is achieved. Vendor shall incorporate human factors engineering.
Detailed assembly drawings of all items or components that require periodic
maintenance or breakdown repair to be supplied in full and included in the Vendor‟s
scope of supply.
6.7. Training
Onsite training shall be provided to SPDC operations/maintenance personnel. The
objective is to develop their competence to such a level required to successfully operate
and maintain the Package. The level of competence should include 20,000 hours pump
inspection.
6.8. Nameplates
All nameplates shall be made from stainless steel or other corrosion resistant material.
They shall show as a minimum:
Manufacturers‟ name
Year of Manufacture
Equipment name
Equipment type and tag Number
Model and serial Number
Equipment size
rated flow rated head (for the pumps)
SWO-SCiNDO-GBRG1-MX7771-00001 Page 16 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
6.9. HSE
Health, Safety, and Environment (HSE) information (e.g. Material Safety Data sheets for
Chemicals) shall be provided as requested, to the satisfaction of the Purchaser at any
stage of the project.
There will be provision of eyewash in the supply package for safety reasons as part of
ISO 14001 requirements. The Vendor shall provide an organization chart specific to the
execution of the Well Equalization Package supply showing clearly the line
responsibilities for HSE issues. The Vendor shall be responsible for ensuring that the
package and services supplied meet all applicable Nigerian, SPDC, and International
regulations on HSE issues including ISO14001.
The reciprocating pumps shall be capable of operating from minimum flow to maximum
rated flow. They shall be designed to manage full rated flow and shall be provided with a
minimum flow control loop to recycle discharge fluids back to suction. The reciprocating
pump packages shall be designed to achieve 100% system turndown using the recycle
capability.
In addition to this all units shall be provided with low flow, low suction pressure and
high discharge pressure trips as standard.
6.10. Noise
Noise limit for all equipment within the scope of supply shall be 85dB (A) per DEP
31.10.00.31-Gen.„(Noise Control (Amendments/Supplements to ISO 15664)‟ at any
point 1m from the surface of the equipment with the pumps operating at:
a) Design point, and
b) On minimum continuous flow with the minimum flow valve in operation.
The noise data sheet shall be completed as specified.
This scope describes the specific requirements for materials of construction to be used in
the design and fabrication of process and utility piping systems. The basis for the line
classes will be the DEP 31.38.01.15-GEN. Piping Classes Exploration and Production to
meet the Shell Development Petroleum Company Nigeria (SPDC Nigeria) project
requirements.
The design shall comply fully with the statutory laws and regulations of Nigeria and all
relevant SPDC and international Standards/Codes of Practice and industry published
guidelines.
SWO-SCiNDO-GBRG1-MX7771-00001 Page 17 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
The Shell MESC/SAP coding system will be utilized within this project.
For piping components that do not have a MESC rating code, XXX.X shall be used until
a rating code is assigned.
7. GUARANTEES
7.1. Warranty/Process Guarantee
The materials, integrity of construction, workmanship and satisfactory operation of the
Package shall be in accordance with the requirements of the purchase requisition and
shall be guaranteed for a period of 12 months after commissioning or 18 months after
delivery whichever comes first.
8.2. Inspection
The vendor shall prepare an Inspection and Test Plan, which shall comply with the
requirements of the associated relevant DEPs, codes and standards for each tank and
shall conform to the requirement of DEP 61.10.08.11-Gen.
All tests shall be performed in accordance with written test procedures to be submitted
to Principal for review as required by this specification. Testing requirements shall be as
required per the specifications and standards referenced in section 2 of this specification.
Fully detailed test procedures shall be submitted for approval for all tests.
Hydrostatic tests.
Material testing and certification.
Acceptance test.
SWO-SCiNDO-GBRG1-MX7771-00001 Page 18 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
Nozzles shall be painted to the flange edges, inside bolt holes, and up to the gasket
surface. Fireproofed or insulated surfaces shall be shot blasted and given one coat of
primer only.
As a guide the standard procedures shall be at least equivalent to the procedures for long
term preservation set out in Shell DEP 70.10.70.11-Gen. „Preservation of new and old
equipment standing idle‟ Section 7.
Following testing, the Package and accessories shall be cleaned thoroughly and dried. All
equipment shall be shipped fully assembled, where practicable, providing that no damage
can be caused due to shipment forces or lifting. All delicate instrument that are
vulnerable to damage during transportation, shall be removed and separately packed. All
terminal flanges to be sealed and fitted with steel blanking plates bolted to the flange
with a minimum of 4 bolts.
All items shall be properly packed and protected from damage during shipment. Each
crate, bag or package shall be clearly identified with the item number and purchase order
number to facilitate installation in the field and shall be securely fastened to the item.
Tags and wire shall be stainless steel.
All instruments, and any equipment which extends beyond the skid edge, shall be
removed, tagged and crated in waterproof boxes. The boxes shall be securely attached to
the skid for transport. The contents of each box shall be clearly stated on the outside of
the box.
10. TRANSPORTATION
The package supplied will be transported from the Sub-Contractor/Manufacturer‟s
works/test facility by sea, barge and/or by truck to site.
SWO-SCiNDO-GBRG1-MX7771-00001 Page 19 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
The CONTRACTOR shall provide all required transportation aids, lifting attachments,
lifting frames, spreader beams, slings, shackles etc. All lifting equipment shall be
designed in accordance with the General Structural Specification listed in section 2.0 of
this document.
Certification and load test certificates shall be delivered with the goods. Any
Skid/package with dimensions or weights outside the above limits must be approved by
the Purchaser.
All transportation by road and water shall be guided by LIRA. Logistics Infrastructure
and Resources Assessment for Gbaran Ubie Phase II Project.
SWO-SCiNDO-GBRG1-MX7771-00001 Page 20 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
PRINCIPAL or the CONTRACTOR shall from time to time, audit the quality processes
of the Sub-Contractor/Manufacturer.
SWO-SCiNDO-GBRG1-MX7771-00001 Page 21 of 22
This document is controlled electronically and is uncontrolled when printed.
SWO-SCiNDO-
Mech. Spec. for Mobile NAG well Equalization & Killing
GBRG1-MX7771-
Facility Package (A-1001) 00001-R02
Originating Organisation:
...……….....................................................................................
RESPONSE: (By the Technical Authority, with detailed justification, maximum 180
characters. Response required within 5 working days of receipt).
Distribution:
SWO-SCiNDO-GBRG1-MX7771-00001 Page 22 of 22