Tasks Details:-
S.No Task Description of Qty Units Rate Labour Skilled/ Material Total Person
Code Item/Task (Rs) component Semi Skilled Cost (Rs) Cost (Rs) Days
(Rs) component
(Rs)
1 33524 Skilled wages towards 1 LS 5172 0 0 5172 5172 0
cost of Technical
Assistants/Barefoot
Engineers @ 1.25% of
the total cost
2 0367 UNSKILLED LABOUR 1500 Cu.m 275.56 412169 0 0 412169 1682
charges for Earth Work
Excavation and dumping
earth for bund formation
in Hard soil with lead of
20m and lift of 2m
3 37372 Provision For Work Wise 1 Nos. 100 0 0 100 100 0
File
4 35717 Name Board using pre- 1 No. 1500 0 0 1500 1500 0
cast slab
I certify that,I have inspected the work/project site on ........................... date and found the specifications and quantities provided in the
estimate are correct, appropriate and as per the standards and purposefulness of the proposed asset/work.Based on my visit, I am
according technical approval for Rs.418941/-
I certify that, I am responsible for proper preparation of estimate and the estimate is technically approved for Rs.418941/- , with
technical approval number 11/GWRP/041/2019-2020 dated...........................
I abide to be punished if estimates are found with deviations above 10%.
Name of the technical approval authority: Designation of the technical approval authority: