Report As of May 8, 2022
Report As of May 8, 2022
Activity ID Activity Name Original Performance Early Start Early Finish Late Start Late Finish Total April May June July
Duration % Complete Float 1 2 3 4
28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25
86 2.69% 05-May-22 13-Jul-22 04-May-22 13-Jul-22 -1 2.69%, OFFICE BUILDING, C
OFFICE BUILDING, CO
CORE & SHELL
86 0% 05-May-22 13-Jul-22 04-May-22 12-Jul-22 -1 0%, MILESTONE
MILESTONE
M-1000 Issuance of NOA, NTP & PO 0 100% 05-May-22 04-May-22 Issuance of NOA, NTP & PO
M-1010 Start of Contract Day 1 0 100% 05-May-22 04-May-22 Start of Contract Day 1
M-1020 Kick Off Meeting 0 100% 05-May-22 04-May-22 Kick Off Meeting
M-1030 Ground Breaking Ceremony 0 100% 05-May-22 04-May-22 Ground Breaking Ceremony
M-1040 Excavation Complete 0 0% 09-May-22 12-Jul-22 55 Excavation Complete
M-1050 Concrete Topping Off 0 0% 06-Jul-22 12-Jul-22 5 Concrete Topping Off
M-1060 Project Complete 0 0% 13-Jul-22 12-Jul-22 -1 Project Complete
17 100% 05-May-22 05-May-22 04-May-22 13-Jul-22 100%, PRE CONSTRUCTION
PRE CONSTRUCTION
General Requirements 17 100% 05-May-22 05-May-22 04-May-22 13-Jul-22 100%, General Requirements
GR-1000 Securing Miscellaneous Permits 7 100% 05-May-22 05-May-22 04-May-22 04-May-22
11-Apr-22 A 18-Apr-22 A
GR-1010 Mobilization Works 6 100% 05-May-22 05-May-22 04-May-22 04-May-22
18-Apr-22 A 23-Apr-22 A
GR-1020 Construction of temporary facilities 7 100% 05-May-22 05-May-22 13-Jul-22 13-Jul-22
25-Apr-22 A 02-May-22 A
60 0.68% 05-May-22 06-Jul-22 04-May-22 12-Jul-22 5 0.68%, CONSTRUCTION
CONSTRUCTION
Earthworks 25 13.38% 05-May-22 26-May-22 04-May-22 12-Jul-22 40 13.38%, Earthworks
E-1000 Survey Works(Staking/layout) 1 100% 05-May-22 05-May-22 04-May-22 04-May-22
28-Apr-22 A 28-Apr-22 A
E-1010 Clearing/grubbing 3 100% 05-May-22 05-May-22 04-May-22 04-May-22
29-Apr-22 A 30-Apr-22 A
E-1020 Bulk/structural excavation 5 10% 05-May-22 09-May-22 04-May-22 07-May-22 -1
04-May-22 A 10%, 09-May-22
E-1030 Hauling & Disposal 5 10% 05-May-22 07-May-22 09-Jul-22 12-Jul-22 56
02-May-22 A 10%, 07-May-22
E-1035 Manual Trimming 1 0% 10-May-22 10-May-22 16-May-22 16-May-22 5
10-May-22 0%, 10-May-22
E-1040 Backfilling/Compaction 8 0% 18-May-22 26-May-22 17-May-22 25-May-22 -1
18-May-22 0%, 26-May-22
Civil Works 50 0% 10-May-22 06-Jul-22 09-May-22 12-Jul-22 5 0%, Civil Works
Sub Structure 29 0% 10-May-22 11-Jun-22 09-May-22 12-Jul-22 26 0%, Sub Structure
Footing Foundation 7 0% 10-May-22 17-May-22 09-May-22 16-May-22 -1 0% 0%
0%, Footing Foundation
0%
Footing Tie Beam 7 0% 17-May-22 24-May-22 18-May-22 25-May-22 1 0%, Footing Tie Beam
Ground Floor 14 0% 27-May-22 11-Jun-22 26-May-22 12-Jul-22 26 0% 0% 0% 0% 0% 0%, Ground Floor
Super Structure 27 0% 06-Jun-22 06-Jul-22 04-Jun-22 12-Jul-22 5 0%, Super Structure
2nd Floor 15 0% 06-Jun-22 22-Jun-22 04-Jun-22 12-Jul-22 17 0% 0%
0% 0%, 2nd Floor
3rd Floor 15 0% 16-Jun-22 02-Jul-22 15-Jun-22 12-Jul-22 8 0% 0%0% 0%, 3rd Floor
4th Floor 9 0% 27-Jun-22 06-Jul-22 25-Jun-22 05-Jul-22 -1 0% 0%0%, 4th Floor
0%
5th Floor 0 0% 0
6 0% 07-Jul-22 13-Jul-22 06-Jul-22 12-Jul-22 -1 0% 0%, POST CONSTRUCTION
0%
POST CONSTRUCTION
CONSTRUCTIO
P150,000.00 P1,000,000.00
P120,000.00 P800,000.00
P90,000.00 P600,000.00
P60,000.00 P400,000.00
P30,000.00 P200,000.00
Estimate At Completion Cost
Budgeted Total Cost
Actual Total Cost
Remaining Total Cost
Planned Value Cost
P0.00
1 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25
Earned Value Cost
1 2 3 4
April May June July