OFFICE BUILDING, CORE SHELL OVERALL CONSTRUCTION SCHEDULE 29-Oct-22 22:09

Activity ID Activity Name Original Performance Early Start Early Finish Late Start Late Finish Total April May June July
Duration % Complete Float 1 2 3 4
28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25
86 2.69% 05-May-22 13-Jul-22 04-May-22 13-Jul-22 -1 2.69%, OFFICE BUILDING, C
OFFICE BUILDING, CO
CORE & SHELL
86 0% 05-May-22 13-Jul-22 04-May-22 12-Jul-22 -1 0%, MILESTONE
MILESTONE
M-1000 Issuance of NOA, NTP & PO 0 100% 05-May-22 04-May-22 Issuance of NOA, NTP & PO
M-1010 Start of Contract Day 1 0 100% 05-May-22 04-May-22 Start of Contract Day 1
M-1020 Kick Off Meeting 0 100% 05-May-22 04-May-22 Kick Off Meeting
M-1030 Ground Breaking Ceremony 0 100% 05-May-22 04-May-22 Ground Breaking Ceremony
M-1040 Excavation Complete 0 0% 09-May-22 12-Jul-22 55 Excavation Complete
M-1050 Concrete Topping Off 0 0% 06-Jul-22 12-Jul-22 5 Concrete Topping Off
M-1060 Project Complete 0 0% 13-Jul-22 12-Jul-22 -1 Project Complete
17 100% 05-May-22 05-May-22 04-May-22 13-Jul-22 100%, PRE CONSTRUCTION
PRE CONSTRUCTION
General Requirements 17 100% 05-May-22 05-May-22 04-May-22 13-Jul-22 100%, General Requirements
GR-1000 Securing Miscellaneous Permits 7 100% 05-May-22 05-May-22 04-May-22 04-May-22
11-Apr-22 A 18-Apr-22 A
GR-1010 Mobilization Works 6 100% 05-May-22 05-May-22 04-May-22 04-May-22
18-Apr-22 A 23-Apr-22 A
GR-1020 Construction of temporary facilities 7 100% 05-May-22 05-May-22 13-Jul-22 13-Jul-22
25-Apr-22 A 02-May-22 A
60 0.68% 05-May-22 06-Jul-22 04-May-22 12-Jul-22 5 0.68%, CONSTRUCTION
CONSTRUCTION
Earthworks 25 13.38% 05-May-22 26-May-22 04-May-22 12-Jul-22 40 13.38%, Earthworks
E-1000 Survey Works(Staking/layout) 1 100% 05-May-22 05-May-22 04-May-22 04-May-22
28-Apr-22 A 28-Apr-22 A
E-1010 Clearing/grubbing 3 100% 05-May-22 05-May-22 04-May-22 04-May-22
29-Apr-22 A 30-Apr-22 A
E-1020 Bulk/structural excavation 5 10% 05-May-22 09-May-22 04-May-22 07-May-22 -1
04-May-22 A 10%, 09-May-22
E-1030 Hauling & Disposal 5 10% 05-May-22 07-May-22 09-Jul-22 12-Jul-22 56
02-May-22 A 10%, 07-May-22
E-1035 Manual Trimming 1 0% 10-May-22 10-May-22 16-May-22 16-May-22 5
10-May-22 0%, 10-May-22
E-1040 Backfilling/Compaction 8 0% 18-May-22 26-May-22 17-May-22 25-May-22 -1
18-May-22 0%, 26-May-22
Civil Works 50 0% 10-May-22 06-Jul-22 09-May-22 12-Jul-22 5 0%, Civil Works
Sub Structure 29 0% 10-May-22 11-Jun-22 09-May-22 12-Jul-22 26 0%, Sub Structure
Footing Foundation 7 0% 10-May-22 17-May-22 09-May-22 16-May-22 -1 0% 0%
0%, Footing Foundation
0%
Footing Tie Beam 7 0% 17-May-22 24-May-22 18-May-22 25-May-22 1 0%, Footing Tie Beam
Ground Floor 14 0% 27-May-22 11-Jun-22 26-May-22 12-Jul-22 26 0% 0% 0% 0% 0% 0%, Ground Floor
Super Structure 27 0% 06-Jun-22 06-Jul-22 04-Jun-22 12-Jul-22 5 0%, Super Structure
2nd Floor 15 0% 06-Jun-22 22-Jun-22 04-Jun-22 12-Jul-22 17 0% 0%
0% 0%, 2nd Floor
3rd Floor 15 0% 16-Jun-22 02-Jul-22 15-Jun-22 12-Jul-22 8 0% 0%0% 0%, 3rd Floor
4th Floor 9 0% 27-Jun-22 06-Jul-22 25-Jun-22 05-Jul-22 -1 0% 0%0%, 4th Floor
0%
5th Floor 0 0% 0
6 0% 07-Jul-22 13-Jul-22 06-Jul-22 12-Jul-22 -1 0% 0%, POST CONSTRUCTION
0%
POST CONSTRUCTION
CONSTRUCTIO

P150,000.00 P1,000,000.00

P120,000.00 P800,000.00

P90,000.00 P600,000.00

P60,000.00 P400,000.00

P30,000.00 P200,000.00
Estimate At Completion Cost
Budgeted Total Cost
Actual Total Cost
Remaining Total Cost
Planned Value Cost
P0.00
1 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25
Earned Value Cost
1 2 3 4
April May June July

Remaining Level of Effort Remaining Work Date Revision Checked Approved


Prepared By:
Actual Level of Effort Critical Remaining Work
Actual Work Primary Baseline