PROPOSED CONSTRUCTION SCHEDULE

XSTRUCTURES ENGINEERING CONSULTANTS


As of 28 May '23

ID Task N am e Baseline Start Finish Baseline Start Baseline Finish Act.Start Act.Finish % Com p. Forecast Current Q tr4,2022 Q tr1,2023 Q tr2,2023 Q tr3,2023 Q tr4,2023
D uration % % Sep O ct N ov D ec Jan Feb M ar Apr M ay Jun Jul Aug Sep O ct N ov D ec
0 PROPOSED CONSTRUCTION SCHEDULE298.2 days 10 Oct '22 17 Oct '23 10 Oct '22 11 Oct '23 10 Oct '22 NA 52% 51% 50% 52%
1 PLANNING 52 days 10 Oct '22 03 Jan '23 10 Oct '22 13 Dec '22 10 Oct '22 03 Jan '23 100% 100% 100% 100%
2 Create Site Plans 3 wks 10 Oct '22 04 Nov '22 10 Oct '22 29 Oct '22 10 Oct '22 04 Nov '22 100% 100% 100% 100%
3 Submit Plans for Approval 1 mon 05 Nov '22 15 Dec '22 31 Oct '22 02 Dec '22 05 Nov '22 15 Dec '22 100% 100% 100% 100%
4 Order Materials 8 days 16 Dec '22 03 Jan '23 03 Dec '22 13 Dec '22 16 Dec '22 03 Jan '23 100% 100% 100% 100%
5 Planning Completed 0 days 03 Jan '23 03 Jan '23 13 Dec '22 13 Dec '22 03 Jan '23 03 Jan '23 100% 100% 100% 03/01 0 days
6 SITE WORKS 28 days 04 Jan '23 11 Feb '23 14 Dec '22 18 Jan '23 04 Jan '23 11 Feb '23 100% 100% 100% 100%
7 Erect Fencing 0 days? 03 Jan '23 05 Jan '23 NA NA NA NA 0% 0% 0%
8 Erect Site Buildings 4 days 04 Jan '23 10 Jan '23 14 Dec '22 17 Dec '22 04 Jan '23 10 Jan '23 100% 100% 100% 100%
9 Clear and Level Site 3 wks 11 Jan '23 03 Feb '23 18 Dec '22 11 Jan '23 11 Jan '23 03 Feb '23 100% 100% 100% 100%
10 Prepare Drainage Infrastructure 1 wk 04 Feb '23 10 Feb '23 12 Jan '23 18 Jan '23 04 Feb '23 10 Feb '23 100% 100% 100% 100%
11 Prepare Cabling Infrastructure 1 wk 04 Feb '23 11 Feb '23 12 Jan '23 18 Jan '23 04 Feb '23 11 Feb '23 100% 100% 100% 100%
12 Site Works Completed 0 days 11 Feb '23 11 Feb '23 18 Jan '23 18 Jan '23 11 Feb '23 11 Feb '23 100% 100% 100% 11/02 0 days
13 BUILDING CONSTRUCTION 160.2 days 13 Feb '23 10 Aug '23 19 Jan '23 03 Aug '23 13 Feb '23 NA 59% 64% 60% 59%
14 Pour foundations 4 days 13 Feb '23 17 Feb '23 19 Jan '23 23 Jan '23 13 Feb '23 17 Feb '23 100% 100% 100% 100%
15 Erect steelwork 3 mons 24 Feb '23 28 May '23 28 Jan '23 05 May '23 24 Feb '23 28 May '23 100% 100% 100% 100%
16 Erect wall 2 mons 02 May '23 06 Jul '23 26 Apr '23 29 Jun '23 02 May '23 NA 40% 52% 40% 40%
17 Install roofing superstructure 2 wks 07 Jul '23 20 Jul '23 29 Jun '23 13 Jul '23 NA NA 0% 0% 0% 0%
18 Install roof retracting mechanism 1 wk 21 Jul '23 27 Jul '23 13 Jul '23 20 Jul '23 NA NA 0% 0% 0% 0%
19 Erect seating tiers 3 wks 21 Jul '23 10 Aug '23 13 Jul '23 03 Aug '23 NA NA 0% 0% 0% 0%
20 Building Construction Completed 0 days 10 Aug '23 10 Aug '23 03 Aug '23 03 Aug '23 NA NA 0% 0% 0% 10/08 -6.8 days
21 FIT OUT 42 days 11 Aug '23 29 Sep '23 03 Aug '23 22 Sep '23 NA NA 0% 0% 0% 0%
22 Fit all windows and doors 2 wks 18 Aug '23 01 Sep '23 10 Aug '23 24 Aug '23 NA NA 0% 0% 0% 0%
23 Install electrical cabling 1 wk 11 Aug '23 17 Aug '23 03 Aug '23 10 Aug '23 NA NA 0% 0% 0% 0%
24 Install electrical fittings and fixtures 2 wks 18 Aug '23 01 Sep '23 10 Aug '23 24 Aug '23 NA NA 0% 0% 0% 0%
25 Install all plumbing 2 wks 18 Aug '23 01 Sep '23 10 Aug '23 24 Aug '23 NA NA 0% 0% 0% 0%
26 Install plumbing fittings and fixtures 1 wk 02 Sep '23 08 Sep '23 24 Aug '23 01 Sep '23 NA NA 0% 0% 0% 0%
27 Lay Carabao Grass 1 wk 11 Aug '23 17 Aug '23 03 Aug '23 10 Aug '23 NA NA 0% 0% 0% 0%
28 Erect handrails and fencing 2 wks 11 Aug '23 24 Aug '23 03 Aug '23 17 Aug '23 NA NA 0% 0% 0% 0%
29 Paint rooms, fixtures, fittings, etc. 1 mon 23 Aug '23 22 Sep '23 15 Aug '23 15 Sep '23 NA NA 0% 0% 0% 0%
30 Install PA system 2 days 18 Aug '23 19 Aug '23 10 Aug '23 12 Aug '23 NA NA 0% 0% 0% 0%
31 Install video imaging equipment 3 days 18 Aug '23 21 Aug '23 10 Aug '23 14 Aug '23 NA NA 0% 0% 0% 0%
32 Fit out control room 1 wk 23 Sep '23 29 Sep '23 15 Sep '23 22 Sep '23 NA NA 0% 0% 0% 0%
33 Fit Out Completed 0 days 29 Sep '23 29 Sep '23 22 Sep '23 22 Sep '23 NA NA 0% 0% 0% 29/09 -6.8 days
34 COMMISSIONING 16 days 30 Sep '23 17 Oct '23 22 Sep '23 11 Oct '23 NA NA 0% 0% 0% 0%
35 Test roof mechanism 1 wk 30 Sep '23 06 Oct '23 22 Sep '23 29 Sep '23 NA NA 0% 0% 0% 0%
36 Test PA system 2 days 30 Sep '23 02 Oct '23 22 Sep '23 25 Sep '23 NA NA 0% 0% 0% 0%
37 Test video imaging equipment 2 days 30 Sep '23 02 Oct '23 22 Sep '23 25 Sep '23 NA NA 0% 0% 0% 0%
38 Test control room equipment 1 wk 07 Oct '23 13 Oct '23 29 Sep '23 06 Oct '23 NA NA 0% 0% 0% 0%
39 Obtain official occupancy certificates 1 day 14 Oct '23 14 Oct '23 06 Oct '23 07 Oct '23 NA NA 0% 0% 0% 0%
40 Obtain safety certification 2 days 16 Oct '23 17 Oct '23 07 Oct '23 10 Oct '23 NA NA 0% 0% 0% 0%
41 Official opening 1 day 10 Oct '23 11 Oct '23 10 Oct '23 11 Oct '23 NA NA 0% 0% 0% 0%
42 Commissioning Completed 0 days 17 Oct '23 17 Oct '23 11 Oct '23 11 Oct '23 NA NA 0% 0% 0% 17/10 -5.8 days

CriticalProgress M anualTask Critical Baseline M ilestone M anualSum m ary Inactive Task


Task Start-only CriticalSplit M ilestone Project Sum m ary Inactive M ilestone
Split Finish-only Baseline Sum m ary Progress ExternalTasks Inactive Sum m ary
Task Progress D uration-only Baseline Split Sum m ary ExternalM ilestone D eadline