Professional Documents
Culture Documents
Contract Accounts Perspective
Contract Accounts Perspective
Contract Accounts Perspective
• Direct purchase
• Supplied from stores
• Transfer from other project/contract
Contract account will be credited −
Direct Expenses
In addition to material and labor, all other expenses, which are directly attributable to
the specific contract account are called direct expenses and will be debited from the
contract account.
a) Contract account will be debited with the full value of Plant & Machinery −
Contract A/cDr(With full value)
To Plant & Machinery A/c(With Full Value)
Contract account will be credited with the depreciated value of Plant & Machinery at the
end of the contract −
Plant & Machinery A/cDr(with Depreciated Value)
To Contract A/c
Sub Contract
When a main or prime contractor assigns some specific work to another contractor as
part of the main contract called as sub contract. Sub-contractors are paid by the main
contractor. Sub-contractors normally do some specialized work, in which they are
specialized. Charges paid to the sub-contractor will be shown in the debit side of the
contract account.
Work in Progress
Uncompleted contracts at the end of the financial year, which are known as work-
inprogress will be accounted as −
• Work-in-progress will be shown at the asset side of the Balance sheet on the
account of expenses incurred the un-completed contracts.
• Value of the work-in-progress will be inclusive of Profit.
• Cash received from the Contractee will be deducted from the value of work-
inprogress.
• Contractee will be treated as a debtor only after completion of the contract.
• Contractee will not be shown as creditor on account of cash received from him.
• Cost of plant and material at the site will be shown separately as “Plant at site”
and “Material at site” on the asset side of the Balance sheet.
Illustration
Please prepare a Contract Account, Contractee Account and Extract of Balance sheet
from the following information as received from M/s “Solid Building Contractor’ for the
period 01-04-2013 to 31-03-2014.
Particulars Amount
Solution
M/s Solid Building Contractor
Contract Account
(For the period 01-04-2013 to 31-03-2014)
Less: Dep.18000
-----------
-----------
Work certified9,600,000
Work uncertified60,000
----------- 102,000
510,000
9,660,000
1,620,000×23×451,620,000×23×45
756,000
Contractee Account
Balance-Sheet
(As on 31-03-2014)
Material at site
Work-in-progress
------------
9,660,000
Less: Reserve756,000
------------
8,904,000
------------
1,224,000
Illustration
Please evaluate the profit of the period by using both of the given methods −
Solutions −
On the Basis of Percentage of Completion Method −
Balance Sheet
Escalation Clause
An Escalation clause is applied to cover up the changes in price due to change in
prices of the raw material or change in utilization of the production capacity. Escalation
clause safeguards both the contractor and the contractee against any unfavorable
change in the cost or the price.
Target Costing
Under this method of a contract, contractee gives target of the production with target
of the expenditure. Contractor cannot increase the cost of contract without increasing
the production. It means, expenditure is fixed with the target of the production.