INSTRUKSI KERJA HARIAN (IKH)

2 5 S E P T E M B E R 2022 (Night Shift)


PT. Bina Sarana Sukses
Site PT Tanjung Alam Jaya
TARGET DAILY PIT 1 D, 25 SEPTEMBER 2022
Weekly Plan 38th 2022 3 4 5 6 7 8 9
PIT 1D 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep Total
Fleet 1 PC1250SP-8R X9212 10,095.63 10,095.63 10,095.63 10,095.63 9,564.79 10,095.63 10,095.63 70,138.55
Fleet 2 PC1250SP-8R X166 8,076.50 10,095.63 10,095.63 10,095.63 9,564.79 10,095.63 10,095.63 68,119.43
Fleet 3 PC1250SP-8R X161 - - 9,707.33 9,707.33 9,196.92 9,547.40 9,707.33 47,866.31
Fleet 4 ZX870H-5G X9238 7,085.37 7,085.37 7,085.37 7,085.37 6,717.55 7,085.37 7,085.37 49,229.77
Fleet 5 ZX870H-5G X9247 - 7,101.78 - - - - - 7,101.78
Total OB 25,257.50 34,378.40 36,983.96 36,983.96 35,044.06 36,824.02 36,983.96 242,455.84
115%
COAL GETTING 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep Total
Fleet 1 ZX350H-5G X9217 - - 1,627.57 1,627.57 1,529.12 1,627.57 1,627.57 8,039.41
Fleet 2 E6210F X9256 1,470.99 1,470.99 - - - - - 2,941.98
Total Coal Getting 1,470.99 1,470.99 1,627.57 1,627.57 1,529.12 1,627.57 1,627.57 10,981.39

TARGET 25 SEPT 2022


OVERBURDEN REMOVAL : 36.980 BCM
COAL GETTING : 1.627 MT
POPULASI UNIT PIT 1D
UNITS RFU :
A. OB REMOVAL :
1. 3 x PC 1250SP-8 (X9212, X161,X166)
2. 2 x ZX 870H-5G (X9238 & x9247)
3. 1 x ZX 350 (X9217)
B. GENERAL & COAL GETTING :
1. 1 x ZX 350 (X9274)
2. 1 x ZX 200 (X9257)
3. 1 x ZX 200 (X9256)
C. HAULLER :
1. 18 x HD (KOMATSU HD-465)
D. SUPPORTS DOZZER :
1. 1 x BULLDOZZER (D-375/D-259)
2. 5x BULLDOZZER (D85E-SS-2/D-276,D-273, D-337, D-277, D-313)
OVERBURDEN REMOVAL

A. 166

PLAN AREA BLASTING P-2

CREST 60

CREST 50 X 9274 Coal Getting C. 212

D. 9238

B. 161

NOTE:
1. Perhatikan area yang ditandai HIGH RISK, jaga
jarak aman unit dan personal dilapangan (Support
Pengawasan dari HSE)
2. Sebelum melakukan pekerjaan, lakukan inspeksi
area terlebih dahulu, sosialisasi JSA
3. Pastikan sarana penerangan front loading
memadai.
Target PDTY PC1250 : 650 bcm/jam
Target PDTY PC870 : 450 bcm/jam
GENERAL ACTIVITY

NOTE:
1. Perhatikan area yang ditandai HIGH RISK, jaga
jarak aman unit dan personal dilapangan (Support
Pengawasan dari HSE)
2. Sebelum melakukan pekerjaan, lakukan inspeksi
area terlebih dahulu, sosialisasi JSA
3. Pastikan sarana penerangan front loading
memadai.

9256 GENERAL SLOPING 65⁰ TOE LINE 60


COAL GETTING & PLAN DEWATERING

POMPA Continue running penurunan level


sump, elv. Act 17 to 14

9217 Coal Getting Seam


D1
PLAN AREA BLASTING P-1

NOTE:
1. Perhatikan area yang ditandai HIGH RISK, jaga
jarak aman unit dan personal dilapangan (Support
Pengawasan dari HSE)
2. Sebelum melakukan pekerjaan, lakukan inspeksi
area terlebih dahulu, sosialisasi JSA
3. Pastikan sarana penerangan front loading
memadai.
DISPOSAL AREA
NOTE:
1. Perhatikan area yang
ditandai HIGH RISK,
jaga jarak aman unit
Dumping Point 1 Fleet (166) dan personal
dilapangan (Support
Pengawasan dari
HSE)
2. Sebelum melakukan
Dumping Point 3 Fleet (9238, 161 & 212)
pekerjaan, lakukan
inspeksi area
terlebih dahulu,
sosialisasi JSA
Plan pembentukan MUD POND Barat
3. Pastikan sarana
Disposal
penerangan front
loading memadai.

CREST

TOE

BOUNDARY

TOE 80
TERIMA KASIH
SELAMAT BEKERJA
SPIRIT MENEMBUS BATAS!