Execution Details for PPNI & PNI Programme at Ankora Yard

S. No. Item Description UOM Rate Quantity Amount Details Remarks

For insertion of Point No. 60A, 60B, 69A,


1 Installation of 1 in12 fan shaped Turnout EA 61200 7.8 477360
69B, 56B, 56B

2 Installation of 1 in 8.5 fan shaped Turnout EA 48600 2 145800 For insertion of Point No. 54A & 61A

For insertion of Point No. 60A, 60B, 69A,


3 Dismantling of Plain Track TM 170 344 87720
69B, 56B, 56B
For insertion of Point No. 60A, 60B, 69A,
4 Scarifying and Digging TM 79.2 344 27244.8
69B, 56B, 56B
For shifting of Switch, Lead Rails & CMS
5 Shifting of Pway Material for lead within 50M MT 125 342.96 42870
Crossing.
For shifting of Switch, Lead Rails & CMS
6 Shifting of Pway Material for lead beyond 50M upto 250M MT 15 342.96 5144.4
Crossing.
For Plain Track Linking in front of Station
7 BG Track Linking MT 350 80.2 28070
Building

8 SEJ Insertion EA 10000 9 90000 For SEJ Insertion in Block at BSYA Yard

9 Fixing of Rail Posts for SEJ, LWR, Curves etc EA 783.9 50 39195
4 labours for 25 days on
regular basis for AT
10 For AT Welding EA 450 100 4500
welding during block
6 labours for 20 days
11 Running and Maintainance of trolley EA 450 120 54000
during PPNI & PNI
Total Payable Amount ₹ 10,01,904.20