Professional Documents
Culture Documents
Part 2 - Handouts of Presentations - Updated 201806
Part 2 - Handouts of Presentations - Updated 201806
Part (II)
Handouts of Presentations
Egypt
2018
Lessons learned from Disasters Updated on: Jan. 2018
2,500
immediate
fatalities;
20,000+ total
Many other
offsite injuries HAZARD:
Highly Toxic
Methyl Isocyanate
2
/
4
9
ARMC 1
Lessons learned from Disasters Updated on: Jan. 2018
HAZARD:
Flammable LPG
in tank
3
/
4
9
HAZARD:
Flammable
hydrocarbon vapors
4
/
4
9
ARMC 2
Lessons learned from Disasters Updated on: Jan. 2018
HAZARD:
Flammable
ethylene/isobutane
vapors in a 10” line
5
/
4
9
DuPont LaPorte
..\..\..\Videos\CSB Videos\LaPorte_DuPont_2014\EMBARGOED
Animation DuPont La Porte.mov
ARMC 3
Overview of PSM
:عرض وإعداد
سعيد محمد طه خليفة
Said Mohamed Khalifa, CSP
(Certified Safety Professional)
HSE and Loss Prevention Consultant
2018
ARMC 1
Overview of PSM
ARMC 2
Overview of PSM
Hazards
An inherent physical or chemical
characteristic that has the potential for
causing harm to people, the environment, or
property1
Hazards are intrinsic to a material, or its
conditions of use.
Examples
◦ Hydrogen sulfide – toxic by inhalation
◦ Gasoline – flammable
◦ Moving machinery – kinetic energy, pinch points
6
1 /
AICHE Center for Chemical Process Safety
4
1/29/2018 An Overview of PSM 9
Hazard Management:
The World as It Was Before
Good people
ARMC 3
Overview of PSM
ARMC 4
Overview of PSM
PSM at Glance
(example)
ARMC 5
Overview of PSM
The problem:
Pilot studies
indicate that
higher yields can
be obtained by
maintaining higher
temperatures in a
reaction vessel.
Example (contd.)
A change in operating temperature must be
approved by all technical and support functions
(MOC).
The impact of this change is assessed through
revision of the process hazard analysis (PHA),
which results in a recommendation to modify
the pressure relief system.
The modifications in temperature and pressure
relief system mandate new steps for process
operators (Operating Procedures),
Operators require training and verification in
the new procedures (Training).
1/29/2018 An Overview of PSM 13
ARMC 6
Overview of PSM
Example (contd.)
The modifications to the pressure relief
system are made by the supplier
(Contractor Safety) and require that a
portion of the process be shut down for this
work.
The work includes a brazing operation
requiring a Hot Work Permit (Nonroutine
Work Authorization).
Potential impacts on the process require a
review of emergency response plans
(Emergency Planning)
1/29/2018 An Overview of PSM 14
Example (contd.)
The new pressure relief system must be
inspected and tested (Mechanical
Integrity)
and all factors for safe operation must be
reviewed (Pre-startup Safety Review [PSR])
before that portion of the process is
brought back on line.
The piping and instrumentation diagrams
(P&IDs) and other engineering drawings
must be revised to show the as-modified
configuration of the system (PSI).
1/29/2018 An Overview of PSM 15
ARMC 7
Overview of PSM
Example (contd.)
The rationale and information about the
changes must be available for review by
employees and their representatives
(Employee Involvement).
Using this information, the PHA is updated
to account for potential hazards associated
with the new equipment.
Also, inspection and maintenance
procedures and training must be updated
(Mechanical Integrity, Operating Procedures,
Training).
ARMC 8
Overview of PSM
PHA Requirements
Use one or more established methodologies
appropriate to the complexity of the process,
ARMC 9
Overview of PSM
What-If
Checklist
What-If/Checklist
Hazard and Operability Study (HAZOP)
Failure Mode and Effects Analysis (FMEA)
Fault Tree Analysis
Event Tree Analysis
An appropriate equivalent methodology
ARMC 10
Overview of PSM
Summary
Despite the aforementioned issues with PHA:
ARMC 11
Overview of PSM
2
1/29/2018 An Overview of PSM 5
ARMC 12
Hazard Perception 1/29/2018
Definitions:
• Hazard.;
• Risk;
• Hazard identification;
• Risk assessment;
• Hazard analysis,
1/29/2018 HazPerception_PHA 2
ARMC 1
Hazard Perception 1/29/2018
1/29/2018 HazPerception_PHA 3
1/29/2018 HazPerception_PHA 4
ARMC 2
Hazard Perception 1/29/2018
Risk
• Risk: the chance or probability that a person
will be harmed or experience an adverse
effect if exposed to a hazard. Factors that
influence the degree of risk are as follows.
– How frequent the person is exposed to the
hazard
– How the person is exposed (via skin contact,
inhalation, etc)
– How severe are the effects due to the exposure
1/29/2018 HazPerception_PHA 5
1/29/2018 HazPerception_PHA 6
ARMC 3
Hazard Perception 1/29/2018
1/29/2018 HazPerception_PHA 7
ARMC 4
Hazard Perception 1/29/2018
ARMC 5
Hazard Perception 1/29/2018
OVERALL PROCEDURE
FOR HAZARD ANALYSIS
1/29/2018 HazPerception_PHA 11
P lanning
P e rmission
C ommissioning
1/29/2018 HazPerception_PHA 12
ARMC 6
Hazard Perception 1/29/2018
1/29/2018 HazPerception_PHA 13
1/29/2018 HazPerception_PHA 14
ARMC 7
Hazard Perception 1/29/2018
1/29/2018 HazPerception_PHA 15
Design Check List Used for audit of new design, or within design
process itself. (Detailed design stage).
Hazard and Operability For identifying failure modes that could occur
Study/Failure Modes and and might have undesirable consequences.
Effects Analysis (Detailed design stage).
ARMC 8
Hazard Perception 1/29/2018
ARMC 9
Hazard Perception 1/29/2018
ARMC 10
Hazard Perception 1/29/2018
END OF INTRODUCTION
QUESTIONS?
ARMC 11
Introduction to HAZOP 1/29/2018
INTRODUCTION TO
HAZOP
Presented by:
Said M. Khalifa
Certified Safety Professional, CSP (since 1997)
HSE and Loss Prevention Consultant
2018
DEFINITION OF HAZOP
• A procedure used to review design and
operations of hazardous process facilities.
ARMC 1
Introduction to HAZOP 1/29/2018
SNAP SHOT OF A
HAZOP
ARMC 2
Introduction to HAZOP 1/29/2018
Before
After
ARMC 3
Introduction to HAZOP 1/29/2018
ARMC 4
Introduction to HAZOP 1/29/2018
ARMC 5
Introduction to HAZOP 1/29/2018
• Simple' to understand
• Legally Enforced ;
• Apply to all.
ARMC 6
Introduction to HAZOP 1/29/2018
ARMC 7
Introduction to HAZOP 1/29/2018
ARMC 8
Introduction to HAZOP 1/29/2018
HAZOP
ARMC 9
The need for a HAZOP 1/29/2018
ARMC 1
The need for a HAZOP 1/29/2018
What is Cyclohexane:
• Trade name: Benzene hexahydride, Hexahydrobenzene,
Hexamethylene, Hexanaphthene.
• Formula: C6H12
• Physical Description: Colorless liquid with a
sweet, chloroform-like odor.
• FP: 0°F (- 17 C) BP: 177°F (80 C); LEL: 1.3%;
• Class IB Flammable Liquid: Fl.P. below 73°F and
BP at or above 100°F.
• Incompatibilities & Reactivity: Oxidizers
ARMC 2
The need for a HAZOP 1/29/2018
What is caprolactam :
• Synonyms & Trade Names: Aminocaproic-lactam, epsilon-
Caprolactam, Hexahydro-2H-azepin-2-one, 2-
Oxohexamethyleneimine.
• Formula: C2H11NO.
• Physical Description: White, crystalline solid or flakes
with an unpleasant odor.
• Combustible Solid.
• Fl.P: 282°F; LEL: 1.4%, BP: 515°F;
• Incompatibilities & Reactivity: Strong oxidizers, (acetic
acid + dinitrogen trioxide)
ARMC 3
The need for a HAZOP 1/29/2018
ARMC 4
The need for a HAZOP 1/29/2018
ARMC 5
The need for a HAZOP 1/29/2018
ARMC 6
The need for a HAZOP 1/29/2018
ARMC 7
The need for a HAZOP 1/29/2018
ARMC 8
The need for a HAZOP 1/29/2018
ARMC 9
The need for a HAZOP 1/29/2018
The Explosion:
• The Court of Enquiry attributed the escape of
the cyclohexane to the collapse of the
temporary bypass pipe.
• The reactors contained a large inventory of
cyclohexane, 50 tons escaped, although the
extensive damage which was caused could
have been caused by the deflagration of 10
to 20 tons of cyc1ohexane.
ARMC 10
The need for a HAZOP 1/29/2018
The Explosion:
• Because the cyclohexane was above its
boiling point at atmospheric pressure, a
proportion of the liquid. would have flashed
off as the pressure was reduced to
atmospheric.
• 1/8 of the liquid was flashed over to vapor.
However, the remaining liquid sprayed over.
• Hence a large gas cloud would have formed,
lead to UCVE.
The Explosion:
• Another assumption was: “the Court could
find no specific reason for the failure of the
bypass pipe, and it has been suggested
subsequently that a sudden pressure surge
caused the pipe to fail. No.4 reactor was
fitted with a stirrer and some water would
have been left in the base of the reactor after
the shutdown”.
ARMC 11
The need for a HAZOP 1/29/2018
The Explosion:
• As the reactor contents were heated during
start-up, the temperature rose until boiling at
the hydrocarbon-water interface could have
taken place. The two phases would mix; there
would be a sudden evolution of vapour and a
pressure surge strong enough to rupture the
bypass pipe.
• This is only one of a number of possible reasons
for the explosion, but is one which makes sense
in terms of the known behaviour of the
substances in the process system.
ARMC 12
The need for a HAZOP 1/29/2018
ARMC 13
The need for a HAZOP 1/29/2018
ARMC 14
HAZOP Methodology 1/29/2018
Definition of a HAZOP
ARMC 1
HAZOP Methodology 1/29/2018
ARMC 2
HAZOP Methodology 1/29/2018
ARMC 3
HAZOP Methodology 1/29/2018
HAZOP DEFINITIONS
ARMC 4
HAZOP Methodology 1/29/2018
HAZOP Definitions
HAZOP Definitions
• Design intent: designer’s desired, or specified range
of behaviour for elements and characteristics
• Element: constituent of a part which serves to
identify the part’s essential features. The choice of
elements may depend upon the particular
application. (the choice is explained in the next slide)
• Guide word: word or phrase which expresses and
defines a specific type of deviation from an
element’s design intent.
ARMC 5
HAZOP Methodology 1/29/2018
ARMC 6
HAZOP Methodology 1/29/2018
Definition (6.1-3)
• Define scope and objectives
• Define responsibility
• Select team
Preparation (6.4)
• Plan the study
• Collect data
• Agree style of recording (6.6.2)
• Estimate the time
• Arrange a schedule
Examination (6.5)
• Divide system into parts
• Select a part and define design intent
• Identify deviation by using guide words on each element
• Identify consequences and causes
• Identify whether a significant problem exists
• Identify protection, detection, and indicating mechanisms
• Identify possible remedial/mitigating measures (optional)
• Agree actions
Repeat for each element and then each part of the system
ARMC 7
HAZOP Methodology 1/29/2018
HAZOP OBJECTIVES
• Identify all deviations, causes and problems
associated with deviations.
• Decide action to control hazard or operability
problem .
• If decision cannot be made immediately, decide
on what information or action is required.
• Ensure that actions decided upon are followed
through .
HAZOP Team
• Leader
• Secretary
• Team members
• '
– Design engineer(s)
– Process engineer(s)
– Operations representative
– Safety specialist
– Instrument engineer·
– Electrical engineer
ARMC 8
HAZOP Methodology 1/29/2018
ARMC 9
HAZOP Methodology 1/29/2018
HAZOP Team
Chairman can also be secretary and
Safety Dept. Representative
Contractor(s) and the Client should
be involved
• Should have authority to decide
when and when, avoid deputies
ARMC 10
HAZOP Methodology 1/29/2018
ARMC 11
HAZOP Methodology 1/29/2018
Relating to order or
BEFORE
sequence
Relating to order or
AFTER
sequence
ARMC 12
HAZOP Methodology 1/29/2018
PHA/HAZOP
ADNOC PRACTICE
CP-24
ARMC 13
HAZOP Methodology 1/29/2018
MORE LEVEL Outlet isolated or blocked - inflow greater than outflow - control
failure - faulty level measurement - gravity liquid balancing.
LESS LEVEL Inlet flow stops - leak - outflow greater than inflow - control
failure - faulty level measurement - draining of vessel.
LESS MIXING Agitator set at wrong speed - drive stops - agitator blade drops
off.
Reverse REACTION Wrong reactant mix - high temperature - incompatible
chemical.
LESS REACTION Wrong reactant mix - low temperature - insufficient catalyst -
channeling.
HAZOP Deviations: Vessels and Tanks Only, apply once to the entire unit
Grounding arrangements - insulated vessels/equipment - low conductance
fluids - splash filling of vessels - insulated strainers and valve components -
IGNITION
dust generation - powder handling equipment - electrical classification -
SUPPRESSION
flame arresters - hot work - hot surfaces - auto-ignition - pyrophoric
materials.
Toxic properties of process materials - fire and gas detection
system/alarms - emergency shut-down arrangements - fire fighting
response time - emergency and major emergency training - contingency
plans - T.L.V.'s of process materials and methods of detection - noise levels
SAFETY
- security arrangements - knowledge of hazards of process materials - first
aid/medical resources -effluent disposal - hazards created by others
(adjacent storage areas/process plant etc.) - testing of emergency
equipment - compliance with local/national regulations.
Installed/non-installed spare equipment - availability of spares - modified
SPARE EQUIPMENT specifications - storage of spares - catalogue of spares - test running of
spare equipment.
The distance between various units for safety and fire exposure - "General
FACILITY LAYOUT Recommendations for Spacing" by Oil Insurance Association or Industrial
Risk Insurers - API - NFPA, OSHA 1910.119.
Control room layout - alarms - valve access and location - human error -
HUMAN FACTORS
OSHA 1910.119.
ARMC 14
HAZOP Methodology 1/29/2018
ARMC 15
HAZOP Methodology 1/29/2018
Normal ops. X
Start up X
Shutdown X
1/29/2018 HAZOP Mthedology 31
ARMC 16
Start HAZOP Process Map
(Life-cycle based)
Updated 201510
Define Objectives of the Study (B&W)
Select an element
(and characteristic if any)
Investigate causes,
Move on to the next Is deviation consequences and
NO YES
deviation/ Guideword credibel? protection or indication, and
document NO
Consider other
Is the cost of the change jutified? NO changes or agree to
accept the HAZARD
Yes
Have all
Have all PARTS All Elements & Parts are
NO
examined
NO ELEMENTS been
examined? examined?
YES
How to conduct
HAZOP Study
1/29/201
How to conduct HAZOP study 1
8
HAZOP OBJECTIVES
2
How to conduct HAZOP study 1/29/2018
ARMC 1
How to conduct HAZOP 1/29/2018
1/29/201
How to conduct HAZOP study 3
8
1/29/201
How to conduct HAZOP study 4
8
ARMC 2
How to conduct HAZOP 1/29/2018
1/29/201
How to conduct HAZOP study 5
8
1/29/201
How to conduct HAZOP study 6
8
ARMC 3
How to conduct HAZOP 1/29/2018
Team Functions
Team Leader
The team leader must take the final
responsibility for ensuring that all the
tasks involved in planning, running,
recording, and implementing the study are
carried out during the study his main task
is to ensure that the team works together
towards a common goal.
1/29/201
How to conduct HAZOP study 7
8
Team Functions
Secretary
The secretary should take notes of the study
and record recommendations in enough detail
for them to be understood. He should refrain
from taking part in the discussions.
Members
The individual members should use their
experience, training and judgment to
identify any issue which should be
discussed by the team as a whole, and put
it forward. They should then assist the
team in resolving issues by suggesting
changes that may overcome the problem
they should be prepared to assist the team
in arriving at a consensus.
1/29/201
How to conduct HAZOP study 8
8
ARMC 4
How to conduct HAZOP 1/29/2018
1/29/201
How to conduct HAZOP study 9
8
1/29/201
How to conduct HAZOP study 10
8
ARMC 5
How to conduct HAZOP 1/29/2018
1/29/201
How to conduct HAZOP study 12
8
ARMC 6
How to conduct HAZOP 1/29/2018
1/29/201
How to conduct HAZOP study 13
8
1/29/201
How to conduct HAZOP study 14
8
ARMC 7
Start HAZOP Process Map
(Life-cycle based)
Updated 201510
Define Objectives of the Study (B&W)
Select an element
(and characteristic if any)
Investigate causes,
Move on to the next Is deviation consequences and
NO YES
deviation/ Guideword credibel? protection or indication, and
document NO
Consider other
Is the cost of the change jutified? NO changes or agree to
accept the HAZARD
Yes
Have all
Have all PARTS All Elements & Parts are
NO NO ELEMENTS been
examined? examined
examined?
YES
Source: Destination
Design Intent:
Material: Activity/ Process
Elements
Characteristics Materials Other Elements
Corrosion/ Erosion
Knowledge_based
Pressure Relieving
Instrumentations
Spare Equipment
Control System
Contamination
Service Failure
Maintenance
Fire & Safety
Composition
Suppression
Operation
Pressure
Abnormal
Sampling
Checklist
Systems
Systems
Ignition
Change
Temp.
Level
Flow
x x x x x x x x x x x x x x
No, None x
Logical Guide Words
More x x x x
Less x x x x
Reverse x
As well As x x
As Part of x x
Early x x x
Clock Guidewords
Late x x x
Clock guide words
Before x x x
After x x x
Ref. No. Guideword/ Deviation Possible Cause Possible Consequences Existing Safeguards Comment Recommendation/ Action/ Discussion Action By
Recommendations Implementation
1/29/2018
Reference : System Reliability Theory (2nd ed), Wiley, 2004
Reporting Hazop 2
ARMC 1
Reporting HAZOP Study 1/29/2018
1/29/2018
Reference : System Reliability Theory (2nd ed), Wiley, 2004
Reporting Hazop 3
ARMC 2
Reporting HAZOP Study 1/29/2018
risk-coding matrix
1/29/2018 Reporting
Reference : System Hazop
Reliability Theory (2nd ed), Wiley, 2004 6
ARMC 3
Reporting HAZOP Study 1/29/2018
ARMC 4
Reporting HAZOP Study 1/29/2018
HAZOP Study
ARMC 5
Cairo Oil Refining Company
HAZOP Study
001-CDU4-01-003 Less Flow 2.1 install PDI after and before filters
001-CDU4-01-004 Reverse flow 3.1 Install NRV downstream of 1/2" injection line.
Crude oil filters 4.1 Install closed drain system to avoid release of
001-CDU4-01-005 Sampling volatile vapors and decrease load on the API
separator.
5.1 Revise the operating procedure to drain the
001-CDU4-01-006 More Pressure
standby filter and keep the drain valve open.
6.1 Extend the gas detection system to cover this
001-CDU4-01-007 Less pressure
area.
Composition
001-CDU4-01-008
change
8.1 Fabricate drip bans underneath filter under
001-CDU4-01-009 Maintenance
maintenance to avoid pollution
Final decision
• Management should evaluate this
recommended action on a cost versus risk-
reduction basis and either take action or
accept the risk.
• ALARP (As Low As reasonable
Practices) principals
ARMC 6
Reporting HAZOP Study 1/29/2018
Recommended implementation
period
• Guidelines are suggested for implementation
of hazard analysis recommendations
according to
– High priority action (resolved within 4 months)
– Medium Priority action (resolved within 4-6
months
– Lower priority action (resolved following medium
priority)
ARMC 7
Reporting HAZOP Study 1/29/2018
tracking document
• The resolution of each recommendation
should be recording in a tracking document
• All recommended actions should be entered
into a computerized information management
system so that management can monitor the
progress of outstanding corrective action
requests.
• Management to assure progress .
Review meetings
• Review meetings should be arranged to monitor
completion of agreed actions that have been
recorded. The review meeting should involve the
whole HAZOP team. A summary of actions
should be noted and classified as:
– Action is complete
– Action is in progress
– Action is incomplete, awaiting further information
ARMC 8
Reporting HAZOP Study 1/29/2018
Conclusions
• HAZOP Results
• Advantages
• Success factors
• Pitfalls and objections
1/29/2018
Reference : System Reliability Theory (2nd ed), Wiley, 2004
Reporting Hazop 17
HAZOP Results
• Improvement of system or operations
– Reduced risk and better contingency
– More efficient operations
• Improvement of procedures
– Logical order
– Completeness
• General awareness among involved parties
• Team building
ARMC 9
Reporting HAZOP Study 1/29/2018
Advantages
• Systematic examination
• Multidisciplinary study
• Utilizes operational experience
• Covers safety as well as operational aspects
• Solutions to the problems identified may be indicated
• Considers operational procedures
• Covers human errors
• Study led by independent person
• Results are recorded
1/29/2018
Reference : System Reliability Theory (2nd ed), Wiley, 2004
Reporting Hazop 19
Success factors
• Accuracy of drawings and data used as a basis for the
study
– the accuracy of the information used
– the quality of the design
• Experience and skills of the HAZOP team leader
• Technical skills and insights of the team
• Ability of the team to use the HAZOP approach as an
aid to identify deviations, causes, and consequences
• Ability of the team to maintain a sense of proportion,
especially when assessing the severity of the potential
consequences.
1/29/2018
Reference : System Reliability Theory (2nd ed), Wiley, 2004
Reporting Hazop 20
ARMC 10
Reporting HAZOP Study 1/29/2018
ARMC 11
2/8/2018
WORKED EXAMPLE
Oil Vaporizer
what if/ checklist
Presented by:
Said M. Khalifa
Certified Safety Professional, CSP (since 1997)
HSE and Loss Prevention Consultant
2017
Interlock shuts
I-5
TSH
FAL
Vaporized oil
Heating coil
TE FC
FE
FCV
Interlock shuts Liquid oil
I-4 Firebox
Burners
PSHH
Pilot Main
valve valve TC
Natural
PRV PV TCV
gas
IEC 456/01
1
2/8/2018
2
2/8/2018
3
2/8/2018
Guide
No. Element Deviation Possible causes Consequences Safeguards Comments Actions required Action by
word
Consider low flow element
Supply failure Vaporizer coil Low flow alarm FAL Safeguard FE to close main burner
depends on quick valve
operator response LB
Flow control valve
overheats and may fail High TCV
PCV closed
1 No Oil flow No oil flow temperature trip TSH
Plugging of coil Oil in vaporizer will boil: Low flow alarm FAL Check whether these
safeguards are adequate
Possible overheating and
Blockage down- High and the ease with which the NE
coking of
stream of vaporizer coil could be cleaned
heating coil temperature trip TSH
Investigate effect of liquid
Unvaporized liquid
oil on the process
Consider interlocking the
Flame out in the oil fed to the process furnace flame out signal
2 No Heat No heat None DH
furnace with closure of FCV
4
FTA/ ETA Analysis 2/8/2018
ARMC 1
FTA/ ETA Analysis 2/8/2018
ARMC 2
FTA/ ETA Analysis 2/8/2018
ARMC 3
FTA/ ETA Analysis 2/8/2018
ARMC 4
FTA/ ETA Analysis 2/8/2018
ARMC 5
FTA/ ETA Analysis 2/8/2018
Consider the following block diagram. Let I/P and O/P be the
input And output terminals. There are two sub-systems A and B
that are connected in series.
X1 X3
INPUT OUTPUT
X2 X4
For this the fault tree analysis diagram shown in next slide
OR
intermediate event
F (A) F (B)
AND AND
Basic event
F( X 1) F( X 2) F( X 3) F( X 4)
ARMC 6
FTA/ ETA Analysis 2/8/2018
FTA PROCEDURE
Procedure
Define Top Event:
• Use PHA, P&ID, Process description etc., to define the top event.
• If its too broad, overly large FTA will result. E.g. Fire in process.
• If its too narrow, the exercise will be costly. E.g. Leak in the valve.
ARMC 7
FTA/ ETA Analysis 2/8/2018
Procedure
•Define overall structure;
•Determine the intermediate events &
combination of failure that will lead to the top
event.
•Arrange them accordingly using logical relationship
Procedure, contd.
Solve the Fault Tree:
• Assign probabilities of failure to the lowest
level event in each branch of the tree.
• From this data the intermediate event
frequency and the top level event frequency
can be determined using Boolean Algebra
and Minimal Cut Set methods.
ARMC 8
FTA/ ETA Analysis 2/8/2018
Procedure
Perform corrections and make decisions:
Example
ARMC 9
FTA/ ETA Analysis 2/8/2018
Moto fails
to start
OR NO EMF applied to the motor
when EMF
applied
Wire from
battery to
OR No EMF from the battery
motor fails
open
Battery faild
to produce OR NO EMF to Battery
EMF
Wire from
switch to
OR NO EMF across switch
Battery fails
open
ARMC 10
FTA/ ETA Analysis 2/8/2018
Advantages Of FTA
•Deals well with parallel, redundant or alternative fault
paths.
Disadvantages Of FTA
• Requires a separate fault tree for each top event and
makes it difficult to analyze complex systems.
ARMC 11
FTA/ ETA Analysis 2/8/2018
Applications
• Used in the field of safety engineering and
Reliability engineering to determine the
probability of a safety accident or a particular
system level failure.
• Aerospace Engineering.
ARMC 12
FTA/ ETA Analysis 2/8/2018
About ETA
• The Event Tree Analysis (ETA) is an inductive logic technique
to model a system with respect to dependability and risk
related measures as well as to identify and assess the
frequency of the various possible outcomes of a given
initiating event.
• According to the IEC 60050(191) the dependability of a system
is defined as the ability to meet success criteria, under given
conditions of use and maintenance.
• The core elements of dependability are the reliability,
availability and maintainability of the item considered.
• Starting from an initiating event the ETA deals with the
question "What happens if..." and thus constructs a tree of
the various possible outcomes.
ARMC 13
FTA/ ETA Analysis 2/8/2018
Cooling Coils
Reactor Feed
Cooling
Water In
Reactor
TIC
Temperature
Controller
TIA
Alarm Thermocouple
at
T > TA
High Temperature Alarm
Figure depicts Reactor with high temperature alarm and temperature controller
ARMC 14
FTA/ ETA Analysis 2/8/2018
• process upset
[Example]
ARMC 15
FTA/ ETA Analysis 2/8/2018
INITIATING EVENT:
Loss of cooling water
to oxidation reactor
INITIATING EVENT:
Loss of cooling water
to oxidation reactor
Succes
s
Failure
REPRESENTATION OF THE
8/11/2017 FIRST
FTA/ ETA Analysis SAFETY FUNCTION 41
ARMC 16
FTA/ ETA Analysis 2/8/2018
INITIATING EVENT:
Loss of cooling water
to oxidation reactor
Succes
s
If the safety function does not affect the course of the
accident, the accident path proceeds with no branch pt
Failure to the next safety function.
8/11/2017 FTA/ ETA Analysis 42
REPRESENTATION OF THE SECOND SAFETY FUNCTION
INITIATING EVENT:
Loss of cooling water
to oxidation reactor
Succes
s
Completed !
Failure
8/11/2017
COMPLETED EVENT TREE
FTA/ ETA Analysis 43
ARMC 17
FTA/ ETA Analysis 2/8/2018
B C D
A Safe condition,
return to normal
operation
AC Safe condition,
process shutdown
INITIATING EVENT:
ACD Unsafe condition,
Loss of cooling water runaway reaction,
to oxidation reactor operator aware of
A problem
AB
Unstable condition,
process shutdown
ABD Unsafe condition,
runaway reaction,
Succes operator unaware
s of problem
Failure
8/11/2017
ACCIDENT SEQUENCES
FTA/ ETA Analysis 44
ADVANTAGES
ARMC 18
FTA/ ETA Analysis 2/8/2018
DISADVANTAGES
Open Discussion
End of Session
ARMC 19
FMEA 2/8/2018
Failure Modes
and
Effects Analysis, FMEA
2/8/2018 1
What Is FMEA?
FMEA is a failure mode and effects analysis tool that is
used in various industries to:
• Identify failures,
• Evaluate the effects of the failures, and
• Prioritize the failures according to severity of effects.
ARMC 1
FMEA 2/8/2018
ARMC 2
FMEA 2/8/2018
It is performed on
• Mechanical equipment such as pumps,
compressors, etc. where there is a history of
component failures.
• Systems for which there are few drawings
or details but where individual components
are readily identifiable.
• Reliability studies or for input into
quantitative risk assessment studies.
ARMC 3
FMEA 2/8/2018
Methodology
1. Collect pertinent information
2. Establish the purpose, scope, depth of the study
3. Break the system into logical and manageable items
by function, or area location.
4. Identify all potential failure modes for each item.
5. Determine the causes of each failure mode.
6. Identify and list the current controls.
7. Assign a rating for severity, occurrence and detection
for each failure.
8. Determine appropriate corrective actions.
9. Carry out the recommended actions.
Rank Description
ARMC 4
FMEA 2/8/2018
Rank Description
ARMC 5
FMEA 2/8/2018
Very High Significant downtime and major financial impacts (Process). Product
Severity 8 inoperable but safe. User very dissatisfied (Product).
Extreme Failure resulting in hazardous effects highly probable. Safety and
Severity 9 regulatory concerns (Process and Product).
ARMC 6
FMEA 2/8/2018
ARMC 7
FMEA 2/8/2018
Benefits of FMEA
• Better company image and competitiveness
• Compliance with regulations, standards, and specifications
• Continuous improvement of product quality, reliability, and safety
• Defining corrective action.
• Documentation of the reasons for changes
• Improved reliability, productivity, quality, safety, and cost efficiency
• Increased liability prevention
• Increasing customer satisfaction
• Recognition and evaluation of potential failures and their effects
• Reduction of downtime
• Reduction of manufacturing process deviations
• Selection of alternative materials, parts, devices, components and tasks.
• Selection of optimal system design
ARMC 8
FMEA 2/8/2018
ARMC 9
2/8/2018
What is QRA?
Quantitative Risk Assessment, QRA.
After the hazard analysis, we might need to quantify the high risk
in mathematical modeling in order to assess the harm on people,
asset , reputation of the organization as well as the environment.
It needs highly experienced professional with good knowledge of
process and the use of mathematical modeling software.
It is highly expensive and time-consuming process.
Used basically by the insurance agents and is required by legislative
authorities in early phase of the project basic design phase.
1
2/8/2018
What is LPG?
Liquefied Petroleum Gas, LPG.
Mixture of propane and butane gases.
Used in cooking and heating.
Stored as liquefied gas under normal temperature.
Vapor pressure is a function of the ambient temperature.
Domestic cylinder has a capacity of 12 Kg.
2
Failure Case Definition Tree
Flammable Toxic
Nature of Hazard
Release case
Event tree Flammable Gas Flammable Liquid Toxic Gas Event Toxic Liquid
or model Bleve Model
Event Tree Event Tree Tree Event Tree
Failure Liquid Event Tree
Is the
release Is there immediate Does pool
Does the pool ignite?
instantaneo ignition? form?
us?
Fireball
Yes Assess fire damage
Calculate spread
and Vaporisation
Yes
Assess pollution
No use gas event trees
No to model gas
behavior
Jet flame
Yes Assess fire damage
Estimate Duration
No Calculate release rate Pool fire
Assess fire damage
Calculate spread Yes
and Vaporisation
Yes
Assess pollution
No use gas event trees
to model gas
No
behavior
Adiabatic Expanion
4
2/8/2018
Fireball/ BLEVE
1
1
Radiation (KW/m2)
0.8 0.75
0.6
0.5
0.4
0.2
0.1
0 Distance (m)
0 20 40 60 80 100 120 140 160
5
2/8/2018
The following have given as the heat flux levels that might be
considered critical in any hazard analysis:
6
2/8/2018
0.6
0.5
Major glass damage
0.4
0.2
0.1
10% glass damage
0
0 20 40 60 80 100 120 140 160