የኢትዮጵያ ኮንስትራክሽን ሥራዎች ኮርፖሬሽን OF/ECWC/006
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
WEATHER FINE
Concrete work
Rebar work
Form work
gypsum plastering
cement screed
RHS 40x40x3mm
RHS 80x80x4mm
aggregate
leader
documentation
the schedule
Repeated rework
Attitude problems
Shortage of cement
rebar,
PMBK REPORTS
1. QUALITY
Qualities of activities performed at site are checked by laboratory and field test
site work inspection
site work inspection
site material handling inspection were held
2. Stake holders
All stake holders in our project perform their duty as per their job description and
responsibility. their communication is also sound and effective .
3. Communication
Ways of communication in our project were held in both formal and informalways.
4. Procurement
The purchasing process in our site is using collection of Performa. And the selection of
suppliers was held by purchasing committee. but this processes is mostly time
consuming and expensive .
6.Time management
The project is facing time over run due to late dsigns, shortage of cement,
shortage of rebar, ready mix concrete. The project was supposed to be end
on 7/4/2022 but its completion percentage is 64 %
Earned value Planned value Schedule Schedule Performance Index (SPI)
(EV) (PV) variance (SV)
553560799.45 670549632.78 =EV-PV EV/PV
-116,988,833.33 0.83
Behind Less work completed
schedule
Note: - from the above table we can conclude that the project is well with respect to
cost
The project has poor material handling due to this reason its exposed to high wastages
of materials and corrosion of rebar’s and RHS .I tried to talk with supporting staffs but
they are not taking measurement .
Shortage of cement
Late purchasing problems
Low labor productivity
Low performance of sub-contractors