Section 2-Earthworks

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 26

Ref. Title Page No.

2.1 Clearing and Grubbing 2-1


2.1.1 Description 2-1
2.1.2 Construction Requirements 2-1
2.1.3 Method of Measurement 2-1
2.1.4 Basis of Payment 2-1
2.1.5 Items in the Bill of Quantities 2-1

2.2 Removal of Structures and


Obstructions 2-1
2.2.1 Description 2-1
2.2.2 Construction Requirements 2-1
2.2.2.1 General 2-1
2.2.2.2 Removal of Bridges, Culverts and Ditches 2-2
2.2.2.3 Removal of Pipes 2-2
2.2.2.4 Removal of Walls, Mortared and Loose Riprap,
Gabions, Rocks and Boulders 2-2
2.2.2.5 Removal of Fences and Gates 2-2
2.2.2.6 Removal of Wells, Shafts and Falajs 2-2
2.2.2.7 Removal of Utilities 2-2
2.2.2.8 Removal of Existing Pavement 2-2
2.2.2.9 Removal of Existing Road Furniture 2-3
2.2.3 Method of Measurement 2-3
2.2.4 Basis of Payment 2-3
2.2.5 Items in the Bill of Quantities 2-3

2.3 Roadway Excavation 2-3


2.3.1 Description 2-3
2.3.2 Classification of Roadway Excavation 2-3
2.3.3 Construction Requirements 2-4
2.3.3.1 Utilization of Excavated Materials 2-4
2.3.3.2 Drainage of Excavation Areas 2-4
2.3.3.3 Obliteration of Disused Roadways 2-4
2.3.3.4 Rock Blasting 2-4
2.3.3.5 Excavation of Unsuitable Material 2-5
2.3.3.6 Slopes, Subgrade and Ditches 2-5
2.3.3.7 Unstable Materials outside Right-of-Way 2-5
2.3.3.8 Disposal of Unsuitable and Surplus Material 2-5
2.3.4 Method of Measurement 2-5
2.3.5 Basis of Payment 2-6
2.3.6 Items in the Bill of Quantities 2-6
Ref. Title Page No. Ref. Title Page No.
2.4 Borrow Materials 2-6 2.6.5 Basis of Payment 2-14
2.6.6 Items in the Bill of Quantities 2-14
2.4.1 Description 2-6
2.4.2 Location of Borrow Pits 2-6 2.7 Excavation and Backfilling for
2.4.3 Borrow Material 2-6 Structures 2-14
2.4.4 Method of Measurement 2-7
2.7.1 Description 2-14
2.4.5 Basis of Payment 2-7
2.7.2 Excavation 2-14
2.4.6 Items in the Bill of Quantities 2-7
2.7.2.1 General 2-14
2.5 Embankments 2-7 2.7.2.2 Temporary Support System 2-15
2.7.2.3 Excavation for Major Structures and Bridges 2-15
2.5.1 Description 2-7
2.5.2 Materials 2-7
2.5.3 Construction Requirements 2-8 2.7.2.4 Excavation for Box Culverts, Pipe Culverts and
2.5.3.1 General 2-8 Miscellaneous Structures 2-15
2.5.3.2 Trial Embankments Sections 2-9 2.7.3 Backfilling 2-16
2.5.3.3 Foundation Preparation 2-9 2.7.3.1 General 2-16
2.5.3.4 Embankment Construction 2-9 2.7.3.2 Backfilling for Box Culverts, Pipe Culverts, Bridge
2.5.4 Testing 2-10 and Building Foundations, Walls, Abutments and
2.5.4.1 General 2-10 Miscellaneous Structures 2-16
2.5.4.2 Standards of Compaction for Soil and Granular 2.7.4 Method of Measurement 2-17
Materials 2-10 2.7.5 Basis of Payment 2-17
2.5.4.3 Degree of Compaction for Rock Fill and Rock-Soil 2.7.6 Items in the Bill of Quantities 2-18
Materials 2-10
2.8 EARTHWORK FOR PIPE TRENCHES
2.5.4.4 Monitoring Settlement of Rockfill 2-11
2-18
2.5.5 Method of Measurement 2-11
2.5.6 Basis of Payment 2-11 2.8.1 Description 2-18
2.5.7 Items in the Bill of Quantities 2-11 2.8.2 Materials 2-18
2.8.2.1 Backfill Material 2-18
2.6 Sub-grade Construction 2-11
2.8.3 Construction Requirements 2-18
2.6.1 Description 2-11 2.8.3.1 Excavation for Pipe Trenches 2-18
2.6.2 Materials 2-12 2.8.3.2 Backfilling 2-19
2.6.3 Construction Requirements 2-12 2.8.3.3 Restoration of Surfaces 2-19
2.6.3.1 Subgrade in Cut 2-12 2.8.4 Method of Measurement 2-19
2.6.3.2 Subgrade in Embankment 2-12 2.8.5 Basis of Payment 2-19
2.6.3.3 Surface Tolerances 2-13 2.8.6 Items in the Bill of Quantities 2-20
2.6.3.4 Maintenance of Finished Subgrade 2-13
2.6.3.5 Drainage Blanket 2-13
2.6.3.6 Subgrade Construction on Sabkha and Gypsum
Rich Soils 2-13
2.6.3.7 Subgrade Construction on top of Dune Sand 2-13
2.6.4 Method of Measurement 2-13

2-4
2.1 Clearing and Grubbing 3 Clearing and grubbing for cut areas, easement areas and
borrow pits shall not to be paid separately but shall be included in the
2.1.1 Description Contractor’s rates.

1 This Sub-section describes removal and satisfactory disposal 2.1.4 Basis of Payment
of all vegetation, surface debris and scattered stones and rocks within
the limits of the actual fill width only. 1 The area of completed and accepted clearing and grubbing
work measured as provided for above, will be paid at the unit rates
2 Removal of structures and similar obstructions and removal of
stated in the Bill of Quantities, which rates shall be full
utilities are specified in Sub-section 2.2 - "Removal of Structures and
compensation for labor, equipment and other items necessary for
Obstructions".
completion of the work.

2.1.2 Construction Requirements 2 Removal of trees with trunk 300mm diameter or greater, when
measured 750mm above existing ground level, will be paid for by
1 The Contractor shall set out the approved construction limits the number removed as stated above. Removal of trees with trunk
and the Engineer will designate all trees, shrubs, plants, vegetation, less than 300mm diameter is deemed to be included in the rate for
etc and other items that are to remain within the right-of-way (ROW). clearing and grubbing.
The Contractor shall carefully preserve all such items from damage
3 Rates for all clearing and grubbing and tree removal shall
or defacement. Trees to be removed and delivered for replanting
include for filling holes and depressions with material as specified.
shall be carefully handled.
2 All surface objects, trees, stumps, roots, stones and rocks (up 2.1.5 Items in the Bill of Quantities
to 0.2 cu.m. or 500 kg individual size or weight), and other
protruding obstructions not designated to be retained shall be cleared i. Clearing and grubbing sq. m.
or grubbed to ground level. Non-perishable solid objects (such as ii. Removal and delivery or disposal of trees nr.
boulders, rocks, concrete blocks, etc.) which will be a minimum of
2m below the sub-grade or finished ground level may be left 2.2 Removal of Structures and
undisturbed at the Engineer’s discretion. If such non-perishable Obstructions
objects are encountered within 2m below the sub-grade or finished
ground level, they will be removed and considered as unsuitable
2.2.1 Description
material, paid under Unclassified Excavation.
3 Stump holes and other holes from which obstructions are 1 This Sub-section describes the removal, wholly or in part, and
removed within the limits of construction, shall be backfilled with satisfactory disposal of all buildings, fences, structures, abandoned
suitable material and compacted in accordance with Sub-section 2.5 - pipelines, and any other obstructions, as shown on the Drawings or
"Embankments". Small holes that are inaccessible to compaction / directed by the Engineer, which are not designated or permitted to
tamping equipment shall be filled and tamped manually using a steel remain, including salvaging of designated materials and backfilling
rod with a 10-15cm diameter steel disc attached to its end. the resulting trenches, holes and pits.

4 Perishable material shall be disposed of or burned under the 2 The Contractor shall examine the Site and record for himself
constant care of competent watchmen at such times and in such a all obstructions and utilities before the commencement of the Works.
manner that any vegetation or other items designated to remain in the
ROW, or other adjacent property, will not be jeopardized. Burning 2.2.2 Construction Requirements
shall be carried out in accordance with applicable laws and
2.2.2.1 General
ordinances.
5 Materials, stones, rocks, and debris which cannot be burned 1 The Contractor shall raze, remove and dispose of all buildings,
and perishable materials, shall be removed from the ROW and foundations, structures, fences and other obstructions, any portions
disposed of at dumping areas off the Site, approved by the of which are on the ROW, except utilities and items for which other
concerned authorities, provided permission of the respective property arrangements for removal have been made. All designated
owners has been obtained in writing to dump such materials on their salvageable material shall be removed, without causing unnecessary
land. The Contractor shall make all necessary arrangements with damage, and in sections or pieces which may be readily transported,
property owners for obtaining such written permission at his own and shall be stored by the Contractor at approved locations, for later
expense. use or possession of others.
2 Unusable perishable material shall be destroyed. Non-
2.1.3 Method of Measurement perishable material may be disposed of off the Site, provided
permission of the respective property owners has been obtained in
1 Clearing and grubbing is measured in square meters of the writing to dump such materials on their land.
cleared area within the limits described in Item 1 of Clause 2.1.1 Basements or cavities left by structure removal shall be filled to the
above and approved by the Engineer. level of the surrounding ground and, if within the prism of
2 Trees with a trunk diameter 300mm or more, when measured construction, shall be compacted to the type of compaction within
750mm above existing ground level are measured by the number the range for the adjacent roadway embankment as specified in Sub-
removed and delivered to the Employer or disposed of as directed by section 2.5 – ‘Embankments’.
the Engineer.

2-1
3 Salvaged pipe culverts and other re-usable materials shall be approved locations on Site. All salvageable material shall become
stored at accessible approved locations on Site and shall become the the property of the Employer. Wells shall be filled to the level of the
property of the Employer. surrounding ground and, if within the prism of construction, shall be
compacted after obtaining the Engineer's permission to the type of
2.2.2.2 Removal of Bridges, Culverts and Ditches compaction within the range designated.

1 Bridges, culverts and other drainage structures in locations 2.2.2.7 Removal of Utilities
traversed by traffic shall not be removed until arrangements, detours
and traffic management plans have been made by the Contractor and 1 The Contractor shall liaise with the Engineer and shall notify
approved by ROP to maintain the flow of traffic. all Utility Authorities and co-operate and coordinate with them in
respect of removals and relocations.
2 Substructures in watercourses shall be removed down to the
level of the natural stream bed. Those parts outside the stream shall 2 Unless shown otherwise on the Drawings, realignment or
be removed to 300 mm below natural ground surface. Where such relocation of active utilities will be to the approval of the respective
portions of existing structures lie wholly or in part within the limits authorities and such work shall be coordinated by the Contractor.
for a new structure, they shall be removed to the extent necessary to The Contractor shall perform the necessary coordination with the
accommodate construction of the proposed structure. relevant utility authorities ahead of time in order to avoid
unnecessary delay to the Works.
3 Steel bridges and timber bridges, designated to be salvaged
shall be dismantled without causing unnecessary damage. Steel 3 The removal of all disconnected or abandoned utilities within
members shall be match marked, unless this requirement is waived the ROW shall be performed by the Contractor as directed by the
by the Engineer. All salvaged material shall be stored as previously Engineer, unless the utility authorities indicate their intention to
specified for reuse or possession of others. carry out such removal and salvaging of materials, fittings, parts, etc.

4 Blasting or other operations necessary for removal of existing 4 The Contractor shall liaise with the Engineer and shall advise
structures or other obstructions, and which may damage new each affected utility authority in writing of his proposed construction
construction in the vicinity, shall be completed prior to commencing schedule and shall arrange for inspection, disconnection or
the new construction. Explosives shall be used only as permitted by interruption of services by the utility authorities as appropriate.
the appropriate security authorities and shall be approved by the 5 The Contractor shall be responsible for supporting and
Engineer. The Contractor shall observe the requirements of Section protecting realigned utilities and existing utilities that are to remain
1, Sub-section 1.9, Clause 1.9.2 for all blasting operations in place, for the duration of the Contract and shall provide all
5 The Contractor shall carry out a structural survey of all the necessary Temporary Works in this respect, all in compliance with
existing buildings and structures located within the blasting influence Section 1, Sub-section 1.8, Clause 1.8.3 and the requirements of the
distance. The survey shall include detailed photographic records for relevant utility owner. Any damage caused to utilities and
the adjacent buildings and structures before and after blasting, in attributable to the Contractor shall be repaired at his expense.
order to avoid later claims by public. 6 All excavation and backfill shall conform to the requirements
of Sub-sections 2.3 - ’Road Excavation‘, 2.5 –’Embankments’ and
2.2.2.3 Removal of Pipes Sub-section 2.7 - ’Excavation and Backfilling for Structures‘, as
1 All pipes unless otherwise directed shall be removed and appropriate.
precautions taken to avoid breaking or damaging the pipes. The
2.2.2.8 Removal of Existing Pavement
Contractor shall exercise utmost care during the removal of pipes so
as to avoid unnecessary damage. 1 The Contractor shall remove, wholly or in part, as shown on
the Drawings or directed by the Engineer, existing asphalt, paving
2.2.2.4 Removal of Walls, Mortared and Loose Riprap, Gabions, blocks and/or concrete pavement layers, and any granular or
Rocks and Boulders stabilized base courses, including disposal of debris and salvaging of
designated materials, and backfilling the resulting holes where and as
1 Masonry walls, mortared and loose riprap, gabions and
instructed by the Engineer.
accumulated stones, large rocks and boulders of individual size
greater than 0.2 cu.m. or greater than 500 kg in weight which lie 2 The Contractor shall examine the Site and record all
within the limits of the Works, shall be removed and disposed of as obstructions and utilities that may be affected by removal of existing
directed. pavements at the commencement of the Works.
3 The Contractor shall raze, remove and dispose of old pavement
2.2.2.5 Removal of Fences and Gates
of different types, (i.e. down to the bottom of the base course) or as
1 When fences and gates enclosing pasture land or farm land are directed by the Engineer, for the portions which are within the limit
to be removed, the Contractor shall notify the Engineer sufficiently of Works.
in advance to permit the property owner reasonable time to construct Unusable perishable material shall be disposed of in accordance with
alternative fencing or make other suitable arrangements. the applicable laws and ordinances. Non-perishable material may be
disposed of off the Site, provided permission of the concerned
2.2.2.6 Removal of Wells, Shafts and Falajs
authorities and/or the respective property owner has been obtained in
1 Existing wells and shafts, abandoned or active, which lie writing to dump such materials on their land.
within the limits of the Works, shall be dismantled, backfilled, and 4 Cavities left by pavement removal shall be filled to the level of
compacted. All salvageable materials shall be removed and stored at the surrounding ground and, if within the prism of construction, shall

2-2
be compacted to the type of compaction specified in Sub-section 2.6 xi. Removal of concrete safety barrier including
– ‘Subgrade Construction’. foundations (dimensions and Type), (lin.m.)
xii. Removal of sign boards including
5 The Contractor shall be responsible for supporting and
post and foundations (size), (nr.)
protecting existing Utilities that are to remain in place, for the
xiii. Removal of Floodway marker posts and
duration of the Contract and shall provide all necessary Temporary
foundations (size), (nr.)
Works in this respect. Any damage caused to utilities and
xiv. Removal of re-usable steel safety barrier
attributable to the Contractor shall be repaired at his expense.
including post and foundations
6 The Contractor shall be responsible for and shall ensure that (dimensions and Type), (lin.m.)
pavement removal operations are completed without applying xv. Removal of re-usable concrete safety barrier
extreme vibration and heavy loading that might damage the existing including foundations
underground utilities. (dimensions and Type), (lin.m)
xvi. Removal of re-usable sign board including post and
2.2.2.9 Removal of Existing Road Furniture
foundations (size), (nr.)
1 Road Furniture items such as curbs, tiles, steel and concrete xvii. Removal of reusable Floodway marker posts
safety barriers, lighting poles, flag poles, sign boards, etc. which lie including foundations (size), (nr)
within the limits of the Works, shall be removed and disposed of, or xviii. Removal of drainage protection
handed- over, as directed. works (type), (cu.m.)
xix. Removal of existing fences and
2.2.3 Method of Measurement gates (description and type), (lin.m.)
xx. Removal of existing block and
1 Removal of structures and obstructions is measured by number,
masonry walls (Size and Type) (cu.m)
length, area or volume as appropriate for the relevant work, unless
xxi. Removal of ditches (Type and size), (lin.m)
Item 2.2.3 (2), applies. The rates shall include in full for the removal,
xxii. Removal of bridges (dimensions, type and
storage, protection and disposal of the structure or obstruction,
description) (nr.)
including items necessary for the proper completion of the work.
xxiii. Removal of rocks and boulders larger than
2 If the Bill of Quantities does not contain separate items for 0.2cu.m. or 500 kg (description) (cu.m.)
removal of structures and obstructions, this work will not be paid for xxiv. Removal of wells and shafts (description and
directly but will be considered as subsidiary work related to other location) (nr.)
items in the Bill of Quantities. xxv. Removal of sand dunes (location
and description) (cu.m.)
2.2.4 Basis of Payment xxvi. Removal of Light Poles including
cabling and foundation (Size) (nr.)
1 The quantities of completed and accepted work, measured as
xxvii. Removal of flag poles including foundation (nr.)
provided for above, will be paid for at the relevant unit rates stated in
xxviii. Removal of Debris Deflectors including
the Bill of Quantities, which rates shall be full compensation for
foundation (nr.)
equipment, tools, labor, materials, transporting and dumping, and for
xxix. Removal of Reuse of Debris Deflectors (nr.)
other items necessary for the proper completion of the work.

2.2.5 Items in the Bill of Quantities 2.3 Roadway Excavation


i. Removal of existing building (type and 2.3.1 Description
description), (nr. or
Length / Area / Volume as appropriate). 1 This Sub-section describes excavation in the cut sections of the
ii. Removal of reinforced concrete (type, location, and roadway, including watercourses, ditches and wadi relocations (but
dimensions), (cu.m.) excluding borrow pits and structural excavation) all as and where
iii. Removal of mass concrete (type, location and shown on the Drawings, and hauling the excavated material either to
dimensions), (cu.m.) locations for roadway embankments or to stockpiles or to waste.
iv. Removal of pre-stressed concrete (type, location 2 The work also includes any necessary excavations outside the
and dimensions), (cu.m.) ROW ordered by the Engineer to safeguard and protect the Works,
v. Removal of curbs (Type), (lin.m.) including diversion of existing wadi channels; excavation of
vi. Removal of Tiles (Type and Size), (sq.m.) materials obstructing or impairing the flow along stream channels;
vii. Removal of pipe culverts (type and excavation of unstable materials which may slide or encroach
and diameter), (lin.m.) into ditches or onto the ROW. Disposal of all such excavated
viii. Removal of existing pavement materials shall be as instructed by the Engineer.
(description and type), (cu.m.)
ix. Removal of reusable road studs, (nr.) 2.3.2 Classification of Roadway Excavation
x. Removal of steel safety barrier including post and
foundations (dimensions and Type), (lin.m.) 1 Road excavation shall be considered as ’Unclassified
Excavation’ which includes all materials encountered of any nature
including silts, clays, sand, gravel, granular materials, all cohesive

2-3
and fractured, jointed cohesionless materials and/or massive rock such drainage ditches and construction grades shall be cleaned and
and unsuitable material. trimmed at regular intervals and when directed to maintain an
unobstructed runoff of storm water during construction.
2 Any information concerning properties of the soil which may
be shown on the Drawings, in the Bill of Quantities, in 3 Damage to the Works attributable to saturation or erosion of
supplementary reports, or as a result of discussion with the Engineer slopes during the period of execution through failure to provide
or others shall be considered as gratis and shall not be a basis for the adequate drainage shall be repaired by the Contractor at his own
Contractor's determination of his bid prices. expense.
4 Whenever groundwater is encountered which may adversely
2.3.3 Construction Requirements affect construction, the Contractor shall advise the Engineer who will
evaluate the situation and order necessary remedial measures.
2.3.3.1 Utilization of Excavated Materials
2.3.3.3 Obliteration of Disused Roadways
1 All materials removed from the excavation shall be used in the
formation of the embankment, sub-grade, shoulder, dykes, and at 1 Obliteration of roadways which are no longer in use shall
such other places as directed, unless it is declared unsuitable and include filling of all ditches and rough grading of the old roadway to
ordered to be wasted by the Engineer. produce within the ROW a neat and well drained ground surface.
2 Unsuitable material shall include:
i. Unstable materials incapable of being compacted to the 2.3.3.4 Rock Blasting
specified density using mechanical compaction
methods at optimum moisture content for the 1 Rock blasting explosives may comprise a diversity of systems,
equipment being used for compaction. including dynamite explosives, watergels, slurry explosives and
ii. Material too wet to be compacted and where slurry blasting agents, pumpable blasting agents, emulsion
circumstances prevent suitable in-place drying prior to explosives and aluminized explosives. Whenever instructed by the
incorporation into the work. Engineer, blasting shall be carried out after pre-splitting the rock
iii. Materials which are otherwise unsuitable for use in or mass by using small localized charges in pre-drilled holes.
under the embankment. 2 When blasting of rock slopes is carried out, a reasonably
uniform face shall be left, regardless of whether or not the excavation
3 No excavation material shall be wasted without written
is carried beyond the specified side slopes as shown on the Drawings.
permission from the Engineer.
All breakage and slides shall be removed and disposed of as directed.
4 If the Contractor chooses to excavate suitable material to waste A dust control system shall be designated by the Contractor and shall
or put it to other uses, and replace it by borrow excavation for be implemented during rock blasting after obtaining the Engineer’s
embankment areas, this shall be undertaken at no extra cost to the approval.
Employer.
3 All drilling and blasting shall be done in such a manner as will
5 Excavated rock which is not immediately suitable for most nearly complete the excavation to the required grade lines, and
incorporation in the works can either be broken down to acceptable produce the least possible disturbance of the material to be left in
sizes or wasted at Contractor's own expense. If such material is place. Blasting by means of drill holes, tunnels, or any other
wasted or used in concrete, granular subbase, aggregate base, asphalt methods shall be entirely at the Contractor's risk. Explosive
mixtures or any other works, the Contractor shall replace it by materials shall be stored and kept under the constant surveillance of
borrow excavation for embankment at no extra cost to the Employer. the Royal Oman Police.
6 Where shown on the Drawings or directed by the Engineer, 4 Where necessary or directed, the Contractor shall provide
salvaged materials such as existing concrete, bituminous or other heavy mesh blasting mats or controlled blasting for protection of
pavements shall, be stockpiled for a specific purpose or for future use. persons, properties, and the Works. If, in the opinion of the
Such materials shall be excavated and handled in a manner that will authorities and the Engineer, blasting would be dangerous to persons
exclude foreign or undesirable material. Stockpiles shall be neatly or adjacent structures, or is being carried out in an unsafe or
formed and maintained in an approved manner. unacceptable manner, the Engineer may prohibit blasting and order
7 Where specified or directed by the Engineer, suitable topsoil the rock to be excavated by other means.
material shall be stockpiled during excavation operations and shall 5 During explosion works, traffic shall be suspended from the
subsequently be spread and compacted on embankment slopes and routes linking to the Site and all diversions and other arrangements
elsewhere as directed, to facilitate re-growth of vegetation. shall be carried out in full coordination with the Royal Oman Police.
The Contractor shall secure approval of his schedule for such
2.3.3.2 Drainage of Excavation Areas
interruptions and his proposed methods for safeguarding the public
1 During construction, surfaces in excavation areas shall be and property.
adequately drained at all times. Side ditches or gutters emptying Excessive blasting will not be permitted. Overbreakage and the
from cut to embankment shall be so constructed as to avoid damage backfilling thereof shall be at the Contractor’s expense. Any
to embankments by erosion. material outside the approved cross section limits which may be
shattered or loosened because of blasting shall be removed by the
2 The Contractor shall, at an early stage of the Works, provide
Contractor at his own expense. All rock slopes with loose material
adequate drainage by scheduling ditch and other construction so as to
shall be scaled by workmen and all loose material removed at the
prevent saturation or erosion of embankments and cut slopes. All
Contractor’s expense.

2-4
6 Backfilling of overbreakage shall be carried out as directed, If the material of the sub-grade is suitable for retention as sub-grade
using approved soil or crushed materials or other special aggregate or layer then it shall be scarified to the required depth, watered and
cyclopean concrete, as shown on the Drawings or as directed by the compacted in accordance with Section 2.6 – ‘Subgrade Construction’,
Engineer. Undrained pockets shall not be left in the surface of the paragraph 2.6.3.1.
rock. 7 The Engineer will periodically check all or any part of the
7 Following blasting, cleaning and scaling rock slopes, the face, work, to determine conformance to the correct lines, grades and
benches and back of the slope shall be inspected for potential failure elevations. Tolerances on finished sub-grade levels and on levels of
planes and the necessary remedial measures shall be taken, as the surface at the underside of the sub-grade layer shall be as
approved by the Engineer, at the Contractor’s expense. specified in Sub-section 2.6 – ‘Sub-grade Construction’, Paragraph
2.6.3.3.
2.3.3.5 Excavation of Unsuitable Material 8 In cases where rock or soil excavations reveal that the adopted
1 Unsuitable materials are materials that do not comply with the cut slopes are not suitable and if failures occur during or after
requirements for suitable materials as described under Clause 2.5.2 completion of the excavation works and while the Contractor is still
below. on Site, the Engineer may request the Contractor to re-excavate
according to the newly established cut slopes, the extra work will be
2 Where excavation to finished grades and cross sections
measured and valued as Unclassified Excavation at the same rate
exposes unsuitable material in the sub-grade, slopes or ditch inverts,
given in the Contract. However, in such case, the Contractor may
etc the Engineer may require the Contractor to remove the unsuitable
submit a proposal for any other alternative solution for the stability
material and backfill the excavated areas using approved material.
of the cut slopes, for the Engineer’s appraisal and final decision.
The Contractor shall plan his operations so that necessary cross
section measurements are taken before such backfill is placed.
2.3.3.7 Unstable Materials outside Right-of-Way
3 Unsuitable material shall be disposed off as directed. Wasted
unsuitable material shall not be deposited on any cropland. 1 Materials outside the ROW or ditch slopes which, in the
4 When the Contractor is directed to excavate unsuitable opinion of the Engineer, are potentially unstable and liable to slide or
material below the surface of the original ground in fill areas, other encroach into the ROW or into the ditches, shall be excavated and
than that required for clearing and grubbing, the depth to which disposed of as specified for unsuitable material, unless it is approved
unsuitable material shall be removed will be determined by the for use as embankment fill.
Engineer. The Contractor shall plan the excavation so that cross
2.3.3.8 Disposal of Unsuitable and Surplus Material
sections are taken before and after material has been removed.
1 Unsuitable and surplus materials disposed of within approved
2.3.3.6 Slopes, Subgrade and Ditches areas shall be spread, leveled and shaped as directed so as to present
1 All excavated slopes, sub-grade and ditches shall be finished a neat and tidy appearance. No materials shall be disposed of in such
true to lines, grades and cross sections as shown on the Drawings. a way as to adversely affect natural drainage courses or to cause
damage to the highway or adjacent public or private property.
2 Slopes, except in massive rock or other material which require
special treatment, shall be trimmed to slopes not steeper than the 2 If approved by the Employer, Government land may be used
specified slope angles and rounded at top and bottom to a smooth for disposal to the maximum extent practicable. If private land is
profile to blend in with the adjacent terrain. Material shall not be used for disposal, the Contractor shall secure the consent of the
loosened beyond the specified slope lines. High cut areas shall landowner or tenant and, if necessary, and at his own expense, pay
continuously be monitored by an engineering geologist or a for the use of such land. The use of cropland for disposal purposes
geotechnical engineer. will not be permitted.

3 In cuts where earth overlays a rock formation, slopes shall be


2.3.4 Method of Measurement
benched in an approved manner.
4 Ditches of all types shall be excavated and trimmed neatly in 1 All excavated material of whatever type (except for
conformity with the specified grades and cross sections. All unauthorized undercut below top of sub-grade or excavations taken
projecting rock, stumps, roots or similar shall be removed. Ditches wider than required) shall be measured as ‘Unclassified Excavation’
include side ditches, interception ditches in the berm of cut slopes, which shall be deemed to include all materials encountered of any
furrow ditches, irrigation ditches, wadi relocations, etc. nature, including silts, clays, sand, gravel and granular materials and
fractured, jointed and massive rock, whether weak or strong, and
5 Where the sub-grade is composed of rock as defined in Sub-
unsuitable material, as approved and instructed by the Engineer.
section 2.6 – ‘Sub-grade Construction’, it shall be undercut to a
depth of 200 mm below top of sub-grade to allow for subsequent 2 Unclassified Excavation shall be measured by cu.m. of
placing and compaction of the leveling sub-grade layer in accordance material excavated, hauled away and either wasted, stockpiled, or
with Sub-section 2.6 – ‘Sub-grade Construction’, paragraph 2.6.3.1. deposited on or in vicinity of roadway embankments and dykes.
Measurements shall be of volumes computed from the cross sections
6 The sub-grade in cut, where the soil is unsuitable for retention
shown on the Drawings, using the Average End Area Method, and
as the sub-grade layer, shall be sub-excavated to a depth of 200 mm
the original ground elevations taken jointly by the Engineer and the
below top of sub-grade to allow for subsequent placing and
Contractor after clearing and grubbing operations. These ground
compaction of the sub-grade layer.
elevations shall form the basis of measurement of the permanent
works. Rates shall include for costs of supporting sides of excavation

2-5
where necessary, keeping excavations free from water, proper 2.4 Borrow Materials
formation of embankments, trimming of slopes, preparation and
completion of the roadway, sub-grade, dykes and shoulders and 2.4.1 Description
scarifying for suitable sub-grade material.
1 This Sub-section describes excavation of suitable material
3 Excavation of unstable material (from areas outside the ROW) from borrow pits, channels and designated borrow areas and hauling
shall be measured by cu.m. of material excavated, hauled away and to locations of embankments or to stockpiles, all as shown on the
disposed of as directed, completed and accepted. Measurements Drawings, or as directed by the engineer.
shall be of volumes computed from surveyed cross sections of
2 The Contractor shall be responsible for locating suitable
original and final ground elevations. When cross sectioning is
borrow pits and for the suitability and sufficiency of borrow
impractical in the opinion of the Engineer, approval may be given to
materials to meet the specified embankment and other backfilling
measure volumes in the vehicles removing such excavated material.
requirements.
4 Ditch excavation and excavation of unstable material are
3 Borrow pits shall be utilized if there is insufficient suitable
considered part of the unclassified excavation.
excavated material to satisfy the embankment and other backfilling
5 Rock blasting, backfilling of overbreakage, trimming and requirements or if the Contractor chooses to excavate suitable
grading of cut slopes, ditches and of other below-sub-grade surfaces, material to waste or put it to other uses, and replace it by suitable
drainage of excavation areas, obliteration of disused roadways, and material excavated from borrow pits at the Contractor’s expense.
other ancillary excavation Works shall not be measured for direct
payment, but shall be considered as subsidiary work the costs of
which will be deemed to be included in the rates for Unclassified
2.4.2 Location of Borrow Pits
Excavation. 1 Generally, the borrow pits shall not be located within 50 m
from the toe of embankment slope or top of cut or formed slope,
6 Excavation under water shall be measured by cu.m. of
unless otherwise approved by the Engineer.
material excavated, hauled away and disposed of as directed,
completed and accepted (including any side support or other 2 In no case shall borrow pits be located within 200 m
enabling works). Measurements shall be of volumes computed from downstream of a drainage structure without the written approval of
surveyed cross sections of original and final ground elevations. the Engineer. Unauthorized borrow pits shall be backfilled and
When cross sectioning is impractical in the opinion of the Engineer, compacted, as directed by the Engineer, at the Contractor's expense.
approval may be given to measure volumes in the vehicles removing 3 In each case where a borrow pit is proposed within privately-
such excavated material. owned property, the Contractor shall secure the consent of the
7 Hauling of excavated materials shall not be measured for landowner in writing, if necessary, and shall, pay for the use of the
direct payment, but shall be considered as subsidiary work the cost material and land. The Contractor shall be solely responsible for any
of which will be deemed to be included in the rates for Unclassified claims for compensation or complaints arising out of borrow pit
Excavation, regardless of the distance required for hauling the operations.
materials to an approved dumping area. 4 The Contractor shall be responsible for the stability of the side
8 Excavation, Stockpiling and recompaction of suitable topsoil slopes of borrow pits and channels at all times, until the pit or
material shall be measured by cubic meter, laid, completed and channel is abandoned.
accepted as directed by the Engineer. 5 Details of the Contractor's proposed haul routes and traffic
arrangements in relation to borrow pit operations shall be submitted
2.3.5 Basis of Payment for approval before any borrow excavation commences.

1 The amount of completed and accepted work, measured as 6 Overburden and any unsuitable top layers within each borrow
provided for above, will be paid for at the unit rates for the various pit shall be completely removed and stockpiled in the vicinity, ready
items in the Bill of Quantities, which rate shall be full compensation for re-use prior to abandonment of the pit.
for equipment, tools, labor, materials, transporting and hauling, and 7 Prior to abandonment of any borrow pit or borrow area, the
for other items necessary for the proper completion of the work. Contractor shall spread and level the original overburden over the
exposed surfaces and clean up, grade and contour the pit or area and
2.3.6 Items in the Bill of Quantities the adjoining properties occupied during execution of borrow
operations, whether Government, or privately-owned, all to the
i. Unclassified Excavation cu.m.
satisfaction of the Engineer.
ii. Excavation of unstable material outside
Right-of-Way cu.m.
2.4.3 Borrow Material
iii. Unclassified Excavation under water cu.m.
iv. Excavate and Stockpile Suitable topsoil 1 Borrow shall be material approved by the Engineer as meeting
and recompact as directed cu.m. the requirements for the particular embankment, dyke, backfill or
other use for which the material is intended.
2 The Contractor shall submit representative samples of
materials from each of the proposed borrow pits or borrow areas. A
minimum of three sets of tests shall be performed for each borrow

2-6
area for each type of material. No borrow material shall be brought Requirements
to the site or used in the Works before its approval. i. 1 Maximum dry density not less than 1.7 g/cu.cm
(AASHTO T-180 Method D)
3 The Engineer will periodically require follow-up testing of ii. 2
borrow materials to verify that no change in quality has occurred Organic matter not more than 5% (AASHTO T-267)
since the original approval. iii. 3
Gypsum content not more than 3% (BS 1377 Part 3)

2.4.4 Method of Measurement iv. 4


No use of A-6, A-7 soil (AASHTO M-145)
1 Borrow Excavation shall be measured by cu.m. of suitable v. 5
Maximum size not more than 1/2 of the layer thickness
material excavated, hauled and used in the proper formation of
embankments, including clearing and grubbing, trimming of slopes, vi. 6 Plasticity Index (P.I.) less than 15% for National, Arterial
preparation and completion of the roadway sub-grade, shoulders and and Secondary Roads and 20% for other roads
dykes. 4-day soaked C.B.R. should not be less than 8%
vii. 7 (AASHTO T-193) when compacted at 100% maximum
2 The quantity of borrow excavation shall be determined by dry density in accordance with AASHTO T-180 Method
calculating the total quantity of filling after compaction and D.
deducting therefrom the total quantity of unclassified excavation less Table 2.5.2.1: Soil Suitable for Embankment
an allowance for material condemned by the Engineer as unsuitable
for filling. 2 The 200 mm depth of embankment sub-grade layer
immediately below the bottom of subbase or aggregate base shall
2.4.5 Basis of Payment consist of selected sub-grade material having a 4-day soaked C.B.R.
of at least 25% when tested in accordance with AASHTO T193 and
1 The amount of completed and accepted work, measured as when compacted at 100% Modified Proctor Density in accordance
provided for above, will be paid for at the unit rates for borrow with AASHTO T-180D, with a gradation and P.I. as specified under
excavation in the Bill of Quantities, which rate shall be full
Sub-section 2.6 – ‘Sub-grade Construction’.
compensation for clearing and grubbing for borrow areas, equipment,
tools, labor, materials, transporting, hauling and placing, and for 3 The 600 mm depth of embankment immediately below the
other items necessary for the proper completion of the work. sub-grade layer shall consist of suitable material having a 4-day
soaked C.B.R of at least 15% when compacted to 95% maximum dry
2.4.6 Items in the Bill of Quantities density in accordance with AASHTO T-180D and tested in
accordance with AASHTO T-193 with a P.I. not more than 15%. If
i. Borrow excavation. cu.m.
rockfill is used for the bottom 400 mm depth then these requirements
shall apply to the top 200 mm depth below the sub-grade layer.
2.5 Embankments 4 Rockfill shall not be used in the top 200 mm of the
embankment below the sub-grade layer. If found necessary and if
2.5.1 Description approved by the Engineer, water may be added as required to achieve
1 This Sub-section describes construction of roadway maximum compaction.
embankments, dykes, including preparation of the areas upon which 5 In areas subject to flooding and prolonged inundation of the
they are to be placed; testing of the material, placing and compacting embankment, such as at bridge and culvert sites, the material used in
approved material within areas where unsuitable material has been embankment shall conform to AASHTO M 145, Class A-1-a, A-1-b,
removed; and placing and compacting approved embankment A-2-4. Rockfill can also be used in these conditions, except for the
material in holes, pits and other depressions within the constructed top 600mm of the embankment. The first 600mm of fill on top of
area, all in accordance with the lines, grades and cross sections
culverts shall consist of suitable soil fill. Rockfill on top of culverts
shown on the Drawings.
is allowed only when it is underlain by a minimum thickness of
600mm suitable soil fill. All slopes surrounding culverts shall be
2.5.2 Materials constructed of suitable soil fill to facilitate trimming.
1 Materials suitable for embankment shall be of classes A-1, A- 6 Where embankments are to be constructed using material
2-4, A-2-5 or A3 ‘when confined’ groups as in AASHTO M145 and classified as A3 (AASHTO M 145) or other material subject to side
complying with Table 2.5.2.1, and shall be used when available, slope erosion or requiring confinement for stabilization purposes, the
except for rock fill embankments. If material of this character is not embankment plating or confining layer shall be constructed using
available, then material from A-2-6, A-2-7, A-4, A-5, groups AASHTO M 145 Class A-1-a, A-1-b, or A-2-4 materials or as
(AASHTO M145) may be used provided it complies with the otherwise approved.
requirements of Table 2.5.2.1; however, special attention shall be
7 The material used in rockfill embankments shall consist
given to its suitability for the particular construction.
predominantly of rock fragments of such size that the material can be
placed in layers of the thickness prescribed conforming to the
requirements stated in Table 2.5.2.2. The size distribution of rockfill
shall be determined according to CIRIA Special Publication 83:
Manual on the use of Rock in Coastal and Shoreline Engineering –
Appendix 2.

2-7
Requirements of each layer of embankment during all placing and compacting
operations.
1
Maximum particle size ........1/2 loose layer thickness
5 Whenever feasible, trucks, scrapers, tractors, loaders and other
2 heavy hauling equipment shall be routed over the embankment in
Passing 0.42mm (Sieve # 40) ........25% maximum
such a manner as will contribute effectively to compaction of the fill
Uniformity coefficient, Cu.......5 minimum, where material.
Cu = D60/D10
3 D60 = the Particle size at which 60% passes 6 Where an embankment is to be constructed over an area
previously occupied by a building basement, cellar, irrigation canal,
D10 = the Particle size at which 10% passes
well, any previous excavation, or adjacent to structures, and where
Table 2.5.2.2: Rock Suitable for Embankment the proper use of normal compaction equipment is not practicable,
the embankment shall be constructed and compacted in accordance
8 Rockfill material shall be obtained from quarries and shall be with the backfilling requirements of Sub-section 2.7 – ‘Excavation
sound, dense, hard and durable rock capable of being spread and and Backfilling for Structures’ until the use of normal compaction
compacted as specified. Individual pieces are to be clean and equipment is practicable. Layers shall not exceed 200 mm thickness
angular. It shall be the Contractor's responsibility to excavate (before compaction) and shall be compacted to the degree of
material from rock cuts, whether by blasting or other means, so that compaction specified for the embankment. The embankment
all excavated materials are of suitable size. construction under this item shall be measured and paid under the
9 When suitable materials of widely divergent characteristics are requirements of Clause 2.7.4.8: “Unclassified Structural Excavation”.
drawn from different sources, such materials may, if approved, be 7 Each embankment layer shall be tested and approved prior to
mixed to meet the embankment requirements. Rock and other placing the following layer in accordance with Clause 2.5.4 ‘Testing’.
materials shall be incorporated in such manner as to avoid 8 The Engineer may at any time order suspension of delivery of
segregation and an accumulation of boulders, etc., at the toe of materials to the embankment sites until previously delivered
embankment slopes. materials have been properly placed and preceding layers are leveled
10 Logs, trees, stumps, weeds, heavy grass, vegetable matter or and uniformly compacted to the specified density.
other undesirable and non-compatible materials shall not be placed in 9 Unacceptable material placed in any embankment shall be
embankments. removed and disposed of by the Contractor at his own expense,
11 Rocks larger than 100 mm in any dimension shall not be used immediately after receiving the Engineer’s instructions in this regard.
as fill material in areas where piling works are to be carried out. Any expected delay with the removal of such material shall be
12 Embankments that consist of rock-soil material shall include coordinated and agreed with the Engineer.
sufficient soil material to make rolling and compaction feasible. The 10 The Contractor shall be responsible for the stability of all
material shall meet, in general, all the requirements for rockfill embankments and shall replace all embankment sections which, in
embankment. The soil material in the mixture shall meet the the opinion of the Engineer, have been damaged or displaced due to
requirements of embankment fill soil material and shall have a CBR
carelessness or neglect on the part of the Contractor, or due to
of 15% minimum and the rock fragments shall comply with the
normally occurring natural causes, such as storms, and not
requirements of rockfill material. The percentage of rock fragments
attributable to the unavoidable movement of the natural ground upon
exceeding 75mm shall be limited to 30% maximum.
which the embankment is constructed.
11 All embankment side slopes shall be neatly finished true to the
2.5.3 Construction Requirements
lines and not steeper than the slope angles as shown on the Drawings.
2.5.3.1 General The bottom (toe) of side slopes shall be graded to a well-rounded,
smooth profile to blend in with the adjacent terrain.
1 Prior to placing embankment material on any area, the ground
12 Where directed by the Engineer, the side slopes of rockfill
shall have been cleared and grubbed as specified in Sub-section 2.1 –
embankments shall be thoroughly blanketed with A-1, A-2-4
‘Clearing and Grubbing’, and the foundation prepared as specified
material, and compacted to the satisfaction of the Engineer.
herein.
13 The Engineer may permit the Contractor to utilize suitable
2 Equipment used for foundation preparation and for placing,
surplus material at his own expense to widen embankments or flatten
spreading and compacting embankment materials shall be of
slopes, etc within the right-of-way. Surplus material used in such
approved types and furnished in sufficient numbers for the purposes
manner shall be compacted to 90 per cent of maximum density.
intended. Provision and use of such equipment shall conform with
When widening embankments, the Contractor shall bear the cost of
Section 19 ‘Plant and Equipment’.
modifying the culverts and any protection work necessary.
3 Draglines shall not be used to construct embankment unless
14 Rockfill shall not be used within 5m of a structural element
approval is given and only when special procedures are adopted to
(next to bridge abutments footings, etc). In some specific cases, rock
keep the layers uniform and the embankment properly graded and
fragments not exceeding 75mm particle size may be used next to
well-drained at all times.
structural elements, but only after obtaining the Engineer’s approval
4 Surfaces of embankment layers shall be kept properly shaped on the location and extent of the work.
and drained at all times. The Contractor shall utilize a sufficient
15 Rockfill shall not be used within 600 mm of top and bottom of
number of motor graders or tractors to level and maintain the surface
box and pipe culverts. Subgrade material shall be used in these areas
up to width excavated for structures.

2-8
16 Potable or sea water can be used for all embankment slopes steeper than 3:1 (H:V) when measured at right angles to the
construction works, except that only potable water shall be used for road centerline shall be continuously benched as the embankment is
compaction of fill material within 1m from all surfaces of structures. brought up in layers. Benching shall be of sufficient width to permit
operation of spreading and compaction equipment, and in any case
not less than 2 m wide except where insufficient width is available
2.5.3.2 Trial Embankments Sections between existing and new embankments. Each horizontal cut shall
1 If shown on the Drawings, or if required by the Engineer, a begin at the intersection of the original ground and the vertical sides
trial embankment shall be constructed. The trial section shall be at of the previous cuts. The vertical face of each bench shall not be less
least 2 lanes wide by 100 m long at approved locations at or adjacent than 1 m in height and not exceed 2 m. Approved benching shall be
to the Site. Compaction and other equipment used shall be as measured as unclassified excavation.
specified in Section 19 ‘Plant and Equipment’. 5 Where embankment is to be placed and compacted on wadi
slopes, the entire slope area shall be graded and trimmed to remove
2 The initial sections of rock embankment shall serve as the trial
any vertical faces and overhangs. The final graded slope shall not be
sections for rock fill, in order to establish the optimum degrees of
steeper than 1.5H:1V. The slope shall then be continuously benched
consolidation for the different layer thickness. This shall be obtained
as the embankment is brought up in layers, all as described above for
by compaction trials correlating number of passes of the roller with
embankment on hillsides.
settlement of the layer, or by different approved methods. The
maximum permitted layer thickness shall be related to the unit 6 Where embankment is to be placed over existing asphalt roads,
weight of the vibratory roller and for compaction, as given in Table the finished grade level of the road shall be at least 1200mm above
2.5.3.1 and shall not exceed 800 mm loose thickness. the existing roadbed surface.
7 Rockfill shall not be placed on any slopes steeper than 1:1. All
Maximum Thickness
Minimum Roller Mass* slopes steeper than 1:1 shall therefore be re-graded to a slope of 1:1
of Layer
(Kg/m Width) or milder and all vertical faces and overhangs removed.
(Loose Thickness)
400 mm 2300 - 2900 2.5.3.4 Embankment Construction
500 mm 2900 - 3600 1 Roadway embankment consisting of soil or granular material
600 mm 3600 - 4300 shall be placed in horizontal layers not exceeding 200 mm
compacted thickness, compacted as specified and approved prior to
700 mm 4300 - 5000 placing the next layer. The thickness of the first layer over areas of
Class A-3 dune sand may exceed 250 mm in order to bridge these
800 mm > 5000
areas. Approximately uniform thickness of each layer shall be
* For multiple rollers, this shall be assumed as the high achieved prior to compaction. As the compaction of each layer
axle load. progresses, continuous leveling and working of the material shall be
Table 2.5.3.1: Maximum Layer Thickness / Minimum Roller carried out to ensure uniform density. The correct moisture content
Mass Requirements shall be maintained at all times.
2 Where embankments are to be constructed to a height in
2.5.3.3 Foundation Preparation
excess of 1.5 m above top of original ground level, the Engineer may
1 If the original surface upon which embankment is to be placed approve layers up to 250 mm compacted thickness if these layers are
is an existing pavement, the surface shall be ploughed, scarified, or located at depths greater than 1.5m from the final elevation of
otherwise broken up regardless of the height of the embankment to embankment and if the Contractor's equipment and the nature of the
be placed thereon. material result in the required density throughout the layer thickness.
2 Clearing and grubbing, and removal of tree stumps, shall be 3 When the moisture content of the embankment material does
undertaken. The degree of compaction for the area to be cleared not fall within the required moisture range, (optimum moisture ±
shall then be determined. The top 150 mm of the surface on which 2%) water shall be added and thoroughly mixed into the soil by
the embankment is to be placed shall be scarified, brought to a approved methods or the material shall be aerated, whichever is
uniform moisture content within the specified range, and compacted necessary to adjust the material to the required moisture content.
to the density specified for the embankment. Hard and smooth
4 When water is added to embankment material, the amount
surfaces are to be roughened before filling is placed.
added shall be sufficient to provide a moisture content within the
3 Where embankment is to be placed over topsoil containing required range plus a reasonable additional amount to compensate
unsuitable organic material which does not meet the requirements of for evaporation and other unavoidable losses. Water added in excess
Table 2.5.2.1, the ground shall be stripped off to a depth of 200mm of this amount shall be removed by aeration or other approved means
and the cleared surface shall be scarified to a minimum depth of at the Contractor's expense. Satisfactory methods and sufficient
200mm or as directed by the Engineer, brought to a uniform equipment shall be used for the furnishing and handling of the water
moisture content within the specified range, and compacted to the in a manner that will minimize loss due to evaporation or waste.
density specified for the embankment.
5 Embankments that consist of rock-soil material with sufficient
4 Where embankment is to be placed and compacted on hillsides soil to make rolling feasible shall be placed and compacted in an
or where new embankment is to be compacted against existing approved manner and to the required degree of compaction. Water
embankments or where embankment is built part width at a time, the

2-9
shall be added as and when directed to assist in the compaction of Alternatively an electronic compaction meter or any other approved
such materials. test equipment shall be provided by the Contractor and used to
determine the degree of compaction achieved.
6 In the case of embankments which are to be formed of
approved rock-soil material containing an appreciable quantity of 5 To determine the degree of compaction for embankment
rock fragments (normally not exceeding 30% greater than 80mm) consisting of rock fill, average differential settlement values shall
and which cannot be placed in layers of the thickness prescribed also be determined from surveys of an adequate number of grid point
without crushing, pulverizing, or otherwise breaking down the elevations as directed by the Engineer at the commencement of,
fragments, the embankment may be constructed in layers not during and after embankment construction. (Refer to Item 6 of
exceeding in thickness twice the average size of the largest rock Paragraph 2.5.4.3 below).
fragments and in any case not exceeding 600 mm (before 6 For rockfill embankments, the modulus of soil reaction shall
compaction). be determined by the plate bearing test; using the method given in
7 Rockfill materials shall be placed in such a manner that the AASHTO T222.
larger rocks are well distributed and the voids are filled to the
2.5.4.2 Standards of Compaction for Soil and Granular
maximum practical extent by smaller particles of rocks, gravel or
Materials
approved granular materials. Each layer shall be bladed into a neat
and homogeneous mass prior to compaction. Any rocks found 1 The following compaction standards shall apply to
protruding from the leveled surface shall be removed and replaced embankment materials other than predominantly rock materials. The
by smaller particles. Initial breakdown compaction shall be ‘maximum density’ of soil type materials shall be the modified
performed with heavy bulldozers. The top level of each layer must maximum density determined in accordance with AASHTO T 180
be surveyed before and after compaction and approved by the (Method D). The ‘relative density’ shall be the relative density
Engineer before the next layer is placed. Oversize rock pieces (i.e. determined in accordance with ASTM D 4254, which identifies the
exceeding the maximum particle size defined in Table 2.5.2.2 by not state of compactness of the material with respect to its loosest and
more than 10%) may be used in high rockfill embankments to a level densest state. The relative density shall be the standard to which the
3 meters below sub-grade. field density is referred for comparison in the case of cohesionless,
8 Rock-soil embankments shall be placed and compacted in an free draining granular materials.
approved manner and to the required degree of consolidation. Water 2 Soil type materials shall be compacted to at least 90%
shall be added as and when directed by the Engineer to assist in the modified maximum density for the full depth of embankment; except
compaction operations. for the 600 mm of embankment material immediately below the sub-
9 Embankments which are formed of approved rock-soil grade layer that shall be compacted to at least 95% modified
material containing a considerable quantity of rock fragments (not maximum density. Moisture content shall be within plus or minus
exceeding 30% exceeding 75mm) and which cannot be placed in 2% of optimum at the time of compaction.
layers of the required thickness without crushing, pulverizing or 3 Cohesionless, free draining granular materials (of 75 mm
breaking down the fragments, the embankment may be constructed maximum size, with not more than 15% passing 0.075 mm (No. 200)
in layers not exceeding the thickness twice the average size of the sieve and a plasticity index (PI) not exceeding 20%) shall be
largest rock fragments and in any case not exceeding 600mm compacted to at least 70% of relative density for the full depth of
uncompacted thickness. embankment. The 600 mm depth of such material immediately
below the sub-grade layer shall be compacted to at least 75% of
2.5.4 Testing relative density.

2.5.4.1 General 4 Minimum soil tests required during the construction of sub-
grade and/or embankment are:
1 For verification of material, moisture content, compaction, - One sample for CBR, classification (AASHTO M145),
thickness and other properties of the materials or workmanship the and laboratory (Moisture - density) or relative density
Engineer shall at all times have access to all parts of the Works and compaction from each source prior to use. Each sample
Site. All sampling and testing of material and work shall be carried shall represent not more than 5,000 cubic meters.
out as specified to the satisfaction the Engineer. - One sample for classification representing not more
2 Materials shall be tested in accordance with AASHTO T96, than 3,000 cubic meters of the material in use.
ASTM D2167, AASHTO T104, AASHTO T176, BS 1377, - For every completed layer, one field density shall be
AASHTO M145, ASTM D1556/D1556M and other applicable and determined for each 1500 square meters or 100 linear
relevant standards. meters, whichever is less. Testing shall be in
accordance with ASTM D 1556/D1556M or ASTM D
3 The Engineer shall test the compaction of embankment
2167 or BS 1377 Part 9.
materials in accordance with the Specification to ensure that
adequate compaction or consolidation has been achieved. All such 2.5.4.3 Degree of Compaction for Rock Fill and Rock-Soil
tests shall be fully documented by the Contractor, in an approved
Materials
manner.
4 In the case of cohesionless, free draining rock-soil materials, 1 To ensure proper compaction of rockfill and rock-soil
where maximum density tests fail to produce a well-defined embankments, the Contractor shall conduct compaction tests such as
moisture/density relationship, the relative density test shall be used. the plate load bearing test or other approved equivalent tests using

2-10
equipment and materials available in order to determine the best using Average End Area Method as per sub-section 2.3.4.2. The cost
compaction control criteria. is deemed to be included in the items for excavation and borrow
excavation stated in Sub-sections 2.3 and 2.4.
2 A rockfill/rock-soil test section shall be placed on a firm
surface approved by the Engineer, and the material and layer 2 The volume of embankment displaced by pipe culverts, box
thickness shall conform to the requirements of these specifications. culverts and associated end walls shall be deducted from the
3 The test section shall be of sufficient dimensions to permit the measured volume of embankment. No deduction shall be made for
establishment of at least twenty leveling points on a 5 meter (5m) pipes less than 500 mm in diameter and associated end walls.
square grid, and no fewer than 3 points on any one line and no point 3 Surplus materials utilized at the Contractor's option within the
less than three meters from the edge of the layer. The arrangement of ROW but, beyond the cross sections shown on the Drawings, are not
the leveling points shall be approved by the Engineer. measured as part of the embankment.
4 Compaction shall then commence with a minimum of three 4 Benching described under Item 4 of Paragraph 2.5.3.3 is
passes of a vibratory roller, as shown in Table 2.5.3.1. Leveling measured as Unclassified Excavation, under Clause 2.3.4.
points shall then established, short lengths of painted steel bars
5 No adjustments or allowances are made in respect of
hammered flush with the surface of the rockfill are suitable for this
expansion or shrinkage of earthwork volumes which may occur
purpose. A level reading shall be taken at each leveling point on top
during excavation and compaction.
of a moveable 300 mm square flat steel plate with a hole drilled in
the center of the plate to enable a visual check to be made that the 6 Embankment foundation treatment such as stripping,
plate is located centrally over the bar. scarifying and re-compaction of topsoil containing unsuitable
organic material, as detailed in Item 3 of Paragraph 2.5.3.3 is not
5 Further readings shall be taken at the leveling points after two
measured but shall be considered as subsidiary work the costs of
additional passes with the roller. If the average settlement is less
which are deemed to be included in the rates for excavation and
than half of one per cent (0.5%) of the average compacted layer
borrow excavation in Sub-sections 2.3 and 2.4.
thickness, or as determined by the Engineer, the rockfill/rock-soil
compaction test is deemed complete. 7 Scarifying old pavement beds (where required), construction
of the trial embankment section if it is outside the pavement,
6 If the average settlement is more than half of one percent
foundation, preparation, testing, including furnishing and using an
(0.5%), two additional passes of the roller are required and the
approved type electronic compaction meter and grid pattern
leveling procedure shall be repeated. If the average settlement is
consolidation surveys, and all other ancillary embankment work are
then less than half of one percent (0.5%), of the average compacted
not measured, but shall be considered as subsidiary work the costs of
layer thickness the test is deemed complete. If not, this step shall be
which are deemed to be included in the rates for excavation and
repeated.
borrow excavation in Sub-sections 2.3 and 2.4.
7 The total number of passes of the rolling equipment necessary
to obtain the required result will establish the minimum number of 2.5.6 Basis of Payment
passes to be used on the rock embankments. However, in no case
shall the number of passes be less than five (5). 1 No separate payment will be made for any work in this Sub-
section 2.5. The cost of all work for embankments is deemed to be
8 This verification procedure shall be conducted for each change
included under Sub-sections2.3 and 2.4.
of material and at least once each week during the initial stages of
construction until a reliable rolling pattern is established. The
frequency verification procedure can then be reduced as approved by
2.5.7 Items in the Bill of Quantities
the Engineer. 1 No items are included in the Bill of Quantities. All items
9 Documentation of the rockfill/rock-soil compaction tests shall under Sub-section 2.5 are subsidiary to other items.
be maintained by the Contractor in the project records and shall be
copied to the Engineer. 2.6 Sub-grade Construction
2.5.4.4 Monitoring Settlement of Rockfill
2.6.1 Description
1 On completion of the embankment, the Contractor shall carry
1 This Subsection describes construction of the sub-grade layer
out precise leveling of the crest of the embankment. This shall
and preparing the sub-grade surface ready to receive the pavement
consist of leveling transverse sections (a minimum of five points) at
structure including shoulders, all as shown on the Drawings.
a maximum spacing of 30 m along the embankment. These shall be
referenced to a stable approved datum. Leveling shall be carried out 2 The sub-grade layer is the 200 mm minimum depth of selected
at suitable time intervals until the average rate of settlement over a material immediately below the sub-grade surface, or as defined in
period of one month does not exceed 0.1 mm per day. No permanent the Drawings or directed by the Engineer.
pavement construction will be permitted until the specified criteria 3 Wherever shallow ground water is expected under the roadway
are achieved. Adequate time shall be allowed in the construction and wherever damage to the pavement layers is potential due to
program for the settlement survey. water impact, a suitable subsurface drainage blanket shall be
installed under the subgrade of the roadway. Drainage blanket is a
2.5.5 Method of Measurement course of washed granular material placed to cut off upward
capillary flow of pore water under paved areas, where and as shown
1 No separate items are included in the Bill of Quantities for
on the Drawings.
embankments and will be measured by the area of cross section

2-11
i. The 15% size of filter (D15 Filter) shall not be greater
2.6.2 Materials than 4 times the 85% size of the surrounding material
(D85 Surrounding material):
1 Sub-grade material shall consist of suitable materials of
D15 Filter < 4 D85 Surrounding material.
Classes A-1, A-2-4 or A-2-5 having a 4-day soaked CBR of not less
than 25% when tested in accordance with AASHTO T 193 when ii. The 15% size of filter (D15 Filter) shall not be less than
compacted at 100% of modified proctor AASHTO (T-180-D) and 4 times the 15% size of the surrounding material (D15
having a maximum P.I. of 10% and Gypsum Content not exceeding Surrounding material):
1% (BS 1377 Part 3). The Maximum Dry Density of Sub-grade D15 Filter > 4 D15 Surrounding material.
material shall be equal or greater than 1.9 t/cu.m. Sub-grade iii. The 50% size of filter (D50 Filter) shall not exceed 25
gradation shall be reasonably smooth without gap grading. All times the 50% size of the surrounding material (D50
material shall pass 75 mm sieve. The percent of material passing the Surrounding material):
0.075 mm (No. 200) sieve shall not exceed 18% and shall not be less D50 Filter < 25 D50 Surrounding material.
than 5%. Where directed by the Engineer, the Contractor shall screen iv. The plasticity index of the portion of all filter materials
the sub-grade material at his own expense. The top 200mm sub- passing sieve # 40 shall not exceed 6%.
grade material shall not contain more than 0.2% total Sulphate The filter materials shall not contain more than 5%
content and 0.05% total Chloride content in areas where the subgrade material passing through sieve # 200.
soil will be in contact with concrete structures or within a 6m
proximity to any buried concrete structures. For general embankment 2.6.3 Construction Requirements
fill layers (not in contact with concrete or within a 6m proximity to
any buried concrete structures), the material shall contain maximum 2.6.3.1 Subgrade in Cut
of 0.5% total sulphate content and 0.2% total chloride content.
1 Where the subgrade is located in rock, the sub-grade, unless
2 If a drainage blanket is shown on the Drawings to be installed shown otherwise on the Drawings, shall be undercut to a depth of
directly underneath the sub-grade, the sub-grade material shall 200 mm by drilling or blasting as directed. No rock shall project
respect the filter criteria specified under Item 5 of this Clause 2.6.2. more than 50 mm above the undercut surface elevation. The
3 Aggregate material for use in drainage blanket shall be rapid subgrade layer shall then be constructed using approved sub-grade
draining crushed stone, or crushed or uncrushed gravel conforming material.
to the properties stated in Table 2.6.2.1 below. 2 Where the sub-grade is on in-situ soil which is of a quality and
CBR value at least equal to those specified for sub-grade, the 200
Property Range mm depth of such material immediately below top of sub-grade shall
Permeability in m/day 300 - 1500 be scarified and all roots, sod, vegetable and other undesirable matter
Effective Porosity 0.25 and stones larger than 75 mm in any dimension shall be removed.
% Fractured Faces – (COE Method) Min. 75% The material shall then be brought to uniform moisture content
Cu (D60/D10) > 3.5 within the specified range and compacted to 100% AASHTO T 180
L.A. Abrasion – AASHTO T96 < 40 (Method D) maximum density.
California Bearing Ratio (CBR) – AASHTO A tolerance of ±2% is applicable to the specified above degree of
> 30%
T193 compaction for the subgrade layer, unless otherwise specified in the
Table 2.6.2.1: Properties of Rapid Draining Materials for use in particular specifications.
Drainage Blanket 3 Where the sub-grade is on in-situ soil which is unsuitable for
retention as the sub-grade layer, such material immediately below the
4 The gradation of the rapid draining material for use in drainage
top of sub-grade layer shall be sub-excavated to a depth of 200 mm,
blanket shall be as provided in Table 2.6.2.2 below:
hauled away and disposed of unless approved for use as embankment
Sieve Designation (mm) Percent Passing fill. The sub-grade layer shall then be constructed using approved
sub-grade material, as specified for sub-grade in embankment. If the
38.0 (1-1/2 in.) 100
material below sub-grade does not consist of suitable materials
25.0 (1 in.) 70 – 100 satisfying the requirements of top 600mm embankment, it shall be
19.0 (3/4 in.) 55 – 100 excavated for further 200mm and replaced by suitable material to
12.5 (1/2 in.) 40 – 80 satisfy the requirements of the top 600mm of the embankment.
9.5 (3/8 in.) 30 – 65
4 The underlying natural material shall be scarified, leveled and
4.75 (No. 4) 10 – 50
rolled. The surface of the natural soil shall be approved by the
2.4 (No. 8) 0 – 25
Engineer before placement of suitable material.
1.2 (No. 16) 0–5
Table 2.6.2.2: Gradation of Rapid Draining Materials for use in 2.6.3.2 Subgrade in Embankment
Drainage Blanket 1 The 200 mm minimum depth of embankment immediately
below top of sub-grade shall consist of selected, approved sub-grade
5 The layer directly underneath the drainage blanket and the one
material. The material shall be spread in one layer over the full
directly above it shall satisfy the following filter criteria:
width of the top of embankment, brought to a uniform moisture

2-12
content within the specified range and compacted to 100% AASHTO the Contractor’s expense, using rock fill and geotextiles as necessary
T 180 (Method D) maximum density. to ensure a safe stable surface.

A tolerance of ±2% is applicable to the specified above degree of 3 If directed by the Engineer the Contractor shall construct sub-
compaction for the subgrade layer, unless otherwise specified in the grade and embankment (where applicable) over sabkha areas or
particular specifications. gypsum-rich soils with a surcharge of excess material that shall
remain in place till all appreciable settlement has stopped. The
2.6.3.3 Surface Tolerances Contractor shall provide a means of monitoring the settlement. The
Engineer shall decide when appreciable settlement has stopped.
1 All finished levels, lines and grades shall be in accordance
with the details shown on the Drawings. Each cross section shall be 4 Unless a specific treatment for using geotextiles, geogrids or
checked at maximum intervals of 20 m, at each change in cross slope geosynthetics is described elsewhere in the contract, work over
and elsewhere as directed. sabkha or gypsum-rich soils shall consist of initially stabilizing the
existing weak soil by laying and rolling rock fill layer type 1
2 The tolerances on levels of finished sub-grade, top of
according to Table 2.6.3.2 below. This operation should be
embankment under the sub-grade layer and sub-excavated (undercut)
continued by adding and rolling type 1 rock fill layer with steel
surface shall be as given in Table 2.6.3.1.
vibratory roller till the layer is completely stabilized.
Surface Tolerances 5 A layer of geotextile fabric shall be laid over the compacted
type 1 pervious material. A layer of 50mm pervious backfill type 2
Finished Sub-grade Soil +10 or -30 mm
according to Table 2.6.3-2 shall be laid over the stabilized layer to
Rock (if approved) +50 or -50 mm protect the geotextile fabric.

Top of Embankment or Sub-excavated 6 A layer of 200mm thick capillary break rock fill type 1 shall be
+10 or -30mm laid over type 2 pervious backfill to receive the required road layers
Surface Soil
Table 2.6.3.1: Tolerances on Elevations of Finished Sub-grade after the above operation.

3 If instructed by the Engineer, when the finished sub-grade ASTM Standard Percentage Passing
surface is tested with a 4 m long straightedge placed parallel to, or at Sieve Size Type 1 Type 2
right angles to the centerline, the maximum depression of the surface 6 inch 100 -
from the straight edge shall be 30 mm. 5 inch 85 - 100 -
4 inch 75 - 90 -
2.6.3.4 Maintenance of Finished Subgrade 2 inch 45 - 65 -
1 The finished and approved subgrade shall be continuously 1 1/2 inch 35 - 55 -
maintained in a smooth, well compacted and properly drained 3/4 inch 20 - 35 100
condition until the sub-base (or base) course is constructed. Re- 1/2 inch 10 - 25 95 - 100
approval of the sub-grade will be required if the overlying course is 3/8 inch 5 - 20 70 - 100
not constructed within 14 days of sub-grade completion or if the sub- No.4 - 0 - 55
grade layer is damaged by traffic or any other causes prior to the No.8 - 0 - 10
placement of the sub-base layer. No. 16 - -
No. 200 - 0-3
2.6.3.5 Drainage Blanket
Table 2.6.3.2: Definition of Type 1 and Type 2 Rockfill Materials
1 Wherever and as shown on the drawings, place drainage for Sabkha Treatment
blanket under roadway pavements on prepared sub-grade as follows:
i. Compact drainage blanket to required cross sections
2.6.3.7 Subgrade Construction on top of Dune Sand
and thickness to not less than 95 percent of maximum
dry density according to ASTM D 1557. 1 Dune sand roadbed shall be compacted only after being
ii. Place drainage blanket in layers not exceeding 150mm confined by special means and methods that shall be approved by the
compacted thickness each, with no layer less than 75 Engineer. These methods may include the construction of an edge
mm thick when compacted. dyke of various materials on both sides of the road to provide the
necessary confinement.
2.6.3.6 Subgrade Construction on Sabkha and Gypsum Rich
2 Dune sand material will be allowed to receive dry compaction
Soils
only if the material is tested and proven to be A-3 type and only in
1 Where the road sub-grade passes over sabkha areas or case where the Proctor test showed a maximum dry density at 0 %
gypsum-rich soils with a high water table the Contractor shall take moisture. Otherwise, the material shall be brought to uniform
the special precautions mentioned below if the sabkha or the moisture content within the specified range and shall be compacted
gypsum-rich soils are encountered within the top 1m below the sub- to 100% AASHTO T 180 (Method D) maximum density.
grade level.
2 These precautions shall include but shall not be limited to the
2.6.4 Method of Measurement
construction of suitable temporary haul roads for all construction 1 Sub-grade layer in embankment is not measured separately but
plant operating in the area. Such haul roads shall be constructed, at is included as part of the computation for the volume of embankment.

2-13
2 Sub-grade preparation in cut is be measured by cu.m. of top retaining walls of all types; and for other major and minor structures;
width of sub-grade layer computed from cross sections shown on the including all necessary clearing and grubbing; bailing; drainage;
Drawings. The rate shall include for all excavation below top of sub- pumping; dewatering; sheeting; temporary shoring and cribbing;
grade, as per the thicknesses and material specified under Item construction of temporary cofferdams or cribs; backfilling with
2.6.3.1.3 including scarification and removal of undesirable matter suitable approved material to the level of original ground or to the
and compacting of replaced matter where necessary. top level of any adjacent embankment; and disposal of all surplus or
unsuitable excavated material, all as shown on the Drawings, or as
3 Drainage blanket shall be measured by cubic meters of
directed by the Engineer.
aggregate materials, furnished, screened, washed, placed, spread,
compacted, completed and accepted. Measurement shall be of 2 The work also includes removal of those portions of existing
volumes computed from the cross sections shown on the Drawings structures below ground which would in any way obstruct or
(and of the field measurements of area) and compacted depth of each interfere with construction of new structures.
trial section. No allowance shall be made in the measurement for 3 The Contractor will be deemed to have satisfied himself, at the
overdepth and/or overwidth construction, regardless of the time of tendering, as to the type and nature of soils and rock that will
Engineer’s permission for it to remain in place. be encountered in structural excavations.
4 Sub-grade construction on sabkha or gypsum-rich soils shall
be measured by cu.m. of top width of sub-grade layer computed 2.7.2 Excavation
from the cross sections shown on the Drawings The rates shall
2.7.2.1 General
include for all excavation below top of sub-grade, as per the
thicknesses and material specified under Item 2.6.3.1.3 including 1 The Contractor shall notify the Engineer a sufficient time in
scarification and removal of undesirable matter, construction of advance of the beginning of any excavation for structures so that the
temporary haul roads, any rockfill, geotextile or geo-synthetics used, Engineer may, where necessary, survey and record the cross
surcharge materials, compaction and completion and any accessories sectional or longitudinal elevations and measurements of the existing
all as specified in Paragraph 2.6.3.6 and as shown on the relevant ground and existing structures affected by the proposed structure.
drawings. Any materials removed or excavated before these measurements
5 Sub-grade construction on top of dune sand shall be measured have been taken and approved by the Engineer will not be paid for.
by cu.m. of top width of sub-grade layer computed from cross 2 The Contractor shall be responsible for the safety of all
sections shown on the Drawings. The rates shall include for all foundation and trench excavations whether supported or not.
excavation below top of sub-grade, as per the thicknesses and Approval of the Contractor's support system or omission of a support
material specified under Item 2.6.3.1.3 including scarification and system for any excavations will not absolve the Contractor from his
removal of undesirable matter, installation and dismantling of the sole responsibility in this regard.
confinement structure or side embankment and compacting the soil 3 The Contractor shall take all necessary precautions, including
layers as specified. shoring or other means, to protect employees and others in the
excavation and on the ground above.
2.6.5 Basis of Payment 4 The sides of all foundation pits and trenches shallower than
1 The amount of completed and accepted work, measured as 1.5m shall be vertical and adequately supported unless otherwise
provided for above, will be paid for at the unit rates for the relevant shown on the Drawings. Sides more than 1.5 m in depth shall be
items in the Bill of Quantities , which rate shall be full compensation sloped at a stable slope or supported in an approved manner unless
for supplying materials, transporting, hauling and placing, for labor, the material through which the pit or trench is cut is deemed to be
equipment, tools and other items necessary for the proper completion sufficiently self-supporting and not requiring support.
of the work. 5 Pits and trenches shall be kept free from water until footing
concrete has been placed or pipes have been installed. The
2.6.6 Items in the Bill of Quantities Contractor shall minimize, as far as practicable, the length of time
excavated areas are open. The Contractor shall be responsible for
i. Sub-grade preparation in cut (cu.m.)
repair of damage due to weather, equipment, and other causes during
ii. Drainage blanket (cu.m.)
periods when the excavations are left open.
iii. Preparation of sub-grade construction
on sabkha or gypsum-rich soils (cu.m.) 6 The Contractor shall plan the Works so that no excavation is
iv. Preparation of sub-grade construction left in an exposed condition for a period greater than 30 days unless
on top of dune sand (cu.m.) otherwise approved.
7 Where excavation is adjacent to public highways and
2.7 Excavation and Backfilling for walkways, warning lights, barriers and barricades shall be provided
to the Engineer’s satisfaction. No excavation shall be left in an
Structures
exposed condition for more than 7 days unless otherwise approved.

2.7.1 Description 8 For excavation in material sensitive to moisture (stiff clays,


marls, etc.) the excavation shall be cleaned and a concrete blinding
1 This Sub-section describes excavation in any material for layer cast immediately on completion of the excavation.
buildings and pump houses; bridges, culverts, pipe culverts, under-
drains; drainage and utility structures; flood areas cut-off-walls;

2-14
9 The Contractor shall notify the Engineer of any sign of failure 9 If temporary works are required for maintaining the excavation
or cracks within or around the excavation immediately when such dry, the Contractor shall be responsible for the design and execution
signs are noticed. of the works. The proposed design shall be submitted to the Engineer
for approval but, such approval shall not relieve the Contractor of his
2.7.2.2 Temporary Support System sole responsibility in this regard.

1 When a temporary support system is required to protect 2.7.2.4 Excavation for Box Culverts, Pipe Culverts and
adjacent property or to protect the public during construction, the Miscellaneous Structures
Contractor's design for such support system shall be submitted for
approval prior to commencing its construction. 1 Excavation shall be carried out to the limits required for
2 All temporary support systems shall be designed with adequate construction and to the depth required for bedding material or
factors of safety to serve with minimal maintenance, for the duration removal of unsuitable material. All trench excavation shall proceed
of its intended use, and shall include adequate safety provisions to upgrade, commencing at the downstream end.
protect the public from construction activities. 2 Foundation material supporting the bedding or structure shall
3 Notwithstanding any approval of temporary support systems, be AASHTO M 145 Class A-1-a, A-1-b or A-2-4 compacted to 95%
the Contractor shall be solely responsible for the adequacy of their AASHTO T 180 maximum density. If the natural material does not
design and construction and for maintenance and all necessary safety meet the classification requirements, it shall be sub-excavated to a
precautions associated therewith. depth of at least 200mm and replaced with material meeting the
specified requirements. Any rock or hard material within 200 mm of
2.7.2.3 Excavation for Major Structures and Bridges the bottom of the pipes shall be similarly sub-excavated and replaced
with material meeting the specified requirements.
1 Foundations for buildings, pump houses and other major
structures and bridges, shall be excavated in accordance with the 3 If no special bedding material is required, the foundation for
dimensions as shown on the Drawings and shall be of sufficient size precast and prefabricated culverts shall be formed to the shape of the
to permit placing of the full width and lengths of the footings. culvert, including all protrusions. The shaping shall extend to 25%
of the height of culvert.
2 Excavation shall be carried down to the levels shown on the
Drawings or as established by the Engineer based on previous 4 Where rock is encountered in the toe wall excavation for
investigations. No concrete shall be placed prior to approval of the concrete box culverts or concrete cut-off-walls for floodway,
excavation pit. embankment protection and pipe culverts and the rock is of such
quality as will prevent erosion, part of the toe wall may be eliminated
3 Unless shown otherwise on the Drawings, the bottom of all
in the rock strata as directed and the toe wall shall be keyed into the
excavations shall be covered with a 75mm minimum depth of lean
rock strata in a satisfactory manner. The minimum thickness of the
(blinding) concrete Class 15 to serve as a working platform.
key shall be as shown on Drawings or as instructed by the Engineer.
4 Foundation pits or trenches shall be of sufficient size and
5 Precast concrete pipes and metal pipes shall be installed in
provide minimum sufficient working space to permit construction of
trenches cut into previously constructed and compacted embankment
structures or structure footings of the full width and length shown on
or from top of sub-grade. Unless otherwise shown on the Drawings,
the Drawings.
trench width shall not be greater than the external diameter of the
5 Where footings are constructed using formwork, the pipe plus 500 mm on each side.
excavations shall generally not extend more than 500 mm beyond the
6 In the case of metal pipes, the bottom of the trench shall be
maximum dimension on each side of the proposed footing unless
shaped to a template so that at least 10% of the overall height of pipe
additional working space is clearly required and approved by the
or arch will be in contact with the bottom of the trench as excavated.
Engineer. Any unauthorized overwidth of excavation beyond the
Recesses shall be excavated to receive any parts of the pipe which
lateral limits or depths shown on the drawings or approved by the
extend below the outside perimeter. Where rock, hardpan or other
Engineer shall be backfilled with selected fill or lean concrete as
unyielding material is encountered it shall be removed below design
directed by the Engineer at the Contractor’s expense.
grade or as ordered by the Engineer for a depth of at least 200 mm
6 Where footings are located, in or adjacent to firm, original and backfilled as specified.
ground and where formwork is not required or ordered, any
7 Trenches for cast in-situ pipes shall be cut into previously
unauthorized overdepth excavation below the approved elevation of
constructed and compacted embankment from top of sub-grade or
base of footing shall be backfilled with blinding concrete.
embankment height or twice the nominal span of the pipe whichever
7 Where excavation to rock foundation is required, the is less. Trench width shall not be greater than the external diameter
excavation shall proceed in such a manner as to allow the solid rock or span of pipe plus 500 mm on each side when external forms are
to be exposed and prepared in horizontal beds or properly serrated used, or the external span of pipe including protection plus 100 mm
for receiving the concrete. All loose and disintegrated rock and thin on each side when external forms are not used.
strata shall be removed.
8 When excavation is required for installation of ducts, the
8 When unstable material or other unsuitable material is Contractor shall notify the Engineer upon completion of the
encountered below foundation elevation, the Contractor shall excavation. No duct shall be laid until the depth and cross section of
excavate such material and replace it with suitable backfill material the excavation has been approved.
or concrete to the depth as directed by the Engineer.
9 Over-width or over-depth excavation for precast concrete
pipes shall be made good at the Contractor's expense by provision of

2-15
an in situ concrete cradle or increased thickness of concrete bedding ASTM Standard
Percentage Passing Size
as directed, or by the use of other approved suitable materials. Sieve Size
10 Over width excavation for in situ concrete pipes shall be made 3/8" 100
good at the Contractor's expense by concrete bedding brought up to
No. 4 < 85
the external haunch of the pipe or by the use of other approved
suitable materials. No. 30 < 45
11 Over depth excavation for metal pipes shall be made well by
No. 200 <5
furnishing and backfilling an approved, fine granular material
containing not more than 0.5% of combined chlorides and sulfates. Table 2.7.3.2: Requirements for Open Graded Backfill -
Gradation
2.7.3 Backfilling
Such material may be deposited below the standing water level
2.7.3.1 General without compaction. Above the water level normal laying and
1 The Contractor shall obtain approval for his proposed method compaction will be considered.
and rate of placing of backfill before work commences. 8 Additional water to be added during placement of backfill
2 Backfill materials shall be uniformly graded granular material, material to achieve required compaction shall be fresh water or
capable of being compacted to required compaction, and having brackish water approved by the Engineer.
adequate permeability to permit free drainage through it. Backfill 9 Minimum tests required during backfilling operations to verify
material shall also conform to the requirements listed in Table material are:
2.7.3.1 below: - One Proctor test for each structure.
- One gradation of materials when materials changed.
Surface Requirements - One plasticity index and field density for 50% of the
Minimum D10 value 1 mm layers and for each footing and abutment as instructed
by the Engineer.
Maximum Plasticity Index 10 per cent
2.7.3.2 Backfilling for Box Culverts, Pipe Culverts, Bridge and
Requirements for bridges, culverts etc. shall be as specified in Building Foundations, Walls, Abutments and
subsequent sections
Miscellaneous Structures
Table 2.7.3.1: Requirements for Backfill Materials
1 Structures shall not be subject to the pressures of backfilling or
3 Backfill material shall not be placed against any structure until to live loads until the 28-day strength of the concrete has been
approval is given. Unless otherwise shown on the Drawings reached, unless a shorter period is approved in special circumstances
structures shall be backfilled to the same requirements as specified where the load is sufficiently small as not to constitute a risk of any
for the adjacent embankment. damage to the structure in the opinion of the Engineer. This period
4 Backfill shall be placed in level layers for the full width of the may be extended if subnormal curing conditions exist.
excavated area until the elevation of the original ground or 2 Backfill placed around culverts shall be deposited on both
surrounding embankment is reached. Backfill next to walls, between sides to approximately the same level at the same time. Special care
columns or in other confined areas, shall be compacted by approved shall be taken to prevent any wedging action against the structure
hand or portable equipment. and slopes bounding the excavation shall be stepped, where
5 Each successive layer of backfill shall contain only sufficient necessary, to prevent such wedge action occurring.
material to ensure proper compaction and in no case shall any layer 3 All backfill intended to support false workloads, including
be greater than 150 mm thickness (after compaction). The moisture temporary fills shall be selected to support the required load. As a
content of the backfill material shall be uniform and within the minimum, such material shall be AASHTO M 145, Class A-1-a, A-
moisture range designated. Backfill material shall be compacted to 1-b or A-2-4, compacted to 90% of the maximum density as
95% of the maximum density as determined by AASHTO T 180 determined by AASHTO T 180 (Method D).
(Method D).
4 Backfill around bridge and building foundations, abutment
6 Jetting of fills or other hydraulic methods involving or likely to walls and retaining walls shall be completed to the level of the
involve liquid or semi-liquid pressure will not be permitted. original ground line and to such heights above original ground line or
7 Water shall be drained from the areas to be backfilled to the levels as shown on the Drawings. Care shall be exercised to
wherever practicable. In cases where, in the opinion of the Engineer, prevent forward movement of the wall.
it is not practicable to drain the areas to be backfilled, the initial 5 Unless shown otherwise on the Drawings, when special
backfill material shall consist of crushed, open graded material permeable backfill (sheathing) is to be placed against the back faces
conforming to the gradation given in Table 2.7.3.2 below: of retaining walls or wing walls, it shall consist of a continuous
covering of approved type proprietary filter cloth protected by a
continuous wall of 200mm minimum thickness precast, porous (no-
fines) concrete blocks laid with dry joints. Prior to construction of
the block wall, ensure that all underdrains or perforated pipes are laid

2-16
along the base of the wall under the sheathing, as shown on the 2 Structural excavation is measured by cubic meter of material
Drawings. excavated for the major structures hauled away and disposed of as
directed, or stockpiled. Measurement of structural excavation shall
6 Backfill material for culverts, pipe culverts and miscellaneous
be from original ground levels or ground levels after removal of all
structures within 300 mm of any part of the structure shall be Class
unclassified highway excavation. Limits shall not be greater than
A-1-a, A-1-b or A-2-4. The 200 mm minimum thickness of sub-
vertical planes 500 mm from the maximum dimension, on each side
grade layer shall consist of approved sub-grade material placed and
of the footing or other controlling portion of the structure. Where
compacted to 100% maximum density as specified under Sub-
structures are constructed against natural ground or rock, excavation
section 2.6 – ‘Sub-grade Construction’. The backfill shall be
limits shall be the dimensions of the structure as shown on the
completed to the level of the original ground or to the top elevation
Drawings. Bottom limits shall be the ordered foundation levels. Only
of any adjacent embankment.
material excavated from its original position shall be measured for
7 Backfilling around and over pipe culverts shall not commence payment. No measurements shall be made of structural excavation in
until headwalls and wingwalls have been constructed and attained embankments previously constructed by the Contractor.
the specified 28-day strength.
3 Additional excavation in unstable material or other unsuitable
8 Water used for compaction of backfill around metal pipes and material encountered below foundation level shall be measured as
reinforced concrete structures shall be from an approved source and part of the unclassified structural excavation.
shall not contain more than 0.5% combined chlorides and sulphates
4 Structural Excavation under Water shall be measured by cu.m.
nor contain other potentially harmful minerals.
of material excavated for the major structures, hauled away and
9 When pipes or other structures temporarily extend above the disposed of as directed, or stockpiled on or in the vicinity of the
grade of the partially constructed embankment, the Contractor shall Works, and the excavated areas backfilled, completed and accepted.
construct the fill over the structure of sufficient depth to protect the
5 Unauthorized overdepth and overwidth excavation in soil and
structure from any damage resulting from construction or other
rock and the backfill material including blinding concrete required in
traffic.
such cases, shall not be measured for direct payment, but shall be
10 The Contractor shall complete the backfill around box culverts considered as subsidiary work the costs of which will be deemed to
to the level of the original ground line and to the full width of be included in the rates for structural excavation.
excavation area. If the top of culvert extends above the original
6 Structural excavation in any material or under water for box
ground line the Contractor shall continue the backfill to the top of
culverts less than one sq.m. in external cross section, and structural
culvert and for a width of 3 m on each side of the culvert for the full
excavation for pipe culverts, underdrains (subsoil drains), pits,
width of roadway embankment. If the embankment is in place at the
catchbasins, manholes, inlets, energy dissipaters, slope protection,
time of backfilling, the Contractor shall backfill around the culvert to
fence posts, guardrail posts, lighting columns, sign posts, signal
the top of embankment.
supports and all other minor structures, shall not be measured for
11 Backfill around pipe culverts shall be completed to the level of direct payment, but shall be considered as subsidiary work the costs
original ground line and to the full width of excavation area. If the of which will be deemed to be included in the rates and prices for the
top of the culvert extends above the original ground line the relevant items.
Contractor shall continue the backfill to the top of culvert for a width
7 Unless specified otherwise in the special specifications,
of 1.5 times the maximum external width of the culvert on each side
temporary cofferdams, temporary support system, bailing, drainage,
of the culvert centerline to the full width of the roadway
dewatering, pumping, sheeting, concrete blinding layers and all other
embankment. If the embankment is in place at the time of
Temporary Works shall not be measured for direct payment, but
backfilling, the Contractor shall backfill around the culvert to the top
shall be considered as subsidiary work the costs of which will be
of culvert or as shown on the Drawings.
deemed to be included in the rates for structural excavation.
12 Any existing roadway pavement cut through, damaged or
8 Backfilling to structural excavation shall not be measured
removed during excavation for pipe culvert installation shall be
separately but is considered as subsidiary work the cost of which are
reinstated, after pipe installation and trench backfilling, using
deemed to be included in the rates for structural excavation.
approved base and surfacing course materials at least equivalent to
those in the original pavement. Materials and construction shall 9 Any blinding concrete used at the bottom of excavations, as
conform to the relevant requirements Sections 3 and 4 of this shown on the Drawings or as instructed by the Engineer shall be
specification. measured and paid for in accordance with the relevant method of
measurement under Clause 5.1.5 of Section 5 ‘Concrete and
13 Miscellaneous structures other than pipe culverts shall be
Concrete Structures’.
backfilled in accordance with the methods specified. Compaction of
backfill when structures are outside the roadway right-of-way or in
2.7.5 Basis of Payment
approach roads, minor roads or similar areas, shall be to 90% of
maximum density as determined by AASHTO T 180 (Method D). 1 The amount of completed and accepted work, measured as
provided for above, will be paid for at the unit rates for the various
2.7.4 Method of Measurement items in the Bill of Quantities , which rate shall be full compensation
for equipment, tools, labor, materials, transporting, hauling, placing,
1 All structural excavation, of whatever type, shall be measured
and for other items necessary for the proper completion of the work.
as ‘unclassified’ which shall be deemed to include all materials
encountered of any nature, including silts, clays, sand, gravel and
granular materials and fractured, jointed and solid rock.

2-17
2.8.3 Construction Requirements
2.7.6 Items in the Bill of Quantities
2.8.3.1 Excavation for Pipe Trenches
i. Unclassified structural excavation
1 The Contractor shall not commence excavation of any section
(Depth 0 to 2m) (cu.m.)
of work until a full supply of pipes and fittings is available for that
ii. Unclassified structural excavation section.
(2m < Depth  4m) (cu.m.) 2 During excavation, material suitable for backfilling shall be
iii. Unclassified structural excavation piled at sufficient distance from the sides of the trench as to avoid
(Depth > 4m) (cu.m.) overloading and prevent cave in. All excavated material not required,
iv. Unclassified structural excavation or unsuitable for backfilling shall be removed and carted away to an
approved dumping area.
(under water) (cu.m.)
3 Trenches shall be excavated to such depths as will permit the
pipes to be laid at elevations, slopes or depths of cover indicated on
the drawings, and at uniform slopes between indicated elevations.
2.8 EARTHWORK FOR PIPE
4 Where excavation depth exceeds the level indicated on the
TRENCHES
drawings and is not authorized in writing by the Engineer, the
Contractor shall place backfill or concrete to the required bottom
2.8.1 Description
level, as instructed by the Engineer, all at his own expense.
1 This Sub-section describes requirements for excavation of 5 Trenches shall be excavated with vertical sides between the
trenches in any material for water supply, sewage, stormwater bottom level and 300 mm above the top of the pipe.
drainage including pipe culverts and irrigation pipes, and all other
6 Trench width up to 300 mm above the crown of the pipe shall
associated works, including all necessary clearing and grubbing,
not exceed the following:
bailing, draining, shoring, planking, strutting and supporting the
i. For pipes not exceeding 65 mm diameter: Nominal
sides of excavation. The work includes backfilling with suitable
diameter plus 300 mm.
approved material and disposal of the excess material to designated
ii. For pipes over 65 mm and not exceeding 600 mm
and approved tip locations.
diameter: Nominal diameter + 600 mm.
iii. For pipes over 600 mm diameter: Nominal diameter +
2.8.2 Materials 1000 mm.
7 Where the above specified trench widths are exceeded; the
2.8.2.1 Backfill Material
Contractor shall provide additional pipe protection or pipes of
1 Initial backfill (up to 300 mm above the top of the pipe) shall increased strength if the Engineer calls for such measures, all at his
be selected fill, sand or other approved material and shall conform to own expense.
the following: 8 Excavation of trenches with battered sides will not be
ASTM permitted within 4m of any building or other structure.
Percent by Weight Percent by
Standard 9 When the pipes are to be laid in embankments or other fill
Passing for Pipes other Weight Passing
Sieve Size areas, the embankment or fill area shall first be filled and compacted
than uPVC for uPVC Pipes
(mm)
as specified to the proposed finished grade or to a height of at least
19 100 - 300 mm above the top of pipe whichever is lower. The trench shall
4.76 25 – 100 100 then be excavated as in undisturbed material.
10 When pipes are to be laid under existing pavements, trenches
1.19 10 – 75 25 – 75
shall be excavated carefully and to minimum widths. Methods that
0.354 5 – 30 10 – 30 will give straight and vertical face shall be used. The pavement shall
be kept at its original level and condition.
0.177 3 – 10 3 – 10
11 In combined trenches where one pipe is at a lower level than
0.075 0–5 0–5 an adjacent pipe the following shall be applied:
i. The whole trench shall have a depth related to the lower
Table 2.8.2-1: Requirements for Initial Backfill - Gradation pipe and the thickness of the bedding shall be increased
to the upper pipe as necessary.
2 For GRP pipes, graded crushed stone 2.83-8 mm shall be used
ii. The lower pipe shall be backfilled with thoroughly
for initial backfilling.
compacted granular material up to a level of 0.30
3 The remainder of the trench shall be backfilled with suitable meters above the higher pipe.
material either from material removed in the course of excavating the
trench, or imported from approved borrow pit. In either case the 12 Final excavation to the correct grade level for trench beds shall
backfill material shall be non-plastic. The percentage by weight be carried out immediately before laying beds or pipes. Unstable
passing a No. 200 (0.075 mm) sieve shall not exceed 15%. The material, rock projections, boulders and hard spots shall be removed
percentage passing a 63 mm sieve shall be 100. and replaced with approved filling material, that will be compacted

2-18
as instructed. Local soft spots shall be compacted by tamping in 4 Surface grading shall be carried out to restore all un-surfaced
bedding material. areas and any adjoining areas disturbed to provide a level, smooth
13 The bottoms of trenches shall be accurately graded to provide surface.
uniform bearing and support for the bottom quadrant of each section 5 The Contractor shall proceed with restoration of surfaces as
of the pipe. Bell holes shall be excavated to the necessary size at soon after completion of other work as is practicable, but in no case
each joint or coupling to eliminate point bearing. Any material that more than 10 days after backfilling of trenches and other excavated
may cause point bearing shall be removed. areas. Restoration shall be completed within 20 days from the start of
14 The Contractor shall report to the Engineer any unsuitable or restoration.
weak ground material that may be found below the indicated
excavation levels before executing any trimming of the excavation, 2.8.4 Method of Measurement
pipe laying, concreting, or other work. Where, in the judgment of the 1 Trench excavation and backfill shall be paid for per cu.m.
Engineer the bottom of the trench is unsuitable, such material shall measured in horizontal layers for the different depth categories
be removed to the width and depth ordered by the Engineer. The shown in the Bill of Quantities. Trench length shall be measured
trench shall then be made up by backfilling with approved material. between outer surfaces of manholes or chambers. Trench width shall
15 Where rock is encountered, the trench shall be excavated to be as specified or shown on Drawings. Depth of excavation shall be
150 mm below bed level and replaced with granular material, the depth of every horizontal layer. Excavation for bedding is
concrete, or blinding grade as directed. included as trench excavation.
2 Rates for trench excavation and backfill shall include for:
2.8.3.2 Backfilling i. Excavating in any material encountered including rock.
ii. Blasting, barring, wedging or other quarrying methods
1 Trenches shall not be backfilled at joints until after that section
for rock excavation.
of the pipeline has successfully passed the specified tests.
iii. Excavation at any level.
Initial backfill or surround up to a level of 300 mm above top of the iv. Excavating curved on plan.
pipe, shall be placed and hand compacted in 150 mm layers. The v. Allowance for working space.
backfill shall be brought up evenly on both sides of the pipe for the vi. Increase in bulk for excavating.
full length of the pipe. Care shall be taken to ensure thorough vii. Excavating below water table and dewatering as
compaction of the fill under the haunches of the pipe. necessary.
2 Suitable backfill shall be placed and well compacted in layers viii. Keeping excavations free from water.
not exceeding 150 mm thick after compaction. Heavy compactors ix. Leveling, compacting, trimming and grading bottoms
shall not be used until there is 600 mm cover over pipes. and trimming sides and bottoms of excavation.
3 Unless otherwise specified each layer shall be compacted to at x. Supporting the sides of excavation.
least 95% maximum density for cohesionless soils and 90% xi. Filling with material as specified and compacting
maximum density for cohesive soils. around pipes and beds multiple handling of excavated
material and excavation from borrows and transporting
4 Backfilling trenches for pipes with concrete beds and or
about the Site.
surrounds shall not start before 24 hours after placing concrete.
xii. Segregation of the various classes of excavated spoil
Heavy compactors shall not be used and traffic shall not be allowed
and stock piling as may be directed by the Engineer.
before the elapse of 72 hours after placing the concrete.
xiii. Disposal of surplus excavated material including
5 When the backfill material is too wet from rain or excessive depositing and consolidating where directed on Site or
application of water, no compaction shall be done. In this case the removing from Site and depositing at a tip to be
work shall be suspended until the previously placed and new provided and paid for by the Contractor.
materials have dried sufficiently to permit proper compaction. Other xiv. Pipe bedding, initial backfill or gravel, and final
measures shall be taken if necessary to obtain proper compaction. backfill.
6 Temporary crossing are to be provided over trenches to xv. Filling over-excavation with material as specified
prevent construction traffic damaging pipes after backfilling. xvi. Consolidation of primary backfill (initial backfill)
material using water or hand tamping.
2.8.3.3 Restoration of Surfaces xvii. Compaction of secondary backfill (main backfill)
1 Restoration of asphalt, concrete, gravel pavements and the material.
likes shall be of materials and thickness to match the existing xviii. Reinstatement of unpaved surfaces. (Reinstatement of
pavement. Materials and workmanship shall be in accordance with paved surfaces shall be made and paid for according to
local authority requirements and as directed by the Engineer. Sections 4 or 12 as appropriate)

2 Restoration of pavement shall be done according to the


2.8.5 Basis of Payment
existing pavement quality and level to ensure that new pavement
matches the existing to provide uniform surface with the existing 1 The amount of completed and accepted work, measured as
profile. provided for above, will be paid for at the unit rates for the various
3 Grassed areas shall be restored by spreading approved fertile items in the Bill of Quantities, which rate shall be full compensation
soil over affected area after backfilling. Seeding, fertilizers and water for equipment, tools, labor, materials, transporting, hauling, placing,
shall be applied until grass is restored to its former condition. and for other items necessary for the proper completion of the work.

2-19
2.8.6 Items in the Bill of Quantities
i. Trench excavation and backfilling
(Depth from 0 to 2m) cu.m.
ii Trench excavation and backfilling
(2m < Depth  3m) cu.m.
iii Trench excavation and backfilling
(3m < Depth  4m) cu.m.
iv Trench excavation and backfilling
(Depth > 4m) cu.m.
v. Trench excavation and backfilling
(under water) cu.m.

2-20

You might also like