Professional Documents
Culture Documents
Lec13-Tunneling in Difficult Ground - PDF Version 1
Lec13-Tunneling in Difficult Ground - PDF Version 1
by
Dr. Muhammad Zubair Abu Bakar
Introduction
• Tunneling in difficult ground could mean any tunneling where it is difficult
simply because you are not using the proper method for that particular
type of ground.
• But what is important is to find the most economical and safest way to
tunnel through it.
Ground Preconditioning Techniques
There are numerous methods to precondition the difficult
ground before you ever try to tunnel through it.
• Dewatering the area;
• ‚Freezing the ground mass;
• ‚Compensation grouting;
• ‚Permeability grouting;
• ‚Vertical jet grouting;
• ‚Umbrella Methods;
Drilling and grouting;
Horizontal Jet grouting;
Concreted Pilot Tunnels;
Pipe Jacking;
Driving a series of small lined or concreted tunnel around what will become
the new opening.
Driving small drifts in the area of the perimeter of the future opening and
prestressing the zone, which will minimize the roof tension in a large chamber.
• A few very basic rules of ground control laid down by Dr. John
Reed, considered as the “father of practical rock mechanics” in the
U.S.A.
– If you know that the ground is going to be very difficult to tunnel
through and you have a chance to stabilize it in some way before
opening the ground, while it is still in an equilibrium condition, do it;
– ‚ Do what ever you can to keep the heavy ground intact and from
moving, even slightly when you open it;
– ‚ Try to find ways to reinforce the rock and still use the strength of the
rock in place as much as you can (Remember, reinforced rock will
probably be stronger than any steel and concrete that you can put under
it.);
– ‚ Get the reinforcing in place before you make the opening if you can: if
not get it in place as soon as possible after you make the opening.
• Tunnel in a mixed layers of fill material from beds of clay, silt, sand and
gravel, only about 65 feet below the surface, in Hannover, Germany.
• Two twin tunnels were driven that were very close to each other, but one
was kept slightly behind the other.
• They would work at drilling out their freeze pipe holes, placing the pipes (42
m long), and then freezing one tunnel. Then when it was frozen using their
650 kW plant pumping -40°C brine, they would move over to the other
tunnel, and freeze it.
• Meanwhile in the previously frozen tunnel, they excavated it with a backhoe
type loader. They placed shotcrete directly onto the frozen ground,
probably using air entrained shotcrete.
• The length of the tunnel that had to be frozen was 251 m, and the volume
of frozen ground 3600 m³. To drill the pipe freezing holes, they had to
widen out the last part of their tunnel in order to have room to drill the
next round of holes parallel to the new tunnel to be frozen.
• Finally an inner lining of water tight concrete was placed completely around
the tunnel, on top of a PE (polyethylene) film.
Case Studies: (Harvey, S., 1988, Ground Freezing, The
First Option, World Tunnelling, Dec., pp. 327-328.)
• A 2.44 m tunnel being driven beneath the River Medway in
Kent, England intersected and unforeseen sand and shell filled
fissure, saturated with and recharged with water from the tidal
estuary approximately 1 km away.
• Obviously it was impossible to dewater. Treatment of this
fissure was carried out from the face by drilling a series of radial
freeze holes fanned out to form a cone shape.
• Liquid nitrogen was used as the refrigerant and was delivered
to the face in rail-mounted containers. The exhaust gases were
collected and vented to the atmosphere by separate vent
columns. Tunneling through the fissure was then completed
without further incident.
• The Du Toitskloof road tunnel in South Africa had a
cross-sectional area of 121 m² constructed through
decomposed granite.
• A number of previous attempts with much smaller
tunnel resulted in mud runs causing serious delays
and abandonment. The use of ground freezing
allowed the tunnel to be constructed full size
without incident.
• At Runcorn near Manchester, England, two 3m dia. Tunnels
were required to link a newly- built 9 m dia. secant piled
access chamber to ancient shafts of brick and cast iron some
13 m away. They were constructed within purpose designed
horizontal cylinders of frozen ground.
• Compaction Grouting
• Fracture Grouting
• Pressure Filtration/Intrusion Grouting
Compaction Grouting
• Injection of stiff, high viscosity grout into the ground
which in general will form an approximately
spherical bulb.
• This causes densification (or recompaction) of the
surrounding ground and displacements to
compensate for the settlements occurring below
the point of injection.
• Normally a cement based grout is used with
sufficient silt sizes to provide plasticity together
with sand sizes to develop friction.
• The grout does not generally enter soil pores but
remains in a homogenous mass.
Fracture Grouting
• Injection of low viscosity grout at pressures
sufficient to split open the ground and form fissure
planes along which the grout flows.
• This is normally undertaken in clay soils.
• Injection volumes have to be strictly limited such
that the extent of the grouting effect can be
controlled.
• Involves penetration of grout over comparatively
greater distances; it may generate pore pressures in
the clay which dissipate with time (Undrained).
Pressure Filtration/Intrusion Grouting
• The injection of a fluid grout with a high solids
content.
• The grout is designed to bleed rapidly so that the
solids are deposited close to the point of injection
and water is lost into the surrounding ground
(Drained Process).
• The technique is applicable to granular soils which
have sufficient permeability to allow the grout to
bleed.
Advantages
• In fracture and
intrusion grouting the
grout is relatively fluid
and can be injected
through sleeved grout
tubes known as tubes a
manchette (TAMs).
• In case of compaction
grouting, the grout is
usually too viscous to
be injected through the
small holes of a TAM
and therefore larger
diameter grout tubes
need to be installed in Rubber sleeves (manchettes) cover each injection
port and serve as one-way valves that open during
the ground. injection and collapse onto the ports after injection
Case Study (Wallis, Shani, Paris Metro, World Tunnelling,
Oct., pp. 325-330.)
• For tunnels under the City of Paris, the ground was
apparently very weak and need consolidation grouting.
• They did not report the dimensions of the opening, but
stated that for removing 17,500m³, they pumped
13,500 m³ of cement and chemical grout, through
83,000 m of injection drill holes.
• Then they used 7,500 linear m of Swellex bolts and
1300 m³ of shotcrete. After all this was done from two
small (what appears to be about 18 feet wide) tunnels,
The remaining portion of the station chamber was
excavated.
Case Study: (Mair, R. and D. Hight, 1994, Compensation
Grouting, World Tunnelling, Nov., pp. 361-365.)
Permeability Grouting
• This is where you are grouting to reduce the
permeability of the material that you want to
tunnel through to shut off the water. This is by far
the most common grouting method.
• In soil, sealing grouting can be used, for example, to
form an impervious blanket above a compressed air
tunnel drive to prevent blowouts reaching the
surface.
• Waterproofing of the entire x-section of the future
tunnel can also be carried out by high-pressure or
jet grouting from surface.
Vertical Jet Grouting
• When you have a very weak, or unconsolidated
material that will probably run when you put an
opening in it, and you want to drive a tunnel through it,
the Vertical Jet grouting may be the answer.
• When jet grouting is done horizontally, it then is
classified as umbrella “jet spiling”, but it is still the same
idea.
• Vertical Jet grouting entails drilling holes from the
surface (or another level) to give you complete
coverage of the area that you will be tunneling through,
considering that the jet grouted columns will be about
6 feet in diameter, and they must overlap like a honey
comb.
• First the hole is drilled, then the jet starts injecting,
and in some cases mixing the grout with the
material, in other cases, it removes it completely
and replaces it with grout. In all cases, you end up
with strong column of cement grout that stand side
by side, and form a solid block of concrete to tunnel
through.
Three types of Jet Grout injectors
Case Study: (Burke, Jack, Success at Islais Creek, 1995, World
Tunnelling, Jun., pp N9-N14.)
• This project was done within San Francisco on the eastern side
of the peninsula. At one time before the 1900's, this area was
under water. Over the years it become a land fill/garbage dump
and was then covered with decent land fill. The City lined out a
transport sewer through this area.
• When a geotechnical investigation was done, they found out
that there was artificial loose sand and rock, rubbish, organic
garbage, old piles and even sunken ships to tunnel through.
• In addition, the natural bay mud, which is a plastic silty clay.
The answer was to use vertical jet grouting and excavate the
tunnel with a roadheader shield. The extensive jet grouting is
shown in next slide. The tunnel was then cut by a
roadheader/shield.
Umbrella Methods
• As you know story about the Conway fault in
Viburnum, the umbrella method must have
something to do with putting some sort of a stable
umbrella over the area where you need to drive a
tunnel.
• Also, very similarly, we saw earlier that compaction
grouting can form an umbrella over an area where
you will drive a tunnel, but that doesn’t add the
strength to the ground as much as the methods
that we will discuss now.
Drilling and Grouting
• The method of drilling holes into the ground and leaving the
drill steel in place, and then grouting through the drill steel has
now become common practice in many civil projects. There is
also a system of Grouted Spile Anchor which is illustrated in
next slide.
• This system is a forepoling system for soft to medium hard
ground where spiles (anchors) are placed above and around the
next round to be excavated. In this case however, the system
has a special anchor rod which replaces the perforated boring
tube which is used to bore the hole and inject the grout.
Horizontal Jet Grouting (Sometimes called Jet Piling)
• Just as you can drill and perform jet grouting vertically, you can do a
similar thing horizontally.
• In the case of horizontal jet grouting, the diameter is usually more in
the range of 18 to 24 inches in diameter, rather than 48 to 60 inches.
• A complete umbrella arch must form above where you are going to
drive the tunnel. Sometime in shallow areas, or close to or as part of
the portals, a combination of horizontal and vertical jet grouting is
done.
• Also, if the top excavation is protected by horizontal jet grouting,
which will be followed by bottom excavation that also needs
protection, then within the tunnel vertical jet grouting along the
floor/rib line jet grouting can be done.
Concreted Pilot Tunnels
• This is still another more extensive system of
developing an umbrella over, in these cases very large
tunnels or chambers.
• This particular job was a part of the French Channel
Tunnel where they had to develop a crossover chamber
180 m long, 26 m wide and 20 m high. While most of
the excavation was not in particularly bad ground
conditions (blue chalk marl) the shear size of the
chamber called for such an extensive concrete
structure.
• The longitudinal small tunnels, once filled with
compacted unreinforced concrete, interlocked to form
a complete arch. This arch is designed as the primary
lining of the completed chamber.
• This system of
building an umbrella
over a future
chamber was first
used at the Mount
Baker Ridge tunnel
construction job in
Seattle.
• In this case, a
complete 360° of 24
- 8.33 ft.dia. drifts
were driven and then
filled with concrete.
Thus forming a
complete concrete
shell, that could be
excavated without
causing subsidence.
Pipe Jacking (Pipe Roofing)
• The Korean and Japanese were clearly the developers of this system. It
normally is used to support an arch umbrella over the tunnel excavation.
This is fairly common practice in Germany as well as Korea and Japan.
• Usually when the
Germans use it, it is for a
fairly shallow and short
distance tunnel under a
railroad.
• Furthermore, when the
Germans have used it
according to the
literature, the pipes are
driven touching each
other, but they are not
interconnected.
• When the Koreans and
Japanese use, they have
pipes made up that
actually attach to each
other.
• When the Germans do
it, they seem to
“hammer” the pipes
into place, where as the
Asians seem to jack the
pipes into place.
Case Study: (Anonymous, 1995, “Rammed Pipe Roof Success”
World Tunnelling, Mar., p.50.)
• A new road was needed under a vital railroad
between Neustadt and Wurzburg. Normal
excavation or hydraulic thrust boring was estimated
at several million DM. Potsch, a very large
European contractor gave them a bid for
performing the excavation by a method of “Pipe
Roofing” that was 4 million DM less than the other
methods.
• The method used hydraulic pipe “Ramming
Hammers”. They proposed to install 44, 12.5 m
long pipes , 1220 mm in diameter, with a wall
thickness of 20 mm in a complete 360° circle .
• To avoid any deformation to the embankment, they
lined the entry and exit embankment with vertical
steel sheet piling. They used a 600mm diameter
Tarus Grundoram hammer, which applied 2000 t of
thrust. They pushed off of an I-beam arrangement
that was welded to the steel piling. They were able
to ram the pipes into place, taking 2-6 hours per
pipe.
• The steel piling inside the pipe was then cut and
pulled away and the tunnel then excavated. This
was followed by a road bed that was placed and
compacted within the tunnel at the desired grade
• Reading Assignments: