10.concrete Pour@LDPE Polymerization

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 5

Department JSA No.

       Civil Department   016


CONCRETE WORKS, CONCRETE POURING
  JSA Title
AT LDPE Polymerization Revision 01
 
 Minimum PPE’s “Safety Helmet, Safety Shoes, Safety Glass (dark &
clear glasses), Long sleeves shirt” & Ready to use working gloves. If
Personal Protective Equipment
necessary wear rubber boots, concrete apron, & rubber gloves.
Required
 
TASNEE PROJECT    

JOB SAFETY ANALYSIS   New JSA Revised JSA √X 28 September 2006


Check One Review Date
Revision #: 01
         
BASIC JOB STEPS   POTENTIAL HAZARDS RECOMMENDATIONS
A. PREPARATION / INSPECTIONS PROVIDE / ACQUIRE APPROVED METHOD
STATEMENT AND APPROVED JAB SAFETY ANALYSIS

1. Pre-Commencement Activities (QA-QC 1.1 Key Personnel falling into trenches/excavation, 1.1.1 Barricade the area
inspection prior to concrete pouring) form work, and rebar forms (slip, trip & fall). Falling 1.1.2 Ladder/access and access ramp must provide in
of workers on the access down to excavation. correct location in the excavated area and having clear
Heat Stress and Dehydration access when approaching to it. Appropriate stair steps
shall be provided for convenience to move.
1.1.3 Removal of all tripping hazards
1.1.4 Provide handrail (for stair access)
1.1.5 Provision of sufficient cool drinking water (include the
use of ice)
1.1.6 Provision of shaded rest places (HEAT STRESS
SHELTER)
1.1.7 Frequent breaks during extremely hot weather

General Instruction:
- No materials near excavation, and No blocking the
access route

1.2 No emergency access route due to poor 1.2.1 Provide access for all area of inspection and where
planning and no preparation (slip, trip, and fall) to pour concrete (cutting or bending of rebar to provide
access way; installing timber or planks to make a
connection between/into other area of inspection)
1.2.2 Provide working platform by placing planks into the
path of inspection and pouring.
1.2.3 Wood cup will provide for all rebar-end for protection
1.2.4 Provide Exit / Access Sign Board

B. AREA PREPARATION
1. Preparation of access way 1.1 (slip, trip & fall) 1.1.1 Barricade area of concrete pouring and provide area
for concrete pump.

1.2 Falling of workers on the access 1.2.1 Ladder/access must be fixed in the correct location
and having clear access when approaching to it.
Appropriate stair steps shall be provided for convenience
to move.
1.2.2 Removal of all tripping hazards
1.2.3 Provide handrail (for stair access)
1.2.4Provide access for all area of inspection and where to
pour concrete (cutting or bending of rebar to provide
access way; installing timber or planks to make a
connection between/into other area of concrete pouring
and in time of inspection) as per attached drawing
1.2.5 Provide working platform by placing planks into the
path of pouring.
1.2.6 Wood cup will provide for all rebar-end for protection

1.3 Heat Stress and Dehydration 1.3.1. Provision of sufficient cool drinking water (include
the use of ice)
1.3.2. Provision of shaded rest places (HEAT STRESS
SHELTER)
1.3.3. Frequent breaks during extremely hot weather

2. Transporting Concreting equipments to pouring 2.1 Falling equipment during transportation 2.1.1 Equipment to be secured onto the vehicle for
point area. transportation

2.2 Hitting/bumping of cargo truck while 2.2.1 Spotter/Banksman shall be position to control
maneuvering to get closer to unloading point. movement of equipment.

2.3 Riding (Passengers) on operating equipment 2.3.1 No passenger is allowed to ride outside the
equipment. Passengers can only be transported if there a
dedicated seat and seat belt provided

3. Shifting Concreting equipments within pouring 3.1 Workers tripping while moving concreting 3.1.1. Everyday TBT shall be conducted regarding the
area. equipment. daily activities
3.1.2. JSA’s should be implemented during daily TBT

B. PREPARATION AT POURING AREA

1. Using stair /ladder and access route entering 1.1 Falls from ladder while accessing / egressing 1.1.1 Ladder/access must be fixed in the correct location
down the pouring area. and having clear access when approaching to it.
Appropriate stair steps shall be provided for convenience
to move.
1.1.2 Removal of all tripping hazards
1.1.3 Provide handrail (for stair access)
1.1.4 Provide access for all area of inspection and where
to pour concrete (cutting or bending of rebar to provide
access way; installing timber or planks to make a
connection between/into other area of inspection)
1.1.5 Provide working platform by placing planks into the
path of inspection and pouring.
1.1.6 Wood cup will provide for all rebar-end for protection
(same comments –Site preparation 1.2.1)

C. TRAFFIC FLOW OF TRANSIT MIXER INSIDE C.1 Collision between truck mixers and other C.1.1 Flagmen and spotters shall manage much all of the
JOB SITE. moving equipment on site. time for traffic movement on concrete mixers to avoid
confusion of the drivers.
C.1.2 Drivers and Operators shall be well informed
regarding the route
C.1.3 Equipment Inspection is required/Daily checklist for
Trucks is necessary
C.1.4 Use of truck wheel stopper is required

C.2 Mechanical breakdowns on truck mixers while C.2.1 Safety Dept. shall define safe access/ route for the
inside jobsite causing obstruction movement of equipment during the concrete pouring
operation

C.3 Potential accidents/ injuries cause by vehicles/ C.2.2 Review and Re-route traffic flow. If necessary
equipment moving in congested area

D. SETTING UP CONCRETE PUMP D.1 Potential injuries to workers while deploying D.1.1 Provide barricade/ flagging around the equipment
the outriggers D.1.2 Flagmen/ Banksman shall control the area around
the concrete pump during concreting operations
D.1.3 Avoid outriggers near from the excavation (2 meters)
D.1.4 Large Mats to be deploy under the outrigger feet

E. OPENING UP BOOM PIPE OF CONCRETE E.1 Hitting of equipment, structures or even E.1.1ite Engineer and Pump Operator & his crew shall
PUMP workers while setting up pump. confer about safe position of the equipment and safety
matters before pouring.
E.1.2 Provide barricade/ flagging around the equipment
E.1.3 Flagmen/ Banks-man shall control the area around
the concrete pump during concreting operations
(same comments as D.1.1, D.1.2)

1. Pouring Concrete By Using Concrete Pump 1.1 Workers being struck by hose 1.1.1 Designate workers who are capable of handling the
hose
1.1.2 Experienced / skilled / trained workers shall be use
for the job
1.1.3 Use 2 (two) tag lines to keep under control the
hoses
1.2 Workers struck by concrete pump hose 1.2.1 Supervisor to ensure that the worker (s) designate to
control the hose do so at all times

1.3 Concrete debris striking workers while hose is 1.3.1 Cover/blind the end of pump hose before rotating the
being rotated concrete pump.
1.3.2 Supervisor to ensure all workers are clear of the area
while the hose is being rotate.

2. Movement of worker inside pouring area 2.1 Skin Irritation cause by cement toxicity 2.1.1 Wear Safety Rubber boots with steel toe, safety
(including group of workers handling the gloves, Long sleeves shirt, helmet (body cover or apron
portable handling machine) should be wore by pump hose holder)

2.2 Slipping resulting in injuries to feet and legs 2.2.1 Experienced / skilled / trained workers must to do the
job
2.2.2 Safety Awareness (placing Sign board “ watch your
step”) for additional alertness for all the active workers into
the location
2.2.3. Install planks for easy movements on other
areas

2.3 Back injury cause by improper lifting 2.3.1 Buddy-buddy system will be organized
2.3.2 Proper lifting will be imposed and advised by the
safety-in-charge

2.4 Environmental spill 2.4.1 Report all environmental spills to GAMA HSE Dept.
3. Workers doing the finishing and leveling of lean 2.4.2 Awareness Program regarding environmental safety
concrete
3.1 Slipping resulting in injuries to feet and legs 3.1.1 Wear Safety Rubber boots with steel toe, safety
(same comment as 2.2) gloves, Long sleeves shirt, helmet
3.1.2 Experienced / skilled / trained workers must to do the
job (same comments as 2.1.1, 2.1.2)

F. CLOSING CONCRETE PUMP F.1 Hand injury during closing of outrigger boom of F.1.2 Only concrete pumps operators or equivalent :
concrete pump. Experienced / skilled / trained workers must to do the job

G. CLEANING/WASHING CONCRETE PUMP G.1 Using pressurized water, indiscriminately, G.1.1 Cleaning shall be done in the designated area.
causes Eye Injuries G.1.2 Concrete pump operators to carry out this operation
in designated area.
G.1.3 Wear safety glass

G.2 Environmental and health hazard due to G.2.1 Use of Rubber gloves or equivalent to protect the
diesel use for concrete nozzle cleaning cleaner
G.2.2 Plastic sheet should be provided to protect soil from
hazardous substance
G.2.3 Treated as an environmental spill, must be
reported
H. CLEANING/WASHING CONCRETE TRUCK G.1 Using pressurized water, indiscriminately, G.1.1 Cleaning shall be done in the designated area.
MIXERS causes Eye Injuries G.1.2 Concrete pump operators to carry out this operation
in designated area.
G.1.3 Wear safety glass

G.2 Environmental and health hazard due to G.2.1 Use of Rubber gloves or equivalent to protect the
diesel use for concrete nozzle cleaning (same cleaner
comments as G.1, G.2) G.2.2 Plastic sheet should be provided to protect soil from
hazardous substance
G.2.3 Treated as an environmental spill, must be
reported (same comments as G.1.1, G.1.2, G.1.3, G.2.1,
G.2.2, G.2.3)

I. FINISHING WORK I.1 Tripping and environmental hazard I.1.1 Collecting all concrete debris from around the area
I.1.2 Good housekeeping

Prepared by: Date: Employees 1. V.G.A. Guinza


participating in
Tolga Selcuk / GAMA 2. John Levy Jueves
the development
Checked by: Date: of JSA 3. R. PiapaCruz
Kaan Alkan / GAMA   4.
5.
Approved by: Date:
TAL - HSE
Approved by: Date:
IMT -HSE
 

You might also like