Table shows a partially completed time-study worksheet. Complete the table using the standard time
calculation for this operation. Allowances Personal 5% Fatigue 5% Delay 5%.
A Cumulative time .09 .12 .06 .11 .10 .09 .13 .12 .13 1.10
Element time
B Cumulative time .23 .28 .21 .20 .24 .22 .26 .25 .25 1.00
Element time
C Cumulative time .46 .49 .46 .44 .47 .47 .49 .46 .48 .90
Element time
D Cumulative time .61 .66 .62 .59 .69 .67 .67 .66 .70 .85
Element time
E Cumulative time .70 .74 .72 .68 .79 .80 .76 .78 .81 1.00
Element time
F Cumulative time 1.00 1.02 .98 .99 .1.07 1.09 1.02 1.06 1.09 1.10
Element time