XI.

FORMS
AND
SCAFFOLDINGS:
FORMS

• COLUMN FORMS (Ground Floor):

Note:
The forms that will be used in the first floor will also be
used in the second floor.

a. Vertical Frame (2”x2”)


Length = 4.20 m (14’)

Required = 8 pcs - 2”x2”x14’ coco Lumber


 b. Horizontal Frame (2”x2”)

 1 st Cutting = 0.20m (0.66’)


 Required = 8 pcs x 2 sides
 = 16 pcs. – 2”x2”x0.66’
 *use: 2 pcs - 2”x2”x6’

 2 nd Cutting = 0.30m (1’)

 Required = 8 pcs x 2 sides


 = 16 pcs. 2”x2”x1’
 *use: 2 pcs - 2”x2”x8’
 c. Sheathing ( ½” x 4’ x 8’ Marine Plywood):

 Perimeter = 0.20 x 2 + 0.30 x 2


 Perimeter = 1 .0 m
 *use: 1 sheet - ½” x 4’ x 8’ Marine Plywood

 Total No. of Columns for ground Floor = 20 units
 Materials to purchase:
 = 7 sheets - ½” x 4’ x 8’ Marine Plywood
 = 54 pcs - 2”x2”x14’ = 252 bd. Ft.
 = 14 pcs - 2”x2”x6’ = 28 bd. Ft.
 = 14 pcs - 2”x2”x8’ = 37.33 bd. ft
 Total Bd. Ft. = 317.33 bd. Ft.
 *BEAM FORMS:

 a. Joist (2” x 4”):


 Length = 2.4 m (8’)
 Required = 3 pcs - 2”x4”x8’ coco

 b. Side Forms (2”x2”)
 Length = 2.4m (8’)
 Required = 2 pcs x 2 sides
 = 4 pcs - 2”x2”x8’ coco
 c. Vertical Frame

 Cutting = 0.35 m (1 .15’)


 Required = 5 pcs. x 2 sides
 = 10 pcs. 2”x2”x1.15’
 = 2 pcs. 2”x2”x6’ coco

 d. Sheathing (½” x 4’ x 8’ Marine Plywood):

 Perimeter = 0.35 x 2 + 0.30


 Perimeter = 1 .0 m
 *use: 1 sheet - ½” x 4’ x 8’ Marine Plywood
 No. of Sets = 113.0 m/2.4 m = 47.08 sets/3 usage
 = 15.69 sets, say ≈ 16 sets

 Materials to Purchase:

 = 16 sheets - ½” x 4’ x 8’ Marine Plywood


 = 48 pcs - 2”x4”x8’ = 256 bd. Ft.
 = 64 pcs - 2”x2”x8’ = 170.67 bd. Ft.
 = 32 pcs - 2”x2”x6’ = 64 bd. Ft.

 Total bd. Ft. = 490.67bd. Ft.


 *SLAB FORMS:

Floor Area
 Required no. of sheets =
area of 1 sheet
77 m 2
 Required no. of sheets =
1.2m x 2.4 m
 Required no. of sheets = 26.74 sheets, say ≈ 27
sheets
 Required along shorter span: (S = 9m)
 = L/1 .20 m = 10.0m / 1 .20m = 8 pcs

 Required along Longer span: (S = 10m)
 = L/1 .20 m = 9.0m / 1 .20m = 8 pcs
SCAFFOLDINGS
SCAFFOLDINGS:

• COLUMN SCAFFOLDING:

 a. Vertical Support:
 Length = 4.20 m (14’)
 Required = 4 pcs - 2”x4”x14’ coco Lumber

 b. Horizontal Brace:
 Cutting = 1 .60m (6’)
 Required = 4 pcs x 2 layers
 = 8 pcs. – 2”x4”x6’ coco lumber
 c. Blocks and Wedges:
 Cutting = 1 .60m (6’)
 Required = 4 pcs x 2 layers
 = 8 pcs. – 2”x4”x6’ coco lumber

 d. Diagonal Brace:
 H = 4.50m (14.76 ≈ 16’)
 Required = 4 pcs - 2”x4”x16’ coco lumber

Materials for the scaf foldings of 1 unit column:
2”x 4”x 14’Coco lumber = 4 pcs
2”x 4”x 8’ Coco lumber = 8 pcs
2”x 4”x 6’ Coco lumber = 8 pcs
2”x 4”x16’Coco lumber = 4 pcs

*Determine the materials needed for the scaf foldings of


all columns
*Determine the total volume in Bd. Ft.