Professional Documents
Culture Documents
Deformation Modulus Deriner Dam Yilmaz
Deformation Modulus Deriner Dam Yilmaz
1 (2021) 63-75
https://doi.org/10.12989/gae.2021.26.1.063 63
(Received April 3, 2021, Revised June 14, 2021, Accepted June 24, 2021)
Abstract. Civil engineering structures such as gravity concrete dams, arch dams, pressure tunnels, foundations of high-rise
buildings and bridges are generally founded on rock. Design and performance of these structures are highly dependent on the
deformation modulus of the rock mass so that expected deformations and/or differential settlements stay within the tolerable
limits of the structures. In situ deformation modulus measurements of rock masses are generally performed by using the
borehole dilatometer and plate loading tests in Turkey. The diameter of plate loading test device is 30-35 cm. Tests are
performed in small unlined tunnels excavated in different elevations of dam abutments. The deformations upon loading are
measured on the loading plate in the plate loading tests. It is not possible to exclude the effect of excavation disturbed zone since
deformations are not measured with these devices. Large diameter plate test system may have multiple level extensometers set in
drill holes opened perpendicular to loading plates. Reading from these extensometers may be utilized to exclude the effect of
disturbed zone close to surface together with stress distribution estimated by using elastic theory. There are several field test
methods for determining deformation modulus and each method has its own shortcomings. The optimum methodology to
correlate plate loading test results with corresponding in-situ deformation modulus values is to back-calculate deformation
modulus by using settlements measurements during the construction of dam body. In this paper, Deriner Arch Dam settlements
measured during the construction are used to back calculate deformation modulus. It is found that in situ deformation modulus is
about two times higher than the average value determined by plate loading tests. This finding will have important effects on the
depth of foundation excavations, concrete layers to fortify structure foundations and the amount of consolidation grouting.
Keywords: deformation modulus; excavation disturbed zone; plate loading test
Fig. 6 The distribution of the stresses along beyond loading plates (Serafim and Guerreiro 1968, Palmström and Singh 2001)
disturbs the rock because of the two reasons. One of them is grouting applications in the dam foundations to increase,
the effect of the blasting on surfaces close to the blasting so-called, low deformation modulus of the dam
agents. The thickness of this zone would not exceed a foundations.
couple of meters under normal conditions. The other is the Excavation disturbed zone and/or change of measured
decompression created by excavation to reach to the base of deformation modulus with depth below a dam foundation
the foundation. Seismic measurements made in Cine Dam can be considered by calculating an equivalent foundation
(Eroglu and Yilmaz 2005) showed that the decompression modulus (Scott 1990). Firstly, stress change with depth is
zone could reach about 12-15 m perpendicular to the face of calculated by using Boussinesq stress distribution below a
excavation. This is the reason why the depth of rectangular area. Secondly, the ratio of calculated stress
consolidation grouting executed underneath the dam with depth to the foundation pressure is computed to the
foundations is usually equal to or less than 15 m (Tanchev depth where boundaries of the stress bulb created by the
2014). dam loading are reached. Thirdly, modulus of each layer
The depth of disturbed zone created either by the strains with depth is multiplied by the stress ratio calculated to find
because of blasting or by decompression may have a limited out the equivalent foundation modulus. By doing this
impact on dam behavior for a couple of reasons. First, the approximation, it is possible to take into account the effect
base width of the dam is usually much larger than the depth of excavation disturbed zone. It must be emphasized that as
of disturbed zone and/or the depth of decompression region. the foundation width increases, the effect of excavation
Second, this disturbed zone underneath the dam has a disturbed zone on the equivalent deformation modulus gets
relatively small thickness when it is compared with the decreased. Therefore, it is fair to say that plate loading tests
depth of pressure bulb created by the dam loading. Third, having small diameters of 30-35 cm mostly measure the
not only is the effect of the excavation disturbed zone characteristics of the excavation disturbed zone. Therefore,
ameliorated by shallow consolidation grouting and but also there needs to be an adjustment as suggested by Palmström
decompression due to excavation is compensated by the and Singh (2001) for the plate loading test to be used in the
weight of the dam body during construction. Therefore, the analyses, when the width of the dam, the depth of the stress
excavation disturbed zone and decompression region has a bulb created below the dam and the consolidation grouting
small effect on the dam behavior. On the other hand, the in the excavation disturbed zone are all considered. This
surface gages in plate loading test were strongly affected by suggestion is also verified by data gathered from the
near-surface fractures especially for those tests having small monitoring of Deriner Arch Dam in Turkey.
diameter loading plates. Other than those plate loading tests, the Elastmeter and
Deere et al. (1968) proposed a method for obtaining a the Dilatometer tests were performed in Deriner dam site
weighted deformation modulus by taking into account the right after construction works were tendered. Although
rock mass quality (RQD) and stress distribution underneath there was a good agreement between the results from the
loading plate. They also suggested that deformation Plate-Load and the Dilatometer tests, the discrepancy
measurements be made with depth to consider excavation between the results of the Elastmeter tests and two other
affected zone close to the face of excavation. If their advice type of tests was very high. It was concluded that the
is followed, it can be seen that excavation disturbed zone Elastmeter test or the interpretation of its raw data might not
heavily affects the result of plate jacking test results as the have been performed properly. Therefore, the Elastmeter
diameter of the loading plate gets decreased to 30 to 35cm, test results were not taken into account (Stucky Synthesis
which is the loading plate diameter used in Turkey by State Report 1999). On the other hand, the determination of
Hydraulic Works of Turkey (DSI) and Electrical Research deformability of rock masses by using dilatometer tests has
Institute (EIE). If the test results are directly used for limitations not only because of the small volume of the rock
determining deformation modulus of dam foundations, mass tested but also cracks created due to tensile stresses in
either the depth of excavation to reach foundation level will the borehole. Therefore, deformation modulus values
be increased and/or a layer of concrete cushion below dam determined by the dilatometer may be 2-3 times lower than
body will be used like Yusufeli Dam (ARQ Consulting the in-situ values obtained by using the plate bearing tests
2016). Besides there may be unrealistic consolidation (Rocha 1974, Bieniawski 1978).
Deformation modulus of rock foundation in Deriner Arch Dam 67
Fig. 7 Measured and estimated modulus of deformations for Deriner Arch Dam (Kayabasi et al. 2003).
Fig. 9 Final foundation elevations together with natural ground levels for Deriner Arch Dam. (Deriner Dam Application
Design Drawings, various dates)
Fig. 10 Seismic velocity measurements at Cine Dam after Fig. 12 Grout curtain test panel in the left bank of Deriner
foundation excavations (Eroğlu and Yılmaz 2005) Dam executed in the gallery LG 0 -153.50, the bottom
gallery at the foundation level (Ünal 2007)
Fig. 13 Grout intakes with depth in the test panel executed in the gallery LG 0 -153.50, the bottom gallery at the foundation level (Ünal
2007)
Fig. 14 Grout intakes with depth along the length of the test panel the gallery LG 0 -153.50, the bottom gallery at the
foundation level (Ünal 2007)
was shown that the depth of affected zone could reach to the gallery where the tests were performed could be
about 20 m in vertical direction (Fig. 10). The average evaluated by considering the grout intakes in the grout
depth of excavation in vertical direction is about 30m in curtain test panel. Fig. 13 shows that grout intake in the
terms of the unexcavated rock unit weight (Fig. 11), where upper 0-25 m depth reaches 35 kg/m for primary holes and
those measurements were executed. The ratio of the depth then drops to less than 8 kg/m below the depth of 25m. That
of excavation to the depth affected zone because of is a very low value according to Deere (1976) (Table 1). As
relaxation is about 1.5. pointed out by Nonveiller (1989), any grout take less than
“Grout Curtain Test Panel” was executed in the left bank 10kg/m is a waste of time and resources since
– gallery LG 0 – 153.50 to evaluate the effective-grouting approximately 10 kg/m and 5 kg/m grout is needed to fill
radius in between grout holes, penetrability rate of used 1m of a hole 70 mm and 46 mm in diameter respectively.
grout mixes, penetrability rate of used grout mixes, The diameter of primary holes is 76 mm whereas the
suitability and effectiveness of applied grouting pressures, diameter of secondary and tertiary holes is 59 mm in the
and the achieved rate of grout curtain permeability. The test panel.
beginning of the panel was at 50 m from the entrance of the The average excavated rock cover depth above the test
left bank – gallery LGO – 153.50. The length of “Grout panel is about 80 m over the test panel. Rock cover above
Curtain Test Panel” was 48m and the depth of grout holes the test panel starts with 50 m in the entrance side of the
extended to 160 m from the bottom of the gallery as shown gallery and reaches about 100 m at the end of the gallery.
in Fig. 12. The ratio of the rock cover above test gallery to excavated
The excavation effect together with the excavation of rock depth is about 1.5 at the beginning of the test panel and
70 Davut Yılmaz, Ahmet C. Altunışık and Süleyman Adanur
(a) Photo taken on February 7, 2006 (b) Photo taken on October 12, 2006
Fig. 16 Deriner Dam concreting works at foundation level. Gallery G0 at elevation 153.50 m
reduces to 0.8 at the end. The high ratio of excavated rock intakes observed in the test panel just below the grouting
depth to rock cover over the gallery could be understood as gallery up to 25 m depths cannot define the characteristics
a sign of relaxation due to excavation. This ratio at the of undisturbed dam rock foundation at that elevation. Those
beginning of the panel is almost the same that was values were observed because of decompression and
measured in Cine Dam. Hence, the gallery was built on the disturbance created by gallery excavation. Therefore, there
boundary of the relaxation limit but there is also the effect is a drastic decrease in the amount of grout intake with
of excavation of the gallery as far as the disturbance of the depth exceeding 25 m below the gallery.
ground is concerned. It may be concluded that there is almost no effect of
The thickness of disturbed zone could theoretically consolidation grouting except the zone disturbed by
reach up to two excavated tunnel diameters. In addition to blasting, which may be considered a couple of meters close
that, since there is a removal of some portion of rock due to to the dam foundation since the depth of dam foundation
construction of the gallery, the depth of affected zone excavation was enough to reach sound rock conditions,
because of tunneling could extend to the deeper elevations. because the Water Pressure Tests and grout intakes
It is interesting to note that possible cracks created during corresponding to the foundation level was limited, and for
the excavation of the gallery might have closed by the the dead weight of the dam body and the time passed before
induced stresses due to high rock cover towards the end the zero readings were enough to close decompression cracks
gallery. Therefore, there was no important grout intake in not only by the stress created but also by the effect of
creeping. Besides, the depth of the blast affected zone is
this zone close to the end of the gallery.
small when compared with the width of the dam. Thus
It can be said that there is no considerable effect of the
consolidation grouting may have negligible effect on back
grouting test gallery exceeding a depth of 25m under the calculated deformation modulus values.
gallery not only because high rock stresses exist but also the
excavation disturbed zone due to the opening of the gallery
could not reach to that depth. Besides the quality of rock 4. Back calculation of deformation modulus from
increases with depth as observed in water pressure tests. settlement measurements
The elevation of test gallery (153.50) lies about one 100m
to 180 m down from natural ground surface. The change of Boussinesq’s theory of elastic semi-space could be used
Lugeon water pressure test results with depth given in Fig. to deduce a formula for ground deformations (Herzog
8 shows that undisturbed rock in the place of the test gallery 1999). Normal displacement (settlement) can be calculated
before any grouting executed is highly impermeable and by Eq. (1).
average Lugeon values are about 3-4. Therefore, Lugeon 1
(a) Photo taken on July 4, 2006 (b) Photos taken February 5th, 2009
(c) Photo taken February 5th, 2009 (d) Photo taken June 8th, 2010
Fig. 17 Deriner Arch Dam concreting works
where; u is the normal displacement, L is the length of the 2014). The Geodetic Deformation Monitoring System used
foundation, B is the width of the foundation and N is strip in Deriner Dam was given by Konakoğlu et al. (2020).
loading as shown in Fig. 15. The crown cantilever section and abutment thickening
Early construction stages of dam body were shown of the dam were given in Figs. 21 and 22. The dead weight
through the Figs. 16 and 17. Concrete progress for all dam corresponding to settlement measurements could be
body was shown in Figs. 18 and 19. Settlement calculated. This information could be used for detailed back
measurements together with dates and reservoir water level calculation of modulus by dam modelling at any stage but
were shown in Fig. 20 and Table 2 (Electrowatt and Dolsar
72 Davut Yılmaz, Ahmet C. Altunışık and Süleyman Adanur
Fig. 20 Deriner Dam settlements measured in gallery G0 at elevation 153.50 m (Electrowatt and Dolsar, 2014)
Fig. 21 Definition of main parabolas and crown cantilever section of Deriner Arch dam (Stucky 2000)
that requires not only to know friction coefficient in friction coefficient in between the blocks in the abutments.
between dam concrete and rock foundation but also the High slope angle towards abutments will complicate the
Deformation modulus of rock foundation in Deriner Arch Dam 73
calculation. Therefore, back calculation of deformation concrete backfilling or cushion concrete could be decreased
modulus by using Eq. (1) has been done for just horizontal or probably eliminated.
valley section and neighboring blocks. • In recent years, there is a tendency to increase
The depth of foundation excavation and Water Pressure
consolidation grouting works not only by extending grout
Test results in terms of Lugeon values below foundation
holes into greater depths and widths but also decreasing the
level show that rock foundation is almost untreatable by
distance in between holes. This choice increases the cost
grouting. In other words, consolidation grouting effect in
and extends the time of construction. Consolidation
between zero reading and following readings is minimal as
grouting works for dam foundations may be much needed
far as overall deformation modulus is concerned.
and justified for the zones affected by blasting. The
Average elevations at the time of zero measurement and
thicknesses of those zones are much less than consolidation
at the time second measurement were about 189.5 m and
grouting depths practiced today in many dams in Turkey.
219.0 m, respectively. Average additional load in between
Besides, the amount of consolidation could be reduced
these days was about 27.23 m. Average load per meter on
since in situ deformation modulus’s are higher than test
the foundation is about 3267 ton/m. Measured average
values because of the plate loading test devices utilized.
deformation was about 3.8 mm. Average length of loading
Therefore, the need to increase deformation modulus by
(L) can be taken as 190 m at elevation 189.5 m.
consolidation grouting is diminished.
Deformation modulus can be back calculated by using Eq.
(1). Its value is about 13 GPa. • Best way to reduce the effect of excavation disturbed
This is about 2.2 times plate loading tests made by EIEI zone on test results would be to increase the diameter of
of Turkey. The diameter of the plate is 35 cm. This back plate loading device and to measure displacements with
calculated value verifies those conclusions reached by depth during the test.
Palmström and Singh (2001). As pointed out by the other
studies, Excavation Disturbed Zone (EDZ) created around
the adits must have affected the results because the stress References
change with depth due to test loading is proportional to the
diameter of the loading plate. Therefore, smaller diameter Aksoy, C.O., Uyar Aksoy, G.G., Guney, A., Ozacar, V. and Yaman,
loading test setups are more affected by disturbed zones H.E. (2020), “Influence of time-dependency on elastic rock
around the adits where the tests are run. properties under constant load and its effect on tunnel stability”.
Geomech. Eng., 20(1), 1-7.
http://doi.org/10.12989/gae.2020.20.1.001.
Angın, Z. (2016), “Geotechnical field investigation on Giresun
5. Conclusions hazelnut licenced warehause and spot exchange”, Geomech.
Eng., 10(4), 547-563.
Small diameter plate loading test with surface https://doi.org/10.12989/gae.2016.10.4.547.
displacement measurements gives lower deformation values Agharazi, A., Martin, C.D. and Tannant, D.D. (2015), “Numerical
because the stress bulb created by the plate mainly remains analysis of plate-load test results on fractured rocks using an
in the excavation disturbed zone. There are many test equivalent-continuum model: Case study of the Bakhtiary dam
methods to determine deformation modulus of rock site”, Int. J. Geomech., 15(1), 05014001, 1-11.
https://doi.org/10.1061/(ASCE)gm.1943-5622.0000415.
foundations but each one has its own shortcoming or
ARQ Consulting. (2016), “Yusufeli dam and HEPP”, Report on
difficulty. Therefore, the best way is to use deformation Dam Foundation Strengthening, Revision-1, Artvin, Turkey.
measurement during the construction of the dam to back Barton, N. (2007), Rock Quality, Seismic Velocity, Attenuation and
calculate deformation modulus. This study about Deriner Anisotrophy, Taylor and Francis Group, London, U.K.
Dam shows that in-situ deformation modulus calculated by Bieniawski, Z.T. (1978), “Determining rock mass deformability:
using settlement measurements is about two times higher experience from case histories”, Int. J. Rock Mech. Min. Sci.
than those estimated by using the plate loading tests. This is Geomech. Abstr., 15(5), 237-247.
the same conclusion reached by Palmström and Singh https://doi.org/10.1016/0148-9062(78)90956-7.
(2001). This verification has a lot of important Coon, R.F. and Merritt, A.H. (1970), Predicting In-Situ Modulus of
Deformation using Rock Quality Indexes, ASTM Special
consequences. Some of them are listed below:
Technical Publication, Philadelphia, U.S.A.
• Empirical equations relating rock mass quality to rock Deere, D. (1976), “Dams on rock foundations, some design
mass modulus need to be restudied if the data were obtained questions”, Proceedings of the Rock Engineering for
from the small diameter test devices. In reality more sites Foundations and Slopes Conference, Boulder, Colorado, U.S.A.
Deere, D.U., Hendron, A.J., Patton, F.D. and Cording, E.J. (1968),
would be appropriate for concrete dams, bridges and high-
“Design of surface and near-surface construction in rock”,
rise buildings given the low values of the test results for Proceedings of the 8th Symposium on Rock Mechanics
sound rock conditions. (USRMS), Minneapolis, Minnesota, U.S.A., September.
• Low values of deformations modulus would require Dodds, D.J. and Schroeder, W.L. (1974), “Factors bearing on the
interpretation of in-situ testing results”, Proceedings of the 2nd
more excavation to reach appropriate foundation conditions. Rapid Excavation and Tunnelling Conference, San Francisco,
This extra excavation would increase the cost drastically California, U.S.A., June.
because of both excavation and backfilling with concrete. In DSI. (1999), “Deriner dam final design drawings”, State Hydraulic
fact, the depth of excavation to meet necessary deformation Works of Turkey, Ankara, Turkey.
modulus criteria can be reduced. Besides the amount of DSI. (2015), “Hydraulic jack and dilatometer test report”, Yusufeli
74 Davut Yılmaz, Ahmet C. Altunışık and Süleyman Adanur
Dam and Hydropower Plant Project, Artvin, Turkey. Palmström, A. and Singh, R. (2001), “The deformation modulus of
Electrowatt Engineering Ltd and Dolsar Engineering Ltd. (2014), rock masses-comparisons between in situ tests and indirect
Deriner dam and hydroelectric power plant, Geodetic Dam estimates”, Tunn. Undergr. Sp. Tech., 16(2), 115-131.
Monitoring I8 Readings After Completion of Impounding, https://doi.org/10.1016/S0886-7798(01)00038-4.
Technical Report, Artvin, Turkey. Rocha, M. (1970), New techniques in deformability testing of in
Eroğlu, V. and Yilmaz, D. (2005), “Approaches considered to situ rock masses, in determination of the in-situ modulus of
overcome uncertainties at Çine dam”, Proceedings of the deformation of rock, A.S.T.M. Special Technical Publication,
ICOLD Annual Meeting, Iran. 477, 39-54, A.S.T.M., Philadelphia.
Fan, Q., Zhou, S. and Yang, N. (2015), “Optimization design of Rocha, M. (1974), “Present possibilities of studying foundations
foundation excavation for Xiluodu super-high arch dam in of concrete dams”, Proceedings 3rd International Congress on
China”, J. Rock Mech. Geotech. Eng., 7, 120-135. Rock Mechanics, Denver, Colorado, U.S.A.
https://doi.org/10.1016/j.jrmge.2015.03.001. Scott, G.A. (1990), “Deformation of rock foundations under
Galera, J.M., Alvarez, M. and Bieniawski, Z.T. (2005), dams”, Proceedings of the 10th Annual USCOLD Lecture
“Evaluation of the deformation modulus of rock masses: Series, New Orleans, Louisiana, U.S.A.
comparison of pressuremeter and dilatometer tests with RMR Serafim, J.L. (1964), Rock Mechanics Considerations in the
prediction”, Proceedings of the ISP5-Pressio International Design of Concrete Dams, in State of Stress in the Earth’s
Symposium, France. Crust, 611-650, New York, U.S.A.
Geoconsult GIBB and ARQ. (2000), “Cine RCC dam”, Phase II Serafim, J.L. and Guerreiro, M. (1968), “Shear strength of rock
Design Reports, Volume 1-4, and Final Design Drawings, masses at 3 Spanish dam sites”, Proceedings of the
Artvin, Turkey. International Symposium on Rock Mechanics, Madrid, Spain.
Hall, W.J., Newmark, N.M. and Hendron, A.J. (1974), Serafim, J.L. and Pereira, J.P. (1983), “Consideration of the
“Classification, engineering properties and field exploration of geomechanics classification of Bieniawski”, Proceedings of the
soils, intact rock and in situ rock masses”, Directorate of International Symposium on Engineering Geology and
Regulatory Standards, US Atomic Energy Commission, USA. Underground Constructions, Lisbon, Portugal.
Herzog, M.A.M. (1999), Practical Dam Analysis, ICE Publishing, Shannon and Wilson Inc. (1964), “Report on in situ rock tests,
Thomas Telford. Dworshak dam site”, US Army Engineer District, Walla Walla,
Hoek, E. and Diederichs, M.S. (2006), “Empirical estimation of Seattle, Washington, U.S.A.
rock mass modulus”, Int. J. Rock Mech. Min. Sci., 43, 203-215. Shen, X., Niu, X., Lu, W., Chen, M., Yan, P., Wang, G. and Leng,
https://doi.org/10.1016/j.ijrmms.2005.06.005. Z. (2017), “Rock mass utilization for the foundation surfaces of
Ito, Y., Agui, K., Kikuchi, K., Fujieda, M., Kobayashi, T. and high arch dams in medium or high geo-stress regions: review”,
Saito, T. (2007), “Brief and systematic evaluation for B. Eng. Geol. Environ., 76, 795-813.
deformation characteristics of dam site rock mass by shock https://doi.org/10.1007/s10064-016-0892-4.
response value”, Proceedings of the 11th Congress of the Stucky Consulting Engineers Ltd. (1999), “Deriner dam and
International Society for Rock Mechanics: The Second Half HEPP, Additional Geological Investigations”, Synthesis Report,
Century of Rock Mechanics, July, Lisbon, Portugal. Report No. 4353/4115-1, Switzerland.
Kayabası, A., Gokceoglu, C. and Ercanoglu, M. (2003), Stucky Consulting Engineers Ltd. (2000), “Deriner dam and
“Estimating the deformation modulus of rock masses: A HEPP, Dynamic analysis of the final optimised dam desig”n,
comparative study”, Int. J. Rock Mech. Min. Sci., 40, 55-63. Report No. 4353/4265, Switzerland.
https://doi.org/10.1016/S1365-1609(02)00112-0. Tan, C., Ma, D.H., Liu, Z.F., Gao, Y., Xu, X.C. and Zhang, W.
Konakoglu, B., Cakir, L. and Yilmaz, V. (2020), “Monitoring the (2020), “Research on the deformation and failure pattern of rock
deformation of a concrete dam: A case study on the Deriner masses in dam foundations controlled by continuous gently
Dam, Artvin, Turkey”, Geomatics Nat. Hazards Risk, 11(1), inclined and discontinuous steeply inclined unconformities”,
160-177. https://doi.org/10.1080/19475705.2020.1714755. IOP Conf. Ser. Earth Environ. Sci., 570, 1-12.
Lee, S.W. (2019), “Experimental study on effect of underground Tanchev, L. (2014), Dams and Appurtenant Hydraulic Structures,
excavation distance on the behavior of retaining wall”, Taylor & Francis Group.
Geomech. Eng., 17(5), 413-420. Tayarani, N.S., Jamali, S. and Zahed, M.M. (2020), “Combination
http://doi.org/10.12989/gae.2019.17.5.413. of artificial neural networks and numerical modeling for
Li, W. (2017), “Experiment study on the whole deformation predicting deformation modulus of rock masses”, Arch. Min.
process of arch dam bedrock”, Proceedings of 9th International Sci. 65(2), 337-346.
Economics, Management and Education Technology Ünal, B. (2007), “Deriner dam and HEPP grout curtain test
Conference, Taiyuan, China, July. results”, Proceedings of the Turkey Union of Chambers of
Liu, Y., He, Z., Yang, Q., Deng, J. and Xue, L. (2017), “Long-term Architects and Engineers Second Geotechnical Symposium,
stability analysis for high arch dam based on time-dependent Adana, Turkey, November.
deformation reinforcement theory”, Int. J. Geomech., 17(4), Wallace, G.B., Slebir, E.J. and Anderson, F.A. (1970), In situ
04016092. methods for determining deformation modulus used by the
https://doi.org/10.1061/(ASCE)gm.1943-5622.0000760. bureau of reclamation, ASTM Special Technical Publication,
Nonveiller, E. (1989), “Grouting theory and practice”, 477, 3-26, Philadelphia, USA.
Developments in Geotechnical Engineering, 57, 1-250. Wei, Y., Xu, M., Wang, W., Shi, A., Tang, M. and Ye, Z. (2011),
Oberti, G., Bavestrello, F., Rossi, P.P. and Flamingi, F. (1986), “Feasibility of columnar jointed basalt used for high-arch dam
“Rock mechanics investigations, design and construction of the foundation”, J. Rock Mech. Geotech. Eng., 3, 461-468.
Ridracoli Dam”, Rock Mech. Rock Eng., 19(3), 113-142. https://doi.org/10.3724/SP.J.1235.2011.00461
https://doi.org/ 10.1007/BF01024952. Wu, B, Niu, J, Su, H, Yang, M, Wu, Z and Cui, X. (2019), “An
Oberti, G., Carabelli, E., Goffi, L. and Rossi, P.P. (1979), “Study approach for deformation modulus mechanism of super-high
of an orthotropic rock mass: Experimental techniques, arch dams”, Struct. Eng. Mech., 69(5), 557-566.
comparative analysis of results”, Proceedings of the 4th http://doi.org/10.12989/sem.2019.69.5.557.
Congress International Society for Rock Mechanics, Montreux, Zhang, Y, Ding, X, Huang, S, Qin, Y, Li, P and Li, Y. (2018),
Switzerland, September. “Field measurement and numerical simulation of excavation
Deformation modulus of rock foundation in Deriner Arch Dam 75
CC