VOLUME TYPIKAL JEMBATAN

No. JENIS BANGUNAN HITUNGAN VOLUME (m3)

1 BOX CULVERT 2 X 2 M
1. Beton K-300 1 = 0,30 x 2,6 x 15,00 x 2 23.40

2 = 0,30 x 2,70 x 15,00 x 2 24.30

3 = (0,42 x 0,30) x 15,00 x 4 3.78


2
4 = 0,30 x 0,65 x 15,0 x 2 5.85

5 = 0,3 x 0,50 x 4,40 x 2 1.32

Jumlah 58.65 m3

2. Lantai Kerja K 175 1 = 0,1 x 3.00 x 15,00 4.50

Jumlah 4.50 m3
3. Pasangan Batu
1 = 0,35 x 0,65 x 5,00 x 4 4.55
2 = 0,30 x 2,00 x 5,00 x2 6.00
3 = (0,35+0.80) x 2,70 x 5 x 4 31.05
2
4 = 0,20 x 3,00 x 15,00 9.00

Jumlah 50.60 m3

4. Galian Tanah
1 = (4,92+3,00) x 1,5x15,00 89.10
2
2 = 0,65 x 3,00 x 5,00 x 2 19.50

Jumlah 108.60 m3

5. Timbunan Tanah Pilihan


1 = (1,80+0,30) x 3,50 x 15,00 x 2 110.25
2
Jumlah 110.25 m3
6. Begesting (m2)
1 = 2,60 x 0,30 x 2 1.56

2 = 2,60 x 0,35x 2 1.82

3 = 2,00 x 0,30 x 4 2.40

4 = 1,40 x 15,0 x 3 63.00

5 = 2,65 x 15,0 x 2 79.50

Jumlah 148.28 m2
2 BOX CULVERT 5 X 4 M

1. BETON K - 300

1 = 6,100 x 0,55 x 15,00 50.33

2 = (1,05+0,50) x 0,50 x 15,00 x 2 11.63


2
3 = (1,05+0,55) x 0,450 x 15,00 x 2 10.80
2
4 = 0,35 x 0,30 x 15,00 x 2 3.15

5 = (0,4+0,30) x 0,10 x 15,00 x 2 1.05


2
6 = 3,75 x 0,55 x 15,00 x 2 61.88

7 = 6,10 x 0,60 x 15,00 54.90

8 = (0,7 x 0,35) x 15,00 x2 3.68


2
9 = 0,40 x 0,30 x 15,00 x 2 3.60

Jumlah 201.00 m3
2. Plat Injak

10 = 0,30 x 2,970 x 10,00 x 2 17.82

11 = (0.34 + 0,26)x0,2x5x2 0.61


2
18.43 m3

3. Wingwall 12 = (4,2 x 1,05) x 0,30 x 4 2.65


2
4. Parapet 13 = 0,3 x 1,0 x 8,20 x 2 4.92

Jumlah 7.57 m3

5. Lantai Kerja 14 = 7,10 x 0,1 x 15 10.65

Jumlah 10.65 m3

6. Galian Tanah
1 = (3 + 3,5) x 0,85 x 15,5 42.82
2
2 = (3,5 + 2,2) x 2,6 x 15,5 114.86
2
3 = 1,8 x 2,6 x 15,5 72.54

4 = (3,5 + 2,4) x 1,5 x 15,5 68.59


2
4 = (3,2 +1,7) x 3,5 x 15,5 132.91
2
Jumlah 431.71 m3
7. Timbunan Pilihan
1 = (3,00 + 0,30) x 5,00 x 14,40 x 2 237.60
2
Jumlah 237.60 m3
8. Pasangan Batu
1 = (0,4 + 0,9) x 4 x 10 x 4 104.00
2
2 = 0,9 x 1,0 x 10 x 4 36.00

Jumlah 140.00 m3

9. Lantai Kerja 1 = 0,1 x 7,1 x 15 10.65


Jumlah 10.65 m3
10. Pasangan Batu Kosong 1 = 0,2 x 7,1 x 15 21.30
Jumlah 21.30 m3
11. Saluran / U-Dith 1 = 0,15 x 0,75 x 50 x 8 45.00
2 = 0,15 x 0,60 x 50 x 4 18.00

Jumlah 63.00 m3

3 JEMBATAN DINDING BAJA


1. ABUTMENT K-300, L = 15 .00 m
1 = (0,4 + 0,44) x 1,12 x 15 x 2 14.11
2
2 = 0,28 x 0,3 x 15 x 2 2.52

3 = (0,4 + 0,3) x 0.17 x 15 x 2 1.79


2
4 = (1,54 + 1,8) x6,5 x 15 x 2 325.65
2
5 = (0,4 x 2,6) x15 x 2 15.60
2
6 = 2,6 x 1,4 x 15 x 2 109.20

7 = 3,8 x 1,8 x 15 x 2 205.20

Jumlah 674.07 m3

2. Wingwall, K - 300, t = 0.40 m

1 = 3,4 x 1,5 x 0.4 x 8 16.32

2 = (3,34 + 2,00) x6,12 x 0,4 x8 52.29


2
Jumlah 68.61 m3

3. Plat Injak K - 300, L = 3,20 m

1 = 3,1 x 0,3x3,2 x 4 11.90

2 = (0,27 + 0,34) x0.18x3,2 x 4 0.70


2
Jumlah 12.61 m3
4. Dinding Penahan Tahah K - 250, L = 55.00 m

1 = (0,75 + 0,65) x0.45x25 x 4 31.50


2
2 = (0,45 + 0,3) x0.15x25 x 4 5.63
2
3 = (0,40 x 0,6) x25x3 x 4 36.00
2
4 = 0,3 x 6,2 x 25 x 4 186.00
6
5 = (0,30 x 0,6) x25 x 4 9.00
2
6 = 0,6 x 1,2 x 25 x 4 72.00

7 = 0,4 x 1,2 x 25 x 4 48.00

Jumlah 388.13 m3

5. Lantai Kerja K-175


a. Abutment 1 = 6,40 * 0,1 * 25 * 2 32.00
b. Dinding Penahan Tanah 2 = 1,40* 0,1 * 25 * 2 14.00
3 = 5,3*0,05*25*2 13.25
Jumlah 59.25 m3
6. Bore Pile K - 350, L = 9.00 m

1 = 3,14 x 0,4^2 x 9,00 x 18 x 2 162.78

Jumlah 162.78 m3

Bore Pile Ø 800


L = 9.00 m

6. Pasangan Batu Kosong

1 = 6,40 x 0,20 x 15 x 2 38.40

2 = 1,40 x 0,20 x 25 x 4 28.00

Jumlah 66.40 m3

7. Galian Tanah
a. Abutment - 1
1 = (3,75 + 6,5) x 0,4 x 15,5 31.78
2
2 = (6,5 + 7,5) x 0,4 x 15,5 43.40
2
3 = (12,8 + 7,60) x 5,2 x 15,5 822.12
2

Jumlah 897.30 m3

a. Abutment - 2

1 = (0,64x 11,8) x 15,5 58.53


2
2 = (11,8 + 11,30) x 0,8 x 15,5 143.22
2
3 = (7,6 + 11,30) x 3,7 x 15,5 541.96
2

8.Timbunan Pilihan Jumlah 743.71 m3


1 = (8,1 + 3,7) x 6,5 x 15,5 x 2 1,188.85
2
2 = (1,7 + 0,3) x 2,1 x 15,5 x 2 65.1
2
Jumlah 1,253.95 m3

4 OVERPASS 2 LAJUR TYPE - A

1. Abutment K - 300
1 = 0,30 x 0,60 x 10,00 x 2 3.60
20 30

170 2 = 0,65 x 0,50 x 10,00 x 2 6.50


60
125
65 50
80 50 3 = 0,50 x 1,80 x 10,00 x 2 18.00
150 180 100
3 = 1,00 x 3,50 x 10,00 x 2 70.00
350
Jumlah 98.10 m3
VOLUME (m3)
No. Type Bangunan Beton Beton Beton Beton
Pas. Batu
K - 350 K - 300 K - 250 K - 175
1 Box Culvert 2 x 2 (m) - 58.65 - 4.50 50.60
2 Box Culvert 4 x 5 (m) - 227.00 - 21.30 140.00
3 Dinding Baja 162.78 755.28 388.13 59.25 -
4 Overpass Klas - A (2 Lajur) 767.43 404.37 128.04 33.92 6.00
5 Overpass Klas - A (4 Lajur) 671.59 236.84 304.10 31.78 9.00
6 Overpass Klas - B (2 Lajur) 397.88 246.09 165.59 31.56 9.00
7 Rangka Baja Bentang 35,00 165.79 647.31 184.73 40.50 -
8 Rangka Baja Bentang 56,00 165.79 689.43 196.87 43.20 -
9 Rangka Baja Bentang 91,00 271.30 920.87 231.08 52.80 -
10 PCT Girder Bentang 16,00 120.58 531.75 240.78 51.00 -
11 Voided Slab Bentang 10.00 192.92 383.47 183.76 34.80 -
12 Overpass Klas - C (2 Lajur) 380.44 508.66 75.88 24.02 9.00
VOLUME (m3)
Timbunan Pas. Batu Saluran /
Galian Struktur
Pilihan Kosong U-DITH
108.60 110.25 9.00 -
431.71 237.60 21.30 -
1,641.00 1,253.95 66.40 63.00
539.49 84.05 45.36 21.41
155.73 187.41 27.89 41.72
421.75 71.54 11.01 52.94
1,045.17 557.23 54.00 -
1,045.55 669.62 56.40 -
3,055.52 1,115.13 67.20 -
1,900.13 1,388.05 55.20 -
597.67 355.21 42.00 -
397.74 72.70 28.63 16.98