Method Statement

(Installation of PVC Conduits Embedded in Concrete)

Appendix – 3
Installation Checklist

Method Statement (Installation of PVC Conduits Embedded in Concrete)


, Page 01 0f 02
INSTALLATION CHECKLIST
The Red Sea Development
Project Name Shura Central Hotel 1 Client
Company
Consultant DAR AL HANDASAH Civil Contractor SBG
Installation Check List for PVC
Checklist Title Date ITR Reference
Conduits Embedded in Concrete
Works Location System Grid Ref MST Reference

Inspection Details

PVC Conduits Installation:

Acceptance
SN Description of Checking to be Carried Out / Results Reference Document Remarks / Criteria
YES NO N/A

INSTALLATION CHECK LIST PVC CONDUITS

Check that the materials are in accordance with approved


1 material submittal

Check the Installation of PVC conduits are as per


2 approved shop drawings.
Check the Installation of conduits coordinated with other
3
services
Check the PVC Conduits leveled and aligned properly
4
Check PVC conduits fasten firmly by using coupler and
5 glue.

Ensure proper spacing gap maintained between PVC


6
conduits running in parallel.
Check open ends of the conduits closed with caps or
7 plugs to avoid blockage.
Junction boxes are fixed at accessible locations as
8 required

The sealing of conduits boxes and joints to prevent ingress


9 of concrete during pour
Expansion couplers provided at building expansion
10 joints or where required.

11 Check proper fixing of conduits to Re-bar

12 Check termination of conduits to outlet boxes

13 Check pull boxes provided for conduits where required.

14 Check the floor from any conduits or accessories surplus.

Contractor Contractor Consultant


Site Engineer QA/QC Engineer
Representative
Name

Designation

Date