Revised R07-HC1C20-SBG-MTS-ME-0002 (Rev.01)
Revised R07-HC1C20-SBG-MTS-ME-0002 (Rev.01)
TRS-CN-FRM-0019
General Information
Project Name Shura Hotel Central 01 Project Code R07-HC1C20-3050
Submittal No. R07-HC1C20-SBG-MTS-ME-0002 Date 14-JAN-23
Contract No. R07-HC1C20
Contract Description
Contractor
Method Statement for
Contractor Name Saudi Binladin Group (SBG) Subject Installation of Underground
Storm Drainage Pipe.
Specification No. 22 00 00, 22 14 23 & 22 14 13 Drawing Ref. N/A
Discipline Mechanical Other (please specify)
Planned Date of Work 18-JAN-23 Submitted For: ☒ Approval ☐ Information
Contractor Authorized Representative
Engineer’s - Comments
Comments:
Status Code
Sign
Stamp
PREVIOUS REVISION COMMENTS AND CONTRACTOR RESPONSE
Document Review Respose Form
RSG-DC-FRM-0002
RED_SEA_PROJECT
General Information
Program Name R07 Project Code HC1C20
Doc or Dwg Title: Method Statement For Installation of Underground Storm Darinage Pipe.
The document(s) reviewed under this DRF, were issued "For Review and Comments" under Transmittal Ref- 0, dated on 12-12-2022, and are hereby return to the issuer with the following return code and actions request
(Overall return code will be worst among individual assessment code below) C
Assessment Code
A= Accepted B= Accepted with Comments C = Revise and Resubmit D = Rejected
R07-HC1C20-SBG- Complied.
3 Kamel Hassan/ Dar General Rev.0: Joint method shall be Solvent-Cemented Joints ME C
MTS-ME-0002 Please refer to Clause 12.3.4 (Page-15)
Rev.0:Install sleeves for piping penetrations of walls, ceilings, and floors. Comply with
requirements for sleeves specified in Section 220517 "Sleeves and Sleeve Seals for R07-HC1C20-SBG- Complied.
4 Kamel Hassan/ Dar General ME C
Plumbing Piping.". Fire stop materail shall be considered if the partion is fire rated and MTS-ME-0002 Please refer to Clause 12.3.8 (Page-17)
as per typical details
Rev.0: manholes shall be Internally GRP lined with asphalat painting externally as per R07-HC1C20-SBG- Complied.
5 Kamel Hassan/ Dar General ME C
specs MTS-ME-0002 Please refer to Clause 12.3.6 (Page-16)
Rev.0:On the transmittal cover page , Indicate the related specs for undergound storm R07-HC1C20-SBG-
6 Kamel Hassan/ Dar General ME C Noted & Complied
pipes, excavation and back filling MTS-ME-0002
Rev.0: excavating, trenching, and backfilling shall be in full compliance with civil R07-HC1C20-SBG- Complied.
7 Kamel Hassan/ Dar General ME B
specification Section 312000, to be coordinated with Civil trade MTS-ME-0002 Please refer to Clause 12.3.7 (Page-17)
Table of Contents
1 Project Brief............................................................................................................................................................................... 2
2 Purpose ..................................................................................................................................................................................... 3
3 Scope.......................................................................................................................................................................................... 4
14 Quality Control........................................................................................................................................................................ 19
17 Emergency Arrangements..................................................................................................................................................... 30
1 Project Brief
The Project Hotel Central (HC1) is a standalone LEED Platinum sustainable 5-Storey Hotel located within the Shura
Island in Red Sea (Saudi Arabia). Hotel HC01 provides a focal point in the Island development and is the highest point
on the Island with stunning views over the coastline and surrounding developments, comprising of a wide range of 5
Star quality FOH, MICE and BOH amenities. The hotel consists of 430 keys including space allocation for spa, cafes,
restaurants, retail and banqueting. HC01 is referred to as “The Luxury Village” by Grand Hyatt, while RD&E is known
as Retail, Dining and Entertainment.
The Building designs will be unique, iconic and draw inspiration from the surrounding environment, constructed to
leverage modern technologies and efficiencies, orienting the building to maximize the sunset views over the dunes
and provide a variety of unique and memorable experiences for the guests.
2 Purpose
The Purpose of this method statement is to define the requirements and procedure for the installation and testing of
inside below ground Storm Drainage Pipes and the requirements of checks to be carried out for “SHAURA HOTEL
PROJECT #1 (R07- HC1C20-3050)”.
The storm drainage installation procedure is to establish, monitor and control of all activities during erection of Harps in
WHRB in order to meet project specification, reference codes and standards.
3 Scope
This procedure covers the site installation of PVC piping for below ground storm drainage pipe work and manhole
installation inside buildings to external utilities manholes. This document defines the works procedure as in compliance
with the contract specification, approved drawings and manufacturer recommendation.
This procedure will be used, as needed, to provide assurance that construction activities are being conducted as
required by project specification. It is not expected that completion of the entire procedure will be accomplished during
any one inspection and/or every time the inspection procedure is used. It is a continuing activity until complete
installation of PVC storm drainage pipe is installed.
4.1 Definitions
Term Definitions
Activity Smallest identified object of work in a project
Corrective Action Action to eliminate the cause of a nonconformity and to prevent recurrence
Efficiency Relationship between the result achieved and the resources used
4.2 Abbreviations
Term Description
TRSDC The Red Sea Development Company
MS Method Statement
RA Risk Assessment
QA Quality Assurance
QC Quality Control
ASTM D 2665 Solid Wall PVC Pipe - Drain, Waste and Vent
Material Submittal Ref (TBA) Material Submittal for Solvent Welded Joints
9 Manpower Requirement
• Technical Manager
• Construction Manager
• Site Engineer
• HSE Officer
• Quality Engineer
• Site Supervisor
• Storekeeper
• Foremen
• Electrician
• Helpers
11 Sequence of Work
This section mainly deals with the logical sequence of how the job is to be executed in a safe manner without
risks. Following are the procedural steps Involved in the Installation of uPVC underground drainage pipes,
wherein the same is elaborated under Section 12.
• Prerequisites to Procedure
• Pre-Installation Procedure
• Installation Procedure
• Jointing Method
• Testing Procedure
The following items are pre-requisites to the commencement of underground PVC Pipes and fittings:
• Prior to commencement of work, areas and access will be inspected to confirm that the site is ready and is safe to
commence the work.
• All relevant documentation and material applicable to particular section of works will be checked by site engineer
before commencement of work.
• Prior to commencement of work, coordination will be done with other services.
• Ensure all the site safety requirements are in place in accordance to the approved safety plan.
• Shifting of materials to the work location with enough manpower and all necessary safety precautions
shall be implemented during shifting and installation.
• Engineer / Supervisor shall confirm that all necessary documentation is in place to proceed and identify if
there are any special requirements needed.
• Arrange all necessary Plant / Equipment and services as required for the works.
• Employee induction and toolbox talks to be conducted on risk assessment / hazard identification and
control measures of hazard
12.3.2 Bedding
• Place 150 mm or 250 mm bedding layer according to bottom of trench type soil.
• Soaking Granular, sprinkling water, and compaction for the bedded Granular.
• Check the thickness of bedded Granular.
• Bedding to be inspected prior to installation of pipelines.
• Install compression type rubber plugs with bleeding caps to plug branch in the stack. Plug all other openings with test
plugs.
• Fill water to point of overflow, but not less than 30 kpa. From 15 minutes before inspection starts to completion of
inspection to check the section for any leaks around its joints, water level must not drop. Inspect joints for leaks.
• Gravity test will be carried out in section wise and zone wise to facilitate the progress of the work and in order to
release the line on priority basis.
• If leaks observed during testing, after repair leaks and defects retest shall be repeated unit satisfactory results are
obtained.
• On successful completion of the test the relevant parties will complete and sign off the test certificate.
• After a successful test ensures piping system is fully drained.
• Perform Manhole to Manhole Hydro-test, and then Final Hydro test -to be carried out for the complete network.
12.3.6.1 MH Installation
• After lifting existing pipe, install the formwork for semicircular pipe equal to diameter of adjacent sewers.
• For anchor blocks to be casted with sulphate resisting concrete Class 250/20 to rise vertically from top of channels,
height not less than soffit of outlet pipe, then it shall be sloped upwards to wall.
• Pouring shall be carried out within 3 hours with a coat of sulphate resisting cements and mortar with ratio 1:2. Smooth
finishing to be accomplished with a steel trowel.
• Place the lowest unit on top of the concrete base and haunch in cement mortar. [the lowest unit could be transition
slab or ring depends on the MH base shape].
• Coat the joints of rings with bituminous composition prior to fixing.
• Seal the joints with rubber ring and fill the joints and strike-off surplus compound.
• Externally, coat the manhole/ inspection chamber with 2-layers of asphaltic composition [600 microns min. thickness].
• Internally, coat the inspection chamber with 3-layers of coal tar epoxy paint (70% epoxy, 30% coal tar, 450 microns
min).
• Install 600 mm Ø lockable HDCI cover and frame and should be flushed with road level.
ST
• Add flexible joint when connecting at manholes/ inspection chamber. [Add 1 flexible joint at a distance equal to D of
pipe diameter and the 2ND at 2D].
• All Manhole covers and frames shall be in accordance with BS EN 124. Manholes shall be internally glass reinforced
plastic (GRP) liner as specified in the specification section (220573) Part-2 (Clause 2.1-A).
[Filling materials for general filling shall pass a three-inch U.S. standard sieve and the material passing a No. 4 U.S.
standard sieve is to have a maximum plasticity index of 6%. No piece is to have its largest dimension greater than
one-third the thickness of the compacted layer].
• Apply field density tests on compacted soils where the min. density required on soils is to be 95% max. dry density.
• Excavating, trenching, and backfilling works will be carried out in coordination with civil trade and shall be in full
compliance with civil specification Section 312000.
• Sleeves have to be provided for pipes passing through walls, ceiling and floors as specified in section 221423
(Clause 3.2 T & U) and Section 220517 "Sleeves and Sleeve Seals for Plumbing Piping."
• Fire stop material shall be considered if the partion is fire rated and as per typical details.
• Install escutcheons for piping penetrations of walls, ceilings, and floors. Comply with requirements for escutcheons
specified in Section 220518 "Escutcheons for Plumbing Piping
• Inspection and tests shall be carried out as per approved ITP‟s and which shall detail proposed sequence of work,
hold points, testing frequency, document control etc. and which may need to be modified in specific cases depending
on the nature of installations.
• Compaction test should be conducted at the bottom of the trench and each layer (250 mm to 300 mm) as per
specification.
• Inspection shall be based on approved ITP, Project QC Plan and Project Specifications listed in under
Technical Specification and according to approved shop drawings.
• The quality personnel on site in coordination with Supplier representative will ensure that Installation, Testing and
Commissioning work done conforms to the standard and required specifications prior to raise Inspection request to
Consultant/Client for final approval.
The purpose of an Inspection and Test Plan is to put together a single document that records all inspection and
testing requirements relevant to a specific process.
ITP‟s shall be prepared for each major activity to identify the details of the inspection and tests required, The ITP
details out the reference document to which the inspections are to be carried out, acceptance /rejection criteria and
the verifying party having the jurisdictional authority over the work.
14 Quality Control
The function of Quality Control is to check, measure test, inspect and when necessary, record action in a formalized
matter to confirm compliance with contract requirements.
The personnel responsible for Quality Control shall complete, as necessary check lists, test reports and the like, which
record successful completion of the inspection and test requirements.
The inspection on site is implemented by the QA/QC Engineer together with Engineer’s Representative. At the end
Of the inspection, the QA/QC Engineer checks that all the persons concerned have signed the Inspection Check List
• Work will commence as per Safety regulations laid down in the contract specification and project health and safety
requirements.
• Cordoning off of danger zones, areas and display of placards etc. shall be laid down and strictly adhered to the project
specification requirements.
• Safety Supervisor will arrange the toolbox talks on daily basis, relevant to activities to be carried out at site.
• All personal protective equipment shall be used as appropriate according to the nature of the job.
• Proper safety harness to be used and secured, if required.
• Housekeeping shall be of good standard and all cut pieces and debris shall be removed.
• Ensure that proper scaffolding/ladders are available.
• Ensure that all lifting operations are carried out as per approved procedures and safety regulations
• During testing warning sign boards to be installed and barricade the area of unauthorized personnel.
• Excavation area shall be barricaded with solid and rigid material.
• Permits - Where required, permits to work provided prior to commencement of works. Suitably trained and
experienced HSE personnel shall issue permits only.
• Heat Stress Training to be provided.
• Adequate cool drinking water, shade, and salt-water tablets will be in place.
• Plant and Equipment to be provided with back-up alarms, lights, and all other applicable safety devices.
Toolbox talks will be recorded in traceable forms, which will include information on date, time, duration, details of
the topic, and signed attendance
TRAININGS
INDUCTION TRAINING
All staff and workers including subcontractors to be deployed to this project shall undergo safety training and
induction before deploying to work to site
A permit-to-work system is a formal recorded process used to control work which is identified as potentially hazardous. It is
also a means of communication between site/installation management, plant supervisors and operators and those who
carry out the hazardous work. An official document issued by the Issuer to the Recipient to carry out a specific work in a
restricted area. A work permit is an official record containing evil.
To ensure there are integrated procedures for issuing, receiving, transferring and closing of permits to work during the
installation, operation and maintenance of identified hazardous operations.
GENERAL REQUIREMENT
• Each Business line or project shall perform an overall risk assessment for every site, task and equipment to develop a risk
profile.
• Each Business line or project shall utilize the risk profile to develop work permit procedure to control and manage
the risks associated with the activities according to their risk rating.
• The work permit system shall include the following procedures:
• Work permit procedure
• Lock out Tag out Procedure
• Qualification, Training and Authorization Procedure
Each Business line or project shall ensure that the work permit system is reviewed and approved by industrial security sector
before the implementation.
HEAT STRESS
Heat stress at the workplace can be the cause of serious health issues:
• Heatstroke
• Dehydration
• Heat Cramps
• Heat Exhaustion
• Heat Rashes
• The Heat stress index must be closely monitored to provide the workforce with the proper information regarding rest time
and the amount of water they should be drinking.
• Once the heat index reaches the red limit, the work must be stopped immediately
Heat stress control
Plan your work, cover up and drink plenty of fluids
• Wear long sleeved shirts
• Wear a hat (if appropriate)
• Use sunscreen
• Plan heavier work during cooler periods
• Provide shade wherever possible
• Drink plenty of fluids (water, not soft drink and coffees)
• Take frequent short breaks/rotate tasks
• Exercise in the cooler part of the day – early morning, late afternoon/early evening
The HSE staff or foreman shall sound the alarm that is situated around the site from the designated location. HSE
Manager shall then send out the alert to the, Project Managers, Construction manager, Consultant and Client
representative.
The HSE Team, Site Engineers and Supervisors shall ensure all personnel secure and evacuate the work area and
proceed to the designated Assembly Point.
To secure the workplace the following should be undertaken if possible, without risk to personnel:
Whilst personnel are proceeding to the Assembly Point, the engineer for that area with the assistance of the HSE Dept. shall
systematically work through their area to ensure all personnel have evacuated.
When personnel have assembled, the Foreman/area supervisor shall undertake a roll call of all personnel under their control
and report findings to the Construction Manager.
If any personnel are found to be missing, then the foreman shall attempt to establish their last known location.
No person shall re-enter the workplace until:
a) Authorized by the HSE Manager;
b) It is determined that any search and rescue party shall be placed at risk;
All Medical staff in the area shall ensure they are ready and available to assist in any emergencies that arise.
No personnel shall re-enter the work area until authorized to do so by SBG Management.
COVID-19
Suspicious Case:
Any person presenting w i t h upper or lower respiratory symptoms, with or without temperature or those with
temperature over 37.5 or other symptoms.
Suspected Case:
Any person presenting with upper or lower respiratory symptoms “With or Without Fever”
Authority Notification:
If you are worried about symptoms, please call the MOH HOTLINE - 937. Do not go directly to your Medical Centre
or other healthcare environment, Stay at home. Project Emergency contact Number-(EOC) 0112127111
Follow on Action:
Instruct employees who worked within the immediate vicinity or directly interacted with the employee (e.g.
meetings, bus travel, and room share) to work from home and monitor their health, or to be isolated in camp if
labor, or returned to subcontractor, until confirmed that the person is clear or not. • If not clear the persons sent
home, isolated etc. must stay isolated working from home, or isolated in camp or home as per latest guidelines
protocol & to confirm not infected.
FIRE
The Person finding the fire shall raise the alarm by shouting “FIRE FIRE FIRE” and calling from assistance from
the Supervisor and fire wardens, any person when required.
Fight the fire: Only trained people may attempt to fight the fire. Should the attempt fail, a fire warden shall sound
the closest manual alarm (Sound for 1-2 Min).
16 Risk Assessment
Note- Refer to the Appendix-1 for Risk Assessment
17 Emergency Arrangements
All work permits shall be immediately cancelled in the event of an emergency. Upon returning to the work area new
permits shall be required.
• Technical Manager
• Construction Manager
• Site Engineer
• Site Supervisor
• Foreman
• Quality Engineer
• HSE Officer
• Store keeper
• Electrician
• Helpers
18.2 Responsibilities
18.2.5 Foremen
Foreman shall be responsible for the direct execution of works involved in the Installation process according to
the plan and shall directly control and give instruction to the working personnel. He shall also ensure that works
are performed with proper tools/equipment, PPE and good housekeeping around the working area and that all
equipment has been safety checked and registered in the log
18.2.9 Electrician
Electrician shall review the wiring diagrams and inspect the Electrical system and troubleshoot and repair in case
of any malfunctions noted. To ensure the installation adhere to local authority regulations
18.2.10 Helpers
Helpers shall be responsible for assisting the team during the Installation work
Appendix – 1
Risk Assessment
Section I -Enter general information about the site and job task.
Section II - Determine whether any of these operations apply to the job task to be performed. Make note of any special training, permit, certification, and risk assessment
requirements.
Section III - Identify any human/organizational factors that could impact the ability to perform the work safely.
1. Break the job down into steps - Be as specific as possible. Write each job step in a new row of column A (Activity/Step). It’s a good idea to leave an extra row between
steps in case you need them later. Add additional rows to the table as needed, or if completing the JSA on paper, print additional copies of the sheet to accommodate
all job steps.
2. Determine the hazards associated with each job step and write them in column B (Hazards). Use the examples of hazards provided below to trigger your thinking about
different types of hazards and energy sources.
3. List any control measures that will be taken to ensure that step is done safely in column C (Control Measures). Use the control measure examples and hierarchy provided
to trigger your thinking about different types of controls and their effectiveness at reducing risk. Controls toward the top of the table tend to be more effective at
minimizing the severity and/or likelihood of an event than the controls toward the bottom of the table. If this job involves a Life Crucial Operation, continue to step 4.
Otherwise, repeat steps 2-3 for each of the job steps identified, then proceed to step 8.
4. Considering the hazards involved and the control measures that will be in place, determine the worst credible severity of an incident that could result from this job step.
Use the severity table provided. Write the severity number in column D (Severity).
5. Considering the hazards involved and the control measures that will be in place, determine the likelihood that an incident will result from this job step. Use the likelihood
table provided. Write the likelihood number in column E (Likelihood).
6. Multiply the severity number by the likelihood number and enter the product in column F (Risk).
7. Consider the risk rating against the thresholds provided in the Overall Risk Ratings.
i. Very low and low risk ratings of 1-2. This level is generally considered acceptable provided that all control measures are applied.
ii. Medium risk ratings of 3-9. Medium risk requires a planned approach to control the hazard and applies additional controls if required. Action taken must be
documented on the risk assessment form.
iii. High and Very High-Risk ratings of 10-25. For all high and very high risk, Column G (Additional control measures) must be implemented to further reduce the risk
to a medium or low level. Such activities shall not be proceeded until applying additional control measures. The Construction Director/Manager or facility Manager
must personally review the activities with a High or Very High residual risk score and approve additional control measures by signing off the JSA.
8. Repeat steps 2-7 for each of the job steps identified.
Section IV - Provide the name, company, and title of those who prepared and reviewed/approved this form in the signature box provided. The Construction Director/Manager or
facility Manager must review and approve the additional control measures that have a High or Very High-Risk rating before proceeding the task. Additional space is also provided
for crew members to sign the JSA if desired.
Reference Table in completing Section III – Job Safety Analysis (Column B – Hazard)
Biological & Environmental Electrical Arc Chemical Gravity/Height Mechanical & Motion
Altitude Flash Buried Air Emissions Equipment Tipping/Collapsing Being Thrown Off/Under
Animal Bite/Sting Utilities Chemical Products Excavation/Trench Equipment
Blood-Borne Pathogens Damage to Leads/Cables • Carcinogenic Falling Objects Disintegration of Moving
Contaminated Food/Water Damage to Switches • Combustible/Flammable Floor Openings/Edges Components
Insect-Borne Disease Energized Circuits/Conductors • Explosive Grating Removed Driving/Vehicle Traffic
Pests Inadvertent Energization Lack • Toxic Inadequate Support Ejection of Workpiece/Debris
Poisonous Plants of Isolation/Grounding • Corrosive Lack of Access Ladders/Stairs Entanglement
Precipitation Missing/Damaged Insulation • Reactive Suspended Load Friction
Temperature/Humidity Overhead Lines Client/Process Chemicals Unstable/Insecure Materials Movement/Shifting
Unsanitary Conditions Overload of Circuits Lack of Containment Work Above/Below Others Moving Parts
Weather Stored Energy Leakage/Spills Work at Height/Fall Hazards Pinch/Crush Points
Wind/Turbulence (Batteries/Capacitors) Material Incompatibility Walking/Working Surface Projectiles
Pressure Water Near Electrical Conductors Produced/Disturbed by Work • Slippery Rotating Equipment
Abrasive Blasting Work Environment • Asbestos • Uneven Sharp Edges, Corners, or Points
Compressed Gases Cluttered • Lead • Obstructed Shearing Stored Energy
High Pressure Fluid Confined Space • Silica • Steep (Springs/Accumulators)
Pressure Testing Damaged Tools/Equipment • Welding Fumes • Moving/Swaying/Pitching Striking
Pressure Washing/Blasting Entrapment • Dust • Insufficient/Unstable Trapped Between Equipment and
Radiation Erosion Water Discharges Ergonomic Fixed Structures
Intense Light Hazardous Atmosphere Wastes Generated Awkward Postures/Movement Unexpected/Uncontrolled
Lasers • Oxygen Rich/Deficient • Hazardous Excessive Force/ Exertion Movement
Microwaves • Contaminants • Non-Hazardous Heavy/Awkward Load
Naturally Occurring Ignition Sources Sound Continuous Repetitive Motion
Radioactivity Radioactive Inadequate Ventilation Noise Intermittent Same Position
Material Poor Lighting/Glare Noise Extreme Vibration
X-Rays Restricted Access/Egress Noise Impact
Runoff Noise
Reference Table in completing Section III – Job Safety Analysis (Column F – Risk)
Section III – Job Safety Analysis Risk Assessment (Post Control Measures)
(D) (E)
(A) (B) (C) (F) (G) (H) (I) (J)
Seve Likeli
Activity/Step Hazards Control Measures Risk Additional Control measures Severity Likelihood Risk
rity hood
Access /Egress Unauthorized entry to site • Banksman in place for any awkward • Routes delineated with
reversing barriers; barriers secured
Injury to public • Mandatory PPE worn with sandbags where
• Driving with due care & attention necessary
Vehicle collision • Adherence to site safety signage • Excavations backfilled as
• Never block access and egress soon as possible
routes with materials and equipment • Barriers erected around
• Site tidiness maintained by cleaning up unattended excavations
during work, at end of day and (major) • Ensure all plant is secured
4 5 20 2 3 6
weekly to avoid slips and trips – Clean as against unauthorized
you go. operation; removed the
• No protruding nails allowed: all such nails keys & prevent access to
must be clawed out or hammered flat so the cab.
as to foot injuries
• Open excavations attended.
• Access to the site must be controlled to
ensure the safety of site employees and
visitors.
Loading & Falls from height • Operator trained to the approved third • When mounting or
unloading party company. dismounting the machine
Crushing • Vehicles should never be overloaded. the handholds and steps
Loads should be evenly distributed, must be used and must be
secured and not protruding beyond the maintained in safe
sides or back of the vehicle. condition.
• Reverse beeper and flashing beacon fitted. • Access roads will be
4 5 20 2 4 8
• All guards and covers to be in damped down during fine
position and secured. weather periods to
• Windows, lights, mirrors and camera lens prevent dust from rising.
to be kept clean at all times. • Where the operators
direct field of vision is
Laying of Entrapment due to fall/ • Operator trained to the Approved third • Reverse beeper, flashing
Pipes roll of pipe. party a s per the Construction beacon, CCTV and or
Regulations. mirrors fitted
Operators direct field of
• Vehicles should never be overloaded. • Defective skids removed
vision obscured by load
Loads should be evenly distributed, immediately from the
leading to contact with other
persons or plant.
secured and not protruding beyond line.
the sides or back of the vehicle. • Heavy duty gloves to be
Failure of lifting • The cab floor to be kept clean and worn by operatives
equipment. free from any obstacles which may handling skids.
affect the safe operation of the • All engines guards and
Inadequate supervision. Machine. covers to be in position
• Ground workers to wear Hi Visibility and secured.
Untrained Operatives
Vests at all times and Hard-Hats. • Windows, lights, mirrors
• Warning signs will be erected to alert 4 5 20 and camera lens to be 3 2 6
Use of mobile phones by
pedestrians of Unloading/Loading kept clean at all times
operators.
Operations.
Displacement of load • Traffic management must be in place
where loading/unloading is being
Person being struck by carried out on public
suspended pipe causing roads.
serious injury of harm. • Loads to be tipped only on suitably
level ground to prevent overturning
Defective and broken skids
of skip
causing crushing of limbs of
entrapment of body parts.
Manual Handling
Work at Height Fall of a person a distance • Take into accounts the principles of
• Inspections on equipment
liable of causing personal prevention when working at heights.
carried out (i.e., crowd
injury • Work at height must be adequately
control barriers,
Falls of persons off the planned and supervised
harnesses, fall arrest
edge of structures • Collective fall protection measures must 4 5 20 2 2 4
devices etc.)
be given priority
• Safe means of access to
• Trench boxes must have guard and mid
the work location provided
rails.
using ladders
Manual Handling Ligament strains. Muscle • Full training and instruction provided in both 4 3 12 • Weights marked on all 2 2 4
strains induction and on- going safety training. loads.
• Design out the need for manual • Lift smaller loads.
Fatigue handling where possible • Cutting pipes to length
• Mechanical aids used wherever • Mandatory PPE worn
Abdominal hernias. possible
Prolapsed/herniated • Workers adhere to guideline weights
discs. & to only lift what they are able to lift
• Assess the load
Paralysis.
Slips, Trips & Falls Cuts and bruises • Workplace tidiness maintained by
Laceration cleaning up during work, at
end of day to avoid slips and trips
Serious bodily injury
– Clean as you go. 4 4 16 2 2 4
• Vigilance from employees as to the
dangers from slips trips and falls.
Note: Insert additional rows or print additional sheets as necessary to accommodate all job steps.
Appendix – 2
Inspection & Test Plan
Responsibility
Activity No.
1 PRELIMINARY WORKS
Method Statement for Installation & Sanitary W aste and Vent PH Specification / Section - 220000 (General
1.3 Method Statement Submittal Approval Method Statement Submittal Once (Approval prior to start of activity) H R
Piping Requirement for Plumbing / Section -
221316 (Facility Storm Drainage Piping for
Pl um bi ng
2 MATERIAL INSPECTION
Material Inspection for PVC Storm Drainage Pipes, Fittings and Material Sizes / Dimensions PH Specification / Section - 220000 (General
Accessories Material Quantity Requirement for Plumbing / Section - Each Delivery
2.1 Material Inspection request (MIR) H H/W
Material Test certificate 221316 (Facility Storm Drainage Piping for
Country of Origin Pl um bi ng
3 EXECUTION OF WORKS
Sanitary Waste and Vent Piping Installation conforms the acceptance PH Specification / Section - 220000 (General Work Inspection request (WIR) /
3.1 Installation of PVC Storm Drainages Pipes, Fittings and Accessories Area Wise, IR to be Submitted for each Installation H H/W
criteria in accordance to Approved Shop Drawing / Material Submittal / Requirement for Plumbing / Section - Installation Checklist
Approved Method Statement / Red Line Drawings 221316 (Facility Storm Drainage Piping for
Pl um bi ng
4 TESTING REQUIREMENTS