Professional Documents
Culture Documents
Final Updated Pannah Gah Report 1
Final Updated Pannah Gah Report 1
June, 2021
4th Floor, 65- Trade Centre Block, Ayub Chowk, Johar Town, Lahore
042-99233177-91, info@dgmepunjab.gov.pk
Disclaimer
This report is based on the data provided by the relevant representative of
the relevant department. DG M&E disclaims, expressed or implied, the
accuracy or completeness of any information reported herein, and disclaims
and makes no pledge that the information in this document will fulfil any
of your particular purposes and needs. DG M&E does not undertake to
assure the performance of any individual Project or services by virtue of
this report.
The results of the beneficiary survey shows that the project intervention is
beneficial for needy people. There is some area of improvement for
sustainability of the intervention for the intended goals, it is recommended
to design & develop Standard Operating Procedures (SOPs) & capacity
building programs for the staff.
Page | ii
The project objective was to provide the shelter to 850 needy/destitute
people by construction of (05) Pannah Gah in different location of Lahore
however, the definition of needy/destitute people was not mentioned in the
PC-I furthermore, as per provided that the actual capacity of the
intervention is 588 number (Attached as Annexure-B) which is 69% of the
overall planned target that shows the project was over stated.
Page | iii
Table of Contents
Executive Summary ................................................................................................................................ ii
Section-1: INTRODUCTION & BACKGROUND ........................................................................ 1
1.1 Introduction ................................................................................................................................. 1
1.2 Project Description .................................................................................................................... 2
1.3 Project Objectives....................................................................................................................... 3
1.4 Project Activities ......................................................................................................................... 3
1.4.1 Project Design and Intervention ....................................................................................... 3
1.5 The Evaluation Report: Purpose and Structure ............................................................... 3
Section-2: EVALUATION METHODOLOGY ............................................................................... 5
2.1 Objective of Evaluation ................................................................................................................... 5
2.2 Methodology ....................................................................................................................................... 5
2.2.1 Evaluation Team ........................................................................................................................... 6
2.2.2 Field Visit and Data Collection Tools ..................................................................................... 6
2.2.3 BOS Recommended Sample Size ............................................................................................. 6
2.2.4 Questionnaire Design .................................................................................................................. 7
2.2.5 Development of Data Collection Tools for Civil works ...................................................... 8
2.2.6 Project Major Stakeholders ........................................................................................................ 8
2.2.7 Data Analysis and Reporting .................................................................................................... 8
2.3 Limitation of Data ............................................................................................................................ 9
2.4 Ethical Consideration ..................................................................................................................... 9
2.5 Copyright............................................................................................................................................. 9
Section-3: EVALUATION FINDINGS ......................................................................................... 10
3.1 Technical Assessment and Analysis ......................................................................................... 10
3.1.1 Project Design and Objectives ................................................................................................ 10
3.1.2 Major Deliverables & Procurement of Equipment/Items ............................................... 10
Section - 4 DATA ANALYSIS ............................................................................................... 12
4.1 Overall Analysis of all five w.r.t overall population and repeaters ................................. 12
4.2 Beneficiary Survey ......................................................................................................................... 15
4.3 Year wise Financial Detail ........................................................................................................... 26
Section – 5 OBSERVATIONS AND RECOMMENDATIONS ....................................................... 27
5.1 Observations: ............................................................................................................................ 27
5.2 Recommendations ................................................................................................................... 30
5.3 References .................................................................................................................................. 31
Photo Gallery ........................................................................................................................................... 32
Annexure A: HANDING OVER TAKING OVER DOCUMENT .............................................................. 36
Annexure B: CENTER WISE ACTUAL CAPACITY OF THE PANAGAHS ............................... 38
Annex-C-1: QUESTIONER FOR BENEFICIARIES ....................................................................... 39
Annex-C-2: QUESTIONER FOR THE MANAGEMENT................................................................ 44
Annex-D: BOS RECOMMENDED SAMPLE ............................................................................................ 47
Annex-E: DETAILS OF SANCTION AND VACANT POSTS ................................................................. 49
Annex-F-1: DETAIL OF PROCURED ITEMS .......................................................................................... 50
Annex-F-2: WORK ORDER REVENUE COMPONENT ITEMS ............................................................. 51
Page | iv
List of Tables
Table 1: Location of Centers with accommodation capacity ............................................ 1
Table 2 Project Summary .......................................................................................................... 2
Table 3 Project Objectives ......................................................................................................... 3
Table 4: Detail & Task of Evaluation Team ........................................................................................ 6
Table 5: SAMPLE SIZE FOR THE PANNAH GAHS BENEFICIARIES ........................................................ 7
Table 6: List of Officers Interviewed....................................................................................... 8
Table 7: Assessment of Project Objectives ......................................................................... 10
Table 8 : Verification of Major Deliverables....................................................................... 10
Table 9 Year wise Financial Details ..................................................................................... 26
List of Graphs
Graph 1: No. of Visits at Pannah gah During One Month ........................................... 12
Graph 2: No of Visitors during One month ....................................................................... 12
Graph 3: No. of days Stayed vis-avis Visitors................................................................... 13
Graph 4: No. of Days Stayed vis-a-vis Visitors [Total] ................................................... 13
Graph 5: Centre Visited by one visitor during one month ........................................... 14
Graph 6: Male & Female Visitors ......................................................................................... 14
Graph 7: Gender wise Residents .......................................................................................... 15
Graph 8: District wise Residents .......................................................................................... 15
Graph 9: Sources of Information about Pannah gah ..................................................... 16
Graph 10: Reason for come to Lahore ................................................................................ 16
Graph 11: Reason to Stay at Pannah gah ......................................................................... 17
Graph 12: Occupation of Residents..................................................................................... 17
Graph 13: Monthly income of residents ............................................................................. 17
Graph 14: Visit of Pannah gah .............................................................................................. 18
Graph 15: Stay other than this Center............................................................................... 18
Graph 16: Stay at other Pannah Gah Previously ............................................................ 18
Graph 17: Key Identification required for Entrance ....................................................... 19
Graph 18: Process of lodging and boarding ...................................................................... 19
Graph 19: Parking ..................................................................................................................... 19
Graph 20: Sources of Transportation ................................................................................. 19
Graph 21: Quality of Food ...................................................................................................... 20
Graph 22: Quantity of Food ................................................................................................... 20
Graph 23: Availability of Electricity & Drinking Water ................................................. 20
Graph 24: Availability of Bed linen ...................................................................................... 21
Graph 25: Cleanliness of Bed linen ..................................................................................... 21
Graph 26: Cleanness of Rest rooms .................................................................................... 21
Graph 27 : Behavior of People ............................................................................................... 22
Graph 28: Drugs allowed in Pannah gah........................................................................... 22
Graph 29: Harassment, Child Sexual Abuse & Human Trafficking ......................... 23
Graph 30: Behavior of the staff ............................................................................................. 23
Graph 31: Security of female passengers .......................................................................... 24
Graph 32: Satisfaction of entry and exit ............................................................................ 24
Graph 33: Entry Exist Restrictions ..................................................................................... 25
Graph 34: SOP's regarding COVID-19................................................................................ 25
Page | v
Graph 36: Preference to Pannah gah .................................................................................. 25
Graph 35: Recommend others to stay at Pannah gah .................................................. 25
Graph 37: Year Wise Financial Details ............................................................................... 26
List of Figures
Figure 1: Evaluation Methodology ......................................................................................... 5
Figure 2: Registration counter ......................................................................................................... 32
Figure 3: DGM&E team during survey ............................................................................................. 32
Figure 4: Dinning Hall....................................................................................................................... 32
Figure 5: View of Beds ..................................................................................................................... 32
Figure 6: Water Cooler .................................................................................................................... 32
Figure 7: wash rooms ...................................................................................................................... 32
Figure 8: Mattress without leather cover........................................................................................ 33
Figure 9: Repair work under progress ............................................................................................. 33
Figure 10: Room reserved for the labor .......................................................................................... 33
Figure 11: Blind Protestors .............................................................................................................. 33
Figure 12: Difference of height ........................................................................................................ 33
Figure 13: Expired fire extinguisher ................................................................................................. 33
Figure 14: Expired Medicine ............................................................................................................ 34
Figure 15: view of crack in wall........................................................................................................ 34
Figure 16: view of seepage .............................................................................................................. 34
Figure 17: Broken Cover .................................................................................................................. 34
Figure 18: Fire incident .................................................................................................................... 34
Figure 19: View of Water tank and Pipe .......................................................................................... 34
Figure 20: view of Crack .................................................................................................................. 35
Figure 21: Missing portion of fence ................................................................................................. 35
Figure 22: un-operational water cooler .......................................................................................... 35
Figure 23: Paint ................................................................................................................................ 35
Figure 24: Poor condition of mattresses ......................................................................................... 35
Figure 25: Evaluation Team With Project stakeholders .................................................................. 35
Page | vi
ACRONYMS
DC Director Coordination
Page | vii
Section-1: INTRODUCTION & BACKGROUND
1.1 Introduction
Social Welfare is a supportive activity, designed to give assistance in respect
of social issues that prevent individuals, families and group from achieving
a minimum desirable social wellbeing with dignity. It has universally been
recognized as a process of social development through which the
potentialities of people are stimulated to promote their effective
participation in the process of Social change for improvement of quality of
life.
As the inflation rate is increasing day by day. Lahore being the capital city
of the province, a number of people is traveling towards it for earning of
better life style. Most of the population out of them are destitute, needy and
poor and cannot afford the living cost in the hotels. The provision of cost
free shelters is responsibility of government.
Social Welfare department is one of prime Department which is dealing with
the special segment of the society with keen interest according to the need
of that part of society. The Department has many institutions with the
mandate to provide shelter, food, and other services. However, it is need of
time to provide facility where needy/poor/destitute persons who travel from
other cities to Lahore and take shelter on road sides and parks to spend
one night and move on at morning. , A sizable population for the search of
labor, employment or other purposes move to Lahore but in case of
disappointment they neither have any place to live not they have resources
to acquire rented premises for temporary shelter. Resultantly they are
compelled to spend their nights on footpaths, parks and other public
places. This will exhibit pathological social symptoms like drug abuse,
alcoholism, crime, vandalism and other deviant behavior.
Under the directions of the Chief Minister Punjab five Pannah gah establish
at different locations in Lahore to cater the needs of the poor and destitute,
who moved from different cities to Lahore.
ADMINISTRATIVE STRUCTURE
Five buildings are constructed by Lahore Development Authority on
different five locations of Lahore, detail mentioned in below table:
Table 1: Location of Centers with accommodation capacity
Capacity to
Sr. Site Measurement accommodate the
No beneficiaries
Data Darbar
2 Kanal 144
1
Chowk
1|Page
Fruit and Vegetable
3 Market, Badami 100
One Kanal
Bagh
All the pannah gah are comprising two stories and contain open lawns and
control room for check and balance to facilitate both public and authorities
to ensure smooth operation of the facility.
The five pannah gah are accommodating 588 travelers in full capacity at a
time including females and males in separate portions. The food is being
arranged through charity. The timing of all pannah gah is from 06:00 PM
to 09:00 AM.
1.2 Project Description
The project was proposed with the following project description.
Table below presents the summary of the project:
Table 2 Project Summary
Sponsoring
Social Welfare and Bait-ul-Maal
Agency/Department
i. Lahore Development Authority (LDA),
Executing Govt. of the Punjab
Agency/Department ii. Social Welfare and Bait-ul-Maal,
Govt. of the Punjab
i. Social Welfare and Bait-ul-Maal,
O&M Govt. of the Punjab
Agency/Department: ii. Communication & Works, Govt. of
the Punjab
Project Location Lahore
Original: 23-10-2018
Approval Date/Year
Revised: 02-01-2019
2|Page
Actual Start Date November 2018
Original: June 2020
Planned End Date
Revised: June 2021
Actual End Date In-Progress
No. of Revisions 01
4|Page
Section-2: EVALUATION METHODOLOGY
5|Page
2.2.1 Evaluation Team
For the Evaluation of this project, the Director General (M&E) has assign
the project to Ms. Wajeeha Javed Research Analyst and constituted the
following teams for completion of the assignment on time:
Table 4: Detail & Task of Evaluation Team
Sr. No Description Members
6|Page
of statistics (Annexure-D-1 & D-2) selected the 309 of beneficiaries for the
telephonic survey in which 79 % those beneficiaries selected which stayed
first time and 19 % repeaters were selected for the said purpose. For
telephonic survey 309 beneficiaries who visited on most recent period i.e 1st
June, 2021 to 7th June 2021 were selected through systematic random
sampling methodology and ten beneficiaries for each center interviewed on
spot (17-18 June, 2021) as per the recommended methodology. As shown
in table 04.
General Bus 38 38 38 7
3
Stand
7|Page
randomly verified before entering the same on SPSS data sheet. For
analysis of the data, SPSS software (latest version) was used.
2.2.5 Development of Data Collection Tools for Civil works
The data collection instruments (Annex-C) were developed before the
execution for the field visit.
2.2.6 Project Major Stakeholders
Following are the Major Stakeholders of the Project:
Table 6: List of Officers Interviewed
Sr.
Name Designation Department Contact Nos.
No.
1. Mr. Mubasher Javaid Divisional Director 0301-4422024
Social Welfare &
2. Mr. Amjad Fakhir Deputy Director Bait-ul-Maal 0333-6145076
Social Welfare Department
3. Mr. Haseeb-ur Statistical Officer 0303-4046394
Rahman
4. Mr. Abdul Salam Deputy Director 0346-6853922
Lahore
Engineering
Development
5. Deputy Director
Mr. Noman Mohsin Authority 0323-4830719
Engineering
6. In charge Fruit
Ms. Aminea Sahar 0335-4459981
Market Pannagah
7. MSO, Services
Ms. Ayesha Javaid 0331-4584356
Hospital Lahore
8. Rana Muhammad Incharge Railway
Social Welfare & 0335-4270318
Ghalib Station Pannagah
Bait-ul-Maal
9. Incharge Bus
Mr. Mohammad Department
Stand (Lorri Adda) 0321-4361963
Fayaz
Pannagah
10. Incharge Data
Misbah-ul-Zainab 0300-4780940
Darbar Pannagah
11. Warden, Data
Mr. Qadeer Ali 0341-6726372
Darbar Pannagah
8|Page
DGM&E, and after incorporation of their comments/feedback, the Report
was finalized.
2.3 Limitation of Data
The copies of following project documents were not provided to the
Evaluation team.
9|Page
Section-3: EVALUATION FINDINGS
This section presents the Evaluation findings, based on the data collected
through various quantitative and qualitative sources outlined above.
3.1 Technical Assessment and Analysis
The following major assessment parameters/indicators were used:
• Assessment of project design and achievements of project objectives
• Assessment of construction performance
• Assessment of procured items
3.1.1 Project Design and Objectives
The Project design and objective assessments are shown in the Table
below;
Table 7: Assessment of Project Objectives
Sr.
Project Objectives Assessment
No.
Provision of shelter to the 850 The Actual capacity of the
destitute/needy people daily intervention is 588 number
that has no place to stay in (Attached as Annexure-B) which is
01. Lahore during night i.e. from 69% of the overall planned target
06:00 PM to 09:00 AM. that shows the project was over
stated. Moreover, the center
management not follow the official
timing i.e 6:00 PM to 09:00 AM.
10 | P a g e
Completed (100%), Substantially
Completed (>50%)
Physical Activities Unit Partially Completed (≤50%), Not Started
& Targets (0%)
C SC PC NS Remarks
Recruitment of 15/59 staff positioned
staff 01 filled till the time of visit
√
Job detail attached as
Annexure-E
Procurement of 24/27 items were
01
machinery and √ procured. detail shown
Equipment Job
as Annexure –F-1
Purchase of √ Items procured as
01
Furniture and planned detail shown
Fixture Job
as Annexure –F-1
11 | P a g e
Section - 4 DATA ANALYSIS
The graph shows that 9838 passengers availed the facility in the one month
(07-05-2021 to 07-06-2021) In which 37.7 % passengers visited data
darbar center for stay furthermore 29.1 %, 18.4%, 14.4% & 0.4 persons
stayed at Railway station, thokar niaz baigh , fruit market Lahore & Bus
stand (Lari Adda) respectively.
Fruit Market
No. of Visitors During One Month
Lahore, 278, 8.5% Larri Adda
Lahore, 18, 0.5%
Thokar Niaz Baig
Lahore, 508,
15.5%
Data Darbar
Lahore, 1,448,
44.1%
Railway Station
Opposite Hafiz
Hotel,Lahore,
1,030, 31.4%
No. of Days
Stayed vis-a-vis Visitors
Railway Station
Opposite Hafiz
Fruit Market
20-31, 8 , 0.2%
10-19, 63 , 1.5%
13 | P a g e
The Graph shows that number of person who visited Panna gah repeatedly.
In which 4071 persons stayed 1-9 days at Panna gah which is 98.3% of
total repeaters, however, 63 persons stayed at panna gah 10-19 days which
is 1.5 % of total repeaters and 8 persons stayed for 20-31 days in Panna
gahs which are 0.2% of total repeater’s.
Center(s) Visited by One Visitor During One Month
4; 52 ; 2%
3; 169 ; 5% 5; 0 ; 0%
2; 367 ; 11%
1; 2,694 ;
82%
1400 949
1200
1000
800 494
600 277
400
200 75 1 18 81 14
0
Data Fruit Railwa Thokar Data Fruit Larri Railwa Thokar
Darbar Market y Niaz Darbar Market Adda y Niaz
Lahore Lahore Station Baig Lahore Lahore Lahore Station Baig
Opposi Lahore Opposi Lahore
te Hafiz te Hafiz
Hotel,L Hotel,L
ahore ahore
M F
Total 1373 277 949 494 75 1 18 81 14
14 | P a g e
The graph shows that in one month 1373 male and 75 females visited the
Data Darbar center, in fruit market 277 male and 01 female visited the
center, in Railway Station 949 males and 81 female passengers visited the
center, in Thokar Niaz Baigh 494 males and 14 females passengers stayed
& In Bus Stand only 18 female stayed at the panna gah.
4.2 Beneficiary Survey
To analyze the performance of Pannah gah, a beneficiary survey was
conducted through a well-designed questionnaire (Annex-C). The result
survey are given below.
Gender
100.0 95.2
80.0
Percentage(%)
60.0 Male
40.0 Female
20.0
4.8
0.0
12.0
10.8
District Names
10.0
8.0
6.0
Percentage(%)
4.8
4.8
6.0
3.6
3.6
3.6
3.6
3.6
3.6
3.6
3.6
4.0
2.4
2.4
2.4
2.4
2.4
2.4
2.4
2.4
2.4
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
2.0
0.0
Mandibahawa…
Rahim yar…
Rahim Yar…
Sargodha
T T Singh
Jhang
Malakand
Okara
Chichawatni
Kasur
Lodran
Mian Chanuu
Mianwali
Multan
Bahawalnager
Muzafargarh
Pakpattan
Gujrat
Rajanpur
Swat
Wah cantt
Peshawar
Quetta
Samundari
Bahawalpur
Hafizabad
Faisalabad
Gujranwala
Karachi
khanewal
kybar agency
Mardan
Vehari
Lahore
Abottabad
farooqabad
Fateh Kot
Narowal
Hyderabad
Laki Marwat
15 | P a g e
Sources of Information about Pannha gah
35.0
28.9
30.0 27.7
Friend
25.0
Family
Percentage(%)
19.3
20.0 Bill boards
0.0
This graph shows that 27.7% of beneficiary came to Lahore for search
employment and 26.5% beneficiary came to search labor and 20.5% of
beneficiary came to for other purpose.
16 | P a g e
What was the reason to stay at Pannah gah
80.0 74.7
70.0
60.0 No residence in Lahore
Percentage (%)
20.0 Business
1.2 1.2
1.2 1.2 Driver
2.4
1.2
15.0 1.2 electrical worker
2.4 1.2
1.2 1.2 Electrician
10.0
6.0 2.4 Employee
5.0 3.6
2.4 2.4 2.4 Factory Worker
1.2 1.2
1.2
1.2 1.2
1.2 1.2
1.2
1.2 1.2 1.2
Govt Job (Teacher)
0.0
Monthly Income
12000-20000 20001-25000 25001-30000 31000 & above NA
35 31
30
25 21
Income
20 17
15 11
10
5 3
17 | P a g e
The beneficiaries were further asked about their monthly income. 31%
beneficiaries response that their per month income bracket Rs.12000-
20000 while 21% beneficiaries response that their monthly income
bracket Rs. 20001-25000 and 17% beneficiaries response that their
income bracket 31000 & above.
Visits of Pannah gah
28.9%
50.6%
6.0%
14.5%
60.0
Percentage(%)
Graph 16: Stay at other Pannah Gah Graph 15: Stay other than this Center
Previously
The beneficiaries were more asked about they stayed at other station in this
response 65.1% beneficiaries replied that no stayed at other station while
34.9% beneficiaries’ response that they stayed previously at other station.
Furthermore, when asked to specify the center and reason, 16.9%
respondent response that they stayed railway station previously while 9.6%
respondent response that they stayed fruit & vegetable market previously.
18 | P a g e
Identification
70.0 60.2
60.0
Percentage(%) 50.0
40.0
30.0 25.3
20.0
8.4 6.0
10.0
0.0
38.6
Percentage(%)
40.0
30.0
20.0
10.0 4.8
2.4
0.0
0.0
Somewhat Satisfied Neutral Somewhat Dissatisfied
Satisfied Dissatisfied
The beneficiaries were asked about that they comfortable with the boarding
& lodging process at pannah gah. In this regard, 54.2% beneficiaries
respond neutral, while 38.6% beneficiaries respond satisfied with the
process of lodging and boarding.
Transportation Parking
51.8 39.8
60.0
50.0
Percentage(%)
8.4 NA 27.7
40.0
Percentage(%)
30.0
Outside the premises 4.8
20.0
10.0 67.5
Inside the premises
0.0
Local Transport Personal Vehicle NA
0.0 20.0 40.0 60.0 80.0
Percentage(%)
Neutral 1.2 50.0
Percentage(%)
The beneficiaries were asked about the quality and quantity of food in this
regard, majority of the beneficiaries 59% replies that they were somewhat
satisfied with the quality of food whereas 39.8% replied that they were
satisfied and 1.2% replied that they were dissatisfied with the quality of
food. Further, quantity of food was also gauged. It was observed that 86.7%
beneficiary claim that they were satisfied with the quantity of food and 4.8%
replied that they were somewhat satisfied with the quantity of food.
60.0 Satisfied
50.0 Neutral
40.0 Somewhat Dissatisfied
30.0 Dissatisfied
20.0
10.0 2.4 1.2 1.2 1.2
0.0
100.0 85.5
Percentage(%)
60.0
Neutral
40.0 Somewhat 50.0
7.2 Dissatisfied
20.0 6.0 0.0
Dissatisfied
1.2 6.0 6.0 2.4
0.0 0.0
Graph 25: Cleanliness of Bed linen Graph 24: Availability of Bed linen
90.0 85.5
80.0
70.0
Percentage(%)
60.0
50.0
40.0
30.0
20.0 12.0
10.0 2.4 0.0 0.0
0.0
21 | P a g e
Behavior of People
90.0 84.3
80.0
70.0
Somewhat Satisfied
60.0
Percentage(%)
Satisfied
50.0
Neutral
40.0
Somewhat Dissatisfied
30.0
Dissatisfied
20.0
7.2 6.0
10.0 2.4 0.0
0.0
86.7
100.0
80.0
Percentage(%)
60.0
9.6
40.0 3.6
20.0
0.0
Yes No NA
The beneficiaries were inquired about the drugs were allowed in pannah
gah. In this regard 86.7% beneficiaries answer back that drugs were not
allowed in the premises of pannah gah and 9.6% beneficiaries were replied
that drugs allowed in premises of pannah gah however 3.6% respondents
not responded on the question.
22 | P a g e
Harrasment, Child Sexual Abuse &Human Trafficking
100.0
100.0
Percentage(%)
80.0
60.0
0.0
40.0 0.0
20.0
0.0
Yes No NA
60.0 Satisfied
50.0 NA
40.0 Somewhat Diss atisfied
30.0 Diss atisfied
20.0
10.0 3.6 1.2 0.0 0.0
0.0
The beneficiaries were asked behavior of the staff at pannah gah in this
concern, majority 95.2% of the beneficiaries respond that they were
somewhat satisfied with the behavior of the staff while 1.2% beneficiaries
respond that they were satisfied with the behavior of the staff at pannah
gah.
23 | P a g e
Security of female passengers
Dissatisfied 3.6
Neutral 4.8
Satisfied 80.7
60.0
Somewhat Satisfied
50.0
Satisfied
40.0
Neutral
30.0
Dissatisfied
20.0 13.3 12.0
10.0
1.2
0.0
24 | P a g e
Are you allowed to go outside in case of emergency
66.3
70.0
60.0
50.0
Percentage(%)
40.0 33.7 Yes
30.0 No.
20.0
10.0
0.0
70.0
60.0
Percentage(%)
50.0
Yes
40.0
No
30.0 24.1
20.0
10.0
0.0
60.0 7.2
Percentage(%)
50.0 No
Yes
40.0 92.8
30.0 No
20.0 14.5
Yes
10.0
0.0
0.0 20.0 40.0 60.0 80.0 100.0
25 | P a g e
The beneficiaries were asked about the prefer to stay next time at pannah
gah, majority 85.5% beneficiaries respond that yes they were prefer to stay
at pannah gah next time, then 14.5% beneficiaries respond they were no
prefer to stay at pannah gah next time. Further the beneficiaries asked
about they were recommended other to stay at pannah gah. 92.8%
beneficiaries replied that they were recommend other to stay at pannah gah
and 7.2% beneficiaries replied that they were not recommend to other to
stay at pannah gah.
300
250 16.01
13.65
200
16.01
150
20.77 13.65
100
50 27
16.01
0
0
2018-19 2019-20 2020-21 Total
26 | P a g e
Section – 5 OBSERVATIONS AND RECOMMENDATIONS
5.1 Observations:
Evaluation of the project had revealed many facts and figures about the
project. The observations regarding overall project activities are given in
ensuing paragraphs: -
General Observation
01. The SOPs for Pannah gah are still not framed and approved by the
department and non-availability of SOPs is creating difficulties in
operational matters for the management of centers.
02. The project objective was to provide the shelter to 850 needy/destitute
people through this intervention but the department remained unable
to achieve the planned objective as the actual capacity of the Pannah
gah was found 588 (Annexure-B) furthermore, the definition of
needy/destitute people was not mentioned in the PC-I.
03. It was planned that the Auqaf department shall provide the Meals
(dinner and breakfast) to the passenger/resident but it was observed
that meal is being provided through donation. In case of non-
availability of donation how the department will arrange the meal as
the department still has not contacted the Auqaf department for this
purpose.
04. It was planned to procure 800 number mattress with leather covers
but at the time of physical verification no leather cover were found
present in all centers as shown in the figure No 8 of the photo gallery.
05. The capital portion of the project was executed by the LDA and handed
over to the Social welfare and Bait-ul-Maal department on 17-07-2019,
however, the maintenance of the project was assigned to the C&W
department. During visit, it was found that maintenance works are
being carried out at all the sites (as shown in the figure No 8).
Furthermore, it was observed that (04) four out of (05) five centers were
found functional. Moreover, the centers are running in less capacity
due to maintenance works of buildings as some rooms are being used
by the labor for their stay and storage of their material as shown in the
figure No 10 & 23 of the photo gallery.
06. The Bus Stand (larri Adda) Pannah gah was not fully operational as
the said center was reserved/occupied for the blind protestors since
18-Nov-2019 till the date of visit i.e. 18-06-2021(as shown in the figure
no 11) due to that only female passengers are allowed to stay at the
said center, the documented proof for stay of protestors was not shared
by the department.
07. The official timing for stay at Pannah gah is 6.00 PM to 9.00 AM as
approved in PC-I document but it was found during telephonic survey
and on spot visit that the pannah gah management evacuates the
residents before time i.e. 6:00AM.
27 | P a g e
08. The height of the rooms was not appropriate for bunk beds as the
person who is staying at top bed can be injured due to movement of
ceiling fan as shown in the figure no. 12. Same incidents have been
reported by the pannah gah management that shows the lack of
planning.
09. Most of the fire extinguishers were found expired as shown in the
figure No 13.
10. The dispensary facility was provided by the district administration at
some pannah gah and expired medicine was observed at Fruit &
Vegetable market. As shown in the figure no 14.
11. The fire incident due to substandard electric works were highlighted
by the management of the centers.
THOKAR NIAZ BAIGH CENTER
12.The female attendant was not present at the time of visit. However,
female residents were there for stay purpose.
13.As reported by the passengers and observed by the evaluation team
that the center staff kept the original CNIC of the passenger during the
stay at Pannah gah, this action of the staff is discouraging the
passengers.
14.Minor vertical crack in the wall of pannah gah was observed at site as
shown in the figure No 15 of the photo gallery.
15.Seepage at some section of the Pannah gah outside the toilet block and
broken cover of the manhole was observed at site. As shown in the
figure no 16 &17 of the photo gallery.
16.The drain for waste water of the laundry was not properly designed due
to this it was observed that the water was flowing freely from tuff pavers.
RAILWAY STATION
17. The female attendant was not present at the time of visit. However,
female residents were there for stay purpose.
BUS STAND (LARRI ADDA)
18. The said center was reserved for the blind protestors and they denied
for provision of the feedback.
19.Some fire incidents due to high voltage were accrue at said center as
informed by the center In-charge which was also observed by the
evaluation team as shown in the figure no 18 of the photo gallery.
DATA DARBAR STATION
20. One turbine of the center was found non-functional and the center
staff filling the water tank with the help of the plastic pipe.
21.The level of the barbed wire was found higher at site due to this the
barbed wire is unable to meet the security measures furthermore minor
settlement in the pavers was also observed at site as shown in the figure
No 19 of the photo gallery.
FRUIT & VEGETABLE MARKET
22.The DGM&E team visited the site at 6:25 AM but at the time of visit all
the passenger were evacuated from the said center (while the time and
28 | P a g e
date of the visit was properly communicated) due to this evaluation
team remained unable to get the feedback of the passengers on spot.
23.Minor cracks passing from the lintel of the window was observed at site
as shown in the figure no 20 of the photo gallery.
24. Barbed wire at some sections was found missing at site as shown in
the figure no 21 of the photo gallery.
25.The water cooler of the same center was found out of order at site as
shown in the figure no 22 of the photo gallery.
26.The laundry facility was partially suspended at the center due to repair
purpose and the same was being used for the storage of the material as
shown in the figure 23 of the photo gallery.
27.Mattresses and ply sheets of beds were found in poor condition.
28.Bed sheet covers were not provided on all mattresses.as shown in the
figure no 24 of the photo gallery.
29.Printer of the said center was found out of order.
29 | P a g e
5.2 Recommendations
1. With reference to the observation no 1: SOPs should framed on priority
basis and should be implemented in all centers for smooth
functionality of the project.
2. With reference to the observation no 2, 3 & 4: Client department may
justify in this regard.
3. With reference to the observation no 5: Considering the importance of
the project the renovation works should be completed on urgent basis
and the labor not to be allowed to stay inside the premises.
4. With reference to the observation no 6: Documented proof should be
shared with the evaluation team.
5. With reference to the observation no 7: the concern staff should obey
the official timing in true letter and spirit.
6. With reference to the observation no 8: Executing agency should
consider this factor in upcoming projects.
7. With reference to the observation no 9&10: All the lifesaving equipment
and medicine should be maintained as per the SOPs.
8. With reference to the observation no 11: Proper assessment of the
electric works should be carried out to avoid any incident in future.
9. All the highlighted defects regarding the civil works should be rectified.
10. The department may establish MIS system for the Pannah Gah which
contains information regarding blood group, reason to come Lahore,
reason to stay at pannah gah, marital status and profession/source of
income.
11. The registration system of pannah gah must be linked with the hotel
eye software to avoid any unforeseen activity meanwhile, the detail of
the residents should be shared with the police department on daily
basis. In addition to it, the biometric system should be installed in all
centers.
12. The shed for security guards should be provided in all center.
13. There should be some separate place for religious activities of the
passengers.
14. Laundry facility should be allowed to the resident considering their
needs.
30 | P a g e
5.3 References
31 | P a g e
Photo Gallery
32 | P a g e
Figure 8: Mattress without leather cover Figure 9: Repair work under progress
Figure 10: Room reserved for the labor Figure 11: Blind Protestors
33 | P a g e
Figure 14: Expired Medicine Figure 15: view of crack in wall
Figure 18: Fire incident Figure 19: Height of barbed wire and view of
settlement
34 | P a g e
Figure 21: Missing portion of fence
Figure 20: view of Crack
35 | P a g e
Annexure A: HANDING OVER TAKING OVER DOCUMENT
36 | P a g e
37 | P a g e
Annexure B: CENTER WISE ACTUAL CAPACITY OF THE PANAGAHS
38 | P a g e
Annex-C-1: QUESTIONER FOR BENEFICIARIES
“ESTABLISHMENT OF MUSAFIR KHANA AT DIFFERENT LOCATION OF LAHORE
CITY”
Date: _______________
Time: _______________
Quest. No: _________
Questionnaire for Beneficiary
10. What are the key identification required for boarding and lodging?
I. Name
II. Address
III. CNIC
IV. Picture
V. Mobile number
VI. Emergency contact
VII. Blood Group
VIII. All above
11. Are you comfortable with the boarding & lodging process at pannah gah?
I. Somewhat Satisfied
II. Satisfied
III. Neutral
IV. Somewhat Dissatisfied
V. Dissatisfied
40 | P a g e
II. Personal Vehicle (If Personal vehicle then ask 13 No.)
15. Are you satisfied with the quality of food at pannah gah?
i. Somewhat Satisfied
ii. Satisfied
iii. Neutral
iv. Somewhat Dissatisfied
v. Dissatisfied
16. Are you satisfied with the quantity of food at pannah gah?
i. Somewhat Satisfied
ii. Satisfied
iii. Neutral
iv. Somewhat Dissatisfied
v. Dissatisfied
17. Are you satisfied with the availability of electricity and drinking water facilities?
i. Somewhat Satisfied
ii. Satisfied
iii. Neutral
iv. Somewhat Dissatisfied
v. Dissatisfied
18. Are you satisfied with the availability of Beds, mattresses, pillows and bed
sheets in pannah gah?
i. Somewhat Satisfied
ii. Satisfied
iii. Neutral
iv. Somewhat Dissatisfied
v. Dissatisfied
19. Are you satisfied with the cleanliness of Beds, mattresses, pillows and bed
sheets in pannah gah?
i. Somewhat Satisfied
ii. Satisfied
iii. Neutral
iv. Somewhat Dissatisfied
v. Dissatisfied
41 | P a g e
20. Are you satisfied with the cleanness of rest rooms (wash rooms)?
i. Somewhat Satisfied
ii. Satisfied
iii. Neutral
iv. Somewhat Dissatisfied
v. Dissatisfied
21. Are you satisfied with the inside environment of pannah gah (behavior of people)?
i. Somewhat Satisfied
ii. Satisfied
iii. Neutral
iv. Somewhat Dissatisfied
v. Dissatisfied
22. Is the drugs are allowed in the premises of the Pannah gah?
i. Yes
ii. No
iii. (If yes then please specify) ______________________________
25. Are you satisfied with the security of female passenger/ resident?
i. Somewhat Satisfied
ii. Satisfied
iii. Neutral
iv. Somewhat Dissatisfied
v. Dissatisfied
26. Are you satisfied with the entry and exist restriction in pannah gah?
i. Somewhat Satisfied
ii. Satisfied
iii. Neutral
iv. Somewhat Dissatisfied
v. Dissatisfied
42 | P a g e
27. In any case of emergency, are you allowed to go outside?
I. Yes
II. No (if no please specify)
________________________________________________________________
28. Is the COVID-19 SOPs are being followed by the center?
i. Yes
ii. No
________________________________________________________________
Name of Interviewer
Signature
____________________________________ _______________________
***********************************************
43 | P a g e
Annex-C-2: QUESTIONER FOR THE MANAGEMENT
Date: ____________
Time: ____________
QUESTIONNAIRE FOR MANAGEMENT
Name of the Respondent ________________________ Designation _____________________
Contact # _____________________ Center ________________ Department Social Welfare & Bait-
ul-Maal
44 | P a g e
8. For how many days passenger can stay in pannah gah?
I. One night
II. Two night
III. Daily
IV. Other
9. Do you accommodate repeaters?
I. Yes
II. No
10. Source of meals?
I. Auqaf Department
II. Private Person
III. Donation
11. Is the basic medical facility available?
i. Yes
ii. No
12. Is there any In and Out restriction after getting registered in pannah gah?
I. Yes
II. No
13. Is the pannah gah full occupied at night?
I. Yes
II. No
14. What is the actual Capacity of the pannah gah?
__________________________________________
45 | P a g e
V. Dissatisfy
21. What are the female security measure regarding their safety if they stay?
________________________________________________________________
________________________________________________________________
________________________________________________________________
________________________________________________________________
22. What will you do if the number of persons came more than the actual
capacity?
________________________________________________________________
________________________________________________________________
________________________________________________________________
23. What are the problems /challenges /issues raised during the service hours?
________________________________________________________________
________________________________________________________________
________________________________________________________________
24. Any recommendations for the improvement?
________________________________________________________________
_________________________________________________________________
*******************************
46 | P a g e
Annex-D: BOS RECOMMENDED SAMPLE
47 | P a g e
48 | P a g e
Annex-E: DETAILS OF SANCTION AND VACANT POSTS
Sr. Name of the Post with Sanctioned Filled Post Vacant Post Recommended
No BPS post in PC-I for SNE
1 Warden
5 3 2
(BPS-11)
2 Junior Clerk
5 2 3
(BPS-11) To be decided
3 Attendant 19 9 10 in ECM
4 Sweeper 12 0 12
5 Security Guard 18 0 18
Total 59 14 45
49 | P a g e
Annex-F-1: DETAIL OF PROCURED ITEMS
Sr. Description Quantity as Per Actual Remarks
No PC-I Achievement
Procurement of Machinery & Equipment
1 Desktop Computers Procured as
10 Nos. 10 Nos.
planned
2 Electrical Water Cooler 17 Nos. 14 Nos.
Less Procured
Total 27 Nos. 24 Nos
Procurement of Furniture & Fixture
1 Office Tables 10 Nos. 10 Nos.
2 Office Chair 100 Nos. 100 Nos.
3 Computer Table + Chair 5 Nos. 5 Nos.
4 Steel Almirah 10 Nos. 10 Nos.
5 Bunk Beds 400 Nos. 400 Nos.
6 Mattresses “3” with leather cover 800 Nos. 800 Nos.
7 Quilt 800 Nos. 800 Nos.
8 Pillssows & Bed sheet 800 Nos. 800 Nos.
9 Curtains Lump sum Lump sum
50 | P a g e
Annex-F-2: WORK ORDER REVENUE COMPONENT ITEMS
51 | P a g e
52 | P a g e
53 | P a g e
54 | P a g e
55 | P a g e
©Directorate General of Evaluation and Evaluation (ISO: 9001/2015), Planning
and Development Board, Govt. of Punjab.
4th Floor, 65- Trade Centre Block, Ayub Chowk, Johar Town, Lahore
042-99233177-91, info@dgmepunjab.gov.pk
56 | P a g e